SCOPE OF WORK

DOOR REPAIR
LOCK INSTALLATION
ADDITIONAL WATER OULET FOR UTILITY
GROUT SEALING
PLASTERING
INST. OF HARDIFLEX
CLADDING
APPLICATION OF SKIMCOAT
SURFACE PREPARATION
PAINT RETOUCH

WORK QUANTITY
3
8
3
4
1
1
1.5
13.5
15
15

UNIT
unit
unit
unit
ln-m
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

RATE
15 MH/unit
3MH/unit
10MH/unit
0.4MH/ln-m
6MH/sq.m.
2MH/sq.m.
2.66MH/sq.m.
3MH/sq.m.
3.5MH/sq.m.
1MH/9 sq.m.

MANHOURS
27
24
30
1.6
6
2
3.99
40.5
52.5
1.67

MANDAYS
3.4
3.0
3.8
0.2
0.8
0.3
0.5
5.1
3.3
0.2

MANDAYS
4.0
3.0
4.0
1.0
1.0
5.0
4.0
1.0

SCHEDULE OF MANPOWER
1 H, 1 C
1H, 1C
1H, 1P
1H
1H,1M
1C,1H
1H,1C
1H,1M
2P
2P