HSE Monitoring Log sheet Mellitah Oil & Gas Wafa Field

Location: Slug Catcher Area


Plant Area : A-151

Date

Time

May
21
2010

1710h

May
22
2010

0815h

LEL
reading

Equipment description:
Raw Gas Line 30 inches

Visual inspection comments

Equipment tag number:


10-300-SDV008

Discharge flow
rate (per /sec)
condensate

The leaks come out to the bolt and nuts of the body
flange or closure of SDV. At the moment there are
three (3) leak points coming from the closure SDV
passing through the nuts. Minor whistling sound can
heard on the leaking point (1st point)
24%

First point 5 oclock position of SDV

3%

Second points 1 oclock of SDV

1%

Third points 7 oclock of SDV


The leaks come out to the bolt and nuts of the body
flange or closure of SDV. At the moment there are
three (3) leak points coming from the closure SDV
passing through the nuts.

Inspected by:
A. Tan

10 seconds per
drops
25 seconds per
drops
1 minute per
drops
The same
condition

Signature

Date

Time

LEL
reading

Visual inspection comments

Discharge flow
rate (per /sec)
condensate

Inspected
by:

1625h

35 %

First point 5 oclock position of SDV

A. Tan

4%

Second points 1 oclock of SDV

1%

Third points 7 oclock of SDV

1 second per
drop
18 seconds per
drops
1 minute per
drops

Note: HSE monitoring this leak every day (two times a day) from the morning and afternoon before refrain from duty.