Professional Documents
Culture Documents
Ms Project
Ms Project
Project ..........................................................................................................................1
........................................................................................................................2
.........................................................................................................................2
..................................................................................................................2
..........................................................................................3
Project 2007 ............................................................................................4
File->New ....................................................................................6
..................................................................................................................7
(Calendar) ............................................................................7
Project 2007 .................................................................................................................9
...................................................................................................................................................12
............................................................13
(Task Name) ...................................................................................................................14
............................................................................................................14
......................................................................................................................16
(Link) ..............................................................................................................................16
Link Task.............................................................................................18
Lead Lag Time ................................................................................................................18
..........................................................................................................................20
(Summary Task) (Subtask) ................................................................................20
Task .................................................................................21
............................................................................23
...........................................................25
..............................................................................................................30
.........................................................................................................................................30
Microsoft Project
Microsoft Project Gantt Chart
Microsoft Project
Microsoft Project 2007
Project
()
(Milestone)
1.
2.
3.
4.
7
1.
2.
3.
4.
5.
6.
7.
Project 2007
(Task)
Project 2007
(Resource)
Project 2007
(Cost)
Project 2007
(Time)
Project 2007
Project 2007
Standard Toolbar
Undo
Finish to Start
Assign Resource
Gantt Chart
Formatting Toolbar
Assignment
0%
25%
Training Service (ICT Center)
50%
75%
100%
File->New
2
1. (Project Start Date)
2. (Project Finish Date)
Project > Project Information
(Calendar)
3
1. (standard)
08.00-12.00
13.00-17.00
2. 24 24 ..
3.
40 .. /
Project 2007
(View)
10
Gantt
Chart
Gantt Chart
Calendar
Diagram
11
Usage
Assignment
Sheet
Form
12
Resource Graph
Graph
Task Task
Task Details Form
Resource Resource
Resource Form
Microsoft Project
3
1.Calculated
Critical Yes
No
2.Entry
Predecessor Predecessor
3.Calculate & Entry
Start
Finish
Training Service (ICT Center)
13
1.
2.
3. Insert Column
14
(Project Information)
(Change working time)
(day) (week)
Entry Gantt
Chart
(Task Name)
Task Name Entry Gantt Chart
1. Task (Normal)
2. Summary Task
3. Sub Task v
4. Milestone
1. ProjectProject Information
2. Project Information
15
Task name
Duration
16
Schedule from
Project Start Date
Project Finish Date
Project Finish Date
(Link)
Link Tasks
17
4
1. (Finish-to-Start) FS
(Default) Project 2007
2. (Finish-to-Finish) FF
2
Layout
(Predecessor)
(Successor)
3. (Start-to-Start) SS
2
2
4. (Start-to-Finish) SF
Predecessor
Successor
Training Service (ICT Center)
18
Link Task
1.
2.
Link Task Project 2007
FS
Gantt Chart Project 2007
Task Dependency
From :
To :
Type:
19
Predecessor
Successor
Lag:
Lead Lag Time
Delete:
Lead Time
Lag Time
3. Type Finish-to-Start
Lead Time Lag Time
4. OK Lead Lag Time
Lead Time
Finish-to-Start
20
Lag Time
Finish-to-Start
1.
Unlink Task
2. Delete
Task Dependency
(Summary Task) (Subtask)
(Summary Task) (Subtask)
21
1.
2.
3.
4.
Task
Task
Tracking Toolbar
Project 2007 Tracking Toolbar
View > Toolbars > Tracking Tracking Toolbar
Tracking Toolbar
0%, 25%, 50%, 75% 100%
Task
1.
2. Tracking Toolbar
1. Task Update Gantt Chart
(%)
2. Progress
Task
Training Service (ICT Center)
22
1.
3. 2
3.1 % Complete
3.2 Actual dur
Actual
Current
Notes
Notes
23
Project 2007
1. Update
24
3. Update
Update word as complete through:
Set 0% - 100% Complete 0% - 100%
Set 0% or 100% Only 2 0%
100% Update work as complete
through 0%
100%
Entire project Update
Training Service (ICT Center)
Resource Sheet View bar
Resource Name >
Type >
Std. Rate >
Training Service (ICT Center)
25
26
Ovt.Rate>
Cost/Use>
Accrue At> 3
1. Start-
2. Prorated-
3. End-
Base Calendar >
Assign Resource
27
28
29
30
Report Reports
1. FilePrint
2. Print Range
3.
4.
5.
6. OK