Professional Documents
Culture Documents
Revision History
Document Title: Preliminary Outline Method Statement Intake
Structure
(Appendix 4.2 of Environmental Statement)
Revision
Date
Author
01
February 2012
Fairhurst Ltd
RES
North Blyth Renewable
Energy Plant
D/I/D/81354/101
February 2012
CONTROL SHEET
CLIENT:
RES
PROJECT TITLE:
REPORT TITLE:
PROJECT REFERENCE:
81354
Name
Signature
Date
DRAFT
Prepared by
A Lowes
Reviewed by
D Ladkin
Approved by
D Ladkin
Revision Record:
Issue
Date
Status
Description
25/07/11
Information
Minor Amendments
7/09/11
Information
Minor Amendments
2/02/12
Information
Minor Amendments
By
LT
Chk
AJL
App
AJL
This report has been prepared in accordance with procedure OP/P02 of Fairhursts
Quality Assurance System.
CONTENTS
1.0
INTRODUCTION ......................................................................................................... 1
2.0
3.0
4.0
5.0
6.0
7.0
APPENDIX A
DRAWINGS
1.0
INTRODUCTION
As part of the proposal to develop a Biomass Power Station at Battleship Wharf, Port
of Blyth, it will be necessary to construct a cooling water system with an intake
abstracting water from the River Blyth. The intake structure will be located to the rear
of the retaining wall, on the land-ward side of the existing Quay 4.
This preliminary outline method statement discusses the potential methods and
sequence of construction for this structure based upon outline design information
supplied by SKM, available geotechnical and hydrological information for the area and
constraints imposed by constructing the intake within an operational port.
This method statement has been prepared to discuss the technical procedures and
sequence of works for the installation of the intake structure. Health, safety and
environmental requirements, design and construction quality assurance procedures,
regulatory liaison and liaison with third parties are not included in this method
statement.
2.0
LOCATION OF WORKS
The preferred location for the intake structure is to the rear of the existing retaining wall
at the southern end of Quay 4 at Battleship Wharf. As the intake is on the landward
side of the existing cofferdam river wall no construction activity will take place within
the River Blyth Estuary, other than when the existing cofferdam and sheet pile river
wall are broken through for the installation of the header pipe work.
The intake structure will extend from the retaining wall to close to the south western
corner of the Bulk Shed 2. The area in which the intake structure will be located is
currently utilised as a hardstanding area with a circulation road running north south
through it. It is understood that the existing quay retaining wall is restrained by high
level ground anchors.
3.0
FORM OF STRUCTURE
The preliminary general arrangement of the intake structure is shown on sketch
drawing dated 9th February 2010, Appendix A. It will comprise a chambered reinforced
concrete structure with a reinforced concrete cover slab designed to allow the
trafficking or port vehicles and plant over it. The section of the structure that is nearest
to the river will consist of a settling chamber. The central section will contain a band
screen. The inland section will consist of a dry well pump chamber and a
manifold/valve pit. Water will be drawn into the intake via a transverse slotted pipe
intake suspended below the deck of Quay 4. The pipe will penetrate through the
existing retaining wall.
It is understood, from the information presented in the desk study provided in
Appendix 15.1 of the accompanying Environmental Statement, that the required
excavation depth for the construction of the intake is approximately -7.5mOD and that
the overall width of the structure will be approximately 9m.
4.0
Page 1
February 2012
Elevation
Description
+4.00m - +3.50m OD
5.0
Highest recorded
+3.61m OD
+2.44m OD
-1.88m OD
Lowest Recorded
-3.61m OD
TECHNICAL CONSTRAINTS
To construct the intake the following technical challenges must be considered in the
design of the temporary and permanent works and construction methodology.
6.0
1.
2.
Maintaining a dry working area adjacent to a river with a large tidal range which is
significantly above the proposed excavation depth.
3.
6.1
1.
2.
3.
Page 2
February 2012
sandstone would be strong enough to form a near vertical face, however, if mudstone
layers are encountered temporary shoring of the face using sprayed concrete may be
required.
On completion of the excavation the intake structure would be constructed. The
sequence of construction would require careful integration with the temporary works
design to ensure that when temporary props are removed the partially constructed
intake structure has sufficient stiffness to resist the lateral earth pressure loads
previously resisted by the props.
There are significant disadvantages with this form of cofferdam installed where the
bedrock horizon is higher than the base of the excavation:
6.2
It is difficult to waterproof sheet pile and combi walls and as such seepages
through the clutches and at the wall bedrock interface should be expected.
If mudstone layers are encountered the excavation face should be supported and
protected with sprayed concrete.
Unless the sheet piles or combi wall is designed to form part of the structure the
temporary works will have to be removed on completion of the structure
Seepages through the base the excavation can be controlled by sump pumping
and general groundwater lowering will not be required.
The reinforcement cages can easily be designed so that couplers project from the
face of the wall to allow the connection of the reinforcement for the transverse
walls without breaking out concrete.
The diaphragm wall will have a rough surface from being cast against the ground,
however this could easily be prepared, if required, to improve the hydraulic
performance of the structure.
Page 3
February 2012
6.3
There would be less likelihood of requiring the use of bentonite in the process.
Seepages through the base the excavation can be controlled by sump pumping
and general groundwater lowering will not be required.
6.4
The internal face of the wall will be a series of interlocking piles with a rough
surface as the concrete was cast against the ground. This may not deliver the
required hydraulic performance required for the structure and an internal nonstructural facing of concrete may be required.
7.0
SEQUENCE OF CONSTRUCTION
The sequence of construction outlined below is based upon the construction of the
intake within a cofferdam constructed from diaphragm walls. The schematic
arrangement of the works is shown on Drawings 81354/SK003 and 81354/SK005,
Appendix A.
1.
Agree with the Port of Blyth and implement a traffic management system to allow
port operations to continue around the work area.
2.
Carry out trial trenching to locate ground anchors restraining existing quay
retaining wall. Where anchors clash with location of intake, agree relocation of
anchors with Port of Blyth.
3.
4.
5.
February 2012
6.
After diaphragm walls have cured sufficiently, excavate to design formation level.
Install props as required by the temporary works design.
7.
Construct internal walls, remove props when required by the temporary works
design.
8.
9.
Break through riverward wall and install header pipework into wall. The
dimensions of the break through will be dictated by the mechanical design of the
cooling water system, however it is anticipated that a break through for a pipe 1
to 2m diameter will be required.
There is only a risk of construction materials / demolition arisings falling into the
intertidal mudflats during breaking through of the quay wall. Prior to this activity
taking place, netting will be erected to contain falling materials. The break
through will be designed so that saw cutting / coring through the wall will be
utilised to allow materials to be removed in sections rather than broken up in situ
using hydraulic breakers.
10.
The final timescale will be determined during detailed engineering design of the works,
though it is recommended that works on the wall and river side of the wall will be
undertaken during the summer months to avoid impacting upon over wintering birds.
Page 5
February 2012
APPENDIX A
DRAWINGS
February 2011
www.fairhurst.co.uk
Aberdeen
Birmingham
Bristol
Dundee
Edinburgh
Elgin
Glasgow
CIVIL ENGINEERING STRUCTURAL ENGINEERING TRANSPORTATION ROADS & BRIDGES
PORTS & HARBOURS GEOTECHNICAL & ENVIRONMENTAL ENGINEERING PLANNING &
Inverness
Leeds
London
Manchester
Newcastle upon Tyne
Sheffield
Watford
Wellesbourne