UNSET AHC PKR BY CUT IN ITS MANDERL USING RCT

WELL:
RIG :
DATE :

SYRAH-8X
EDC-87
07/01/2014

TOP OF 7" AHC PKR @ 12330.58'


BTM OF 7" AHC PKR @ 12337.52'

BTM OF PKR TO BTM OF CUT ZONE = 11.77"


** IN THIS WELL WE SHOOTED RCT 4"
FROM BTM OF CUT ZONE

CUT ZONE
LENGTH=11.27"

TOP OF 7" AHC PKR @ 12330.58'

11.27"

TOP OF PKR TO BTM OF CUT ZONE =71.51"

LENGTH OF PKR FROM TOP TO BTM = 83.28"

CUT ZONE LENGTH=11.27"


LENGTH OF PKR FROM TOP TO BTM =83.28"

11.77" TOP OF PKR TO BTM OF CUT ZONE =71.51"

STOP CCL @ = 12336.21'- 13.875' =12322.33'

SHOOTING DEPTH =12336.21'

BTM OF 7" AHC PKR @ 12337.52'

Calculations:
** IN THIS WELL WE SHOOTED RCT 4" FROM BTM OF CUT ZONE.
** SHOOTING DEPTH = BTM OF PKR (12337.52') - BTM OF PKR TO
BTM OF CUT ZONE (11.77") - (4" FORM BTM OF CUT ZONE)
SHOOTING DEPTH = 12336.21
FT
CCL TO RCT NOZZLE OFFSET = 166.5" =13.875'
STOP CCL @ = 12336.21'- 13.875' =12322.33'

NOTE: BEFORE R/U E/L WE MADE UP 3 1/2" N.VAM TBG STRG UNDER TENSION W/147 KLB's
(STRG WT W/T.B: 112 KLB's & 35 KLB's OVER PULL).

**** TO RETREIVE GAS COMPLETION ON AHC PKR & 13 % CR TBG YOU HAVE TO HANDLE THE FOLLOWING ITEMS:
*** YOU HAVE TO ARRANGE WITH GAS PRODUCTION TO REMOVE THE GAS PROD. LINE, CONCRETE, AND CLEAR
LOCATION BEFORE RIG MOVE BY ENOUGH TIME.

CC L TO RCT NOZZLE
OFFSET = 166.5"

1- E/L TRUCK WITH RCT ( 2 OR 3 RUNS).


2- COMPLETION ENGINEER TO OPEN SCSSV.
3- SAFETY X/O'S ( YOU MUST HAVE SAFETY X/O FOR ALL THRESD CONNECTIONS IN THE GAS COMPL. , 4 1/2" & 3 1/2")
4- 40' x 1/4" CONTROL LINE TO CONNECT IT C/L CONNECTION IN THE TBG HGR & MAKE AS SPRING FOR N/U THE RIG BOP.
5- 4 1/2" N.VAM OR V.TOP LANDING JT DEPENDS ON THREAD OF TBG HGR ( DONT USE FULL TBG JT).
6- FITTING ( 1/4" NPT x 1/4" C/L (3 EA) , 1/2" NPT x 1/4" C/L (2 EA) , C/L x C/L UNION CONNECTION ( 4 EA).
7- 13 % CR HANDLING EQUIP. ( POWER TONG, RUBBER, WOOD, ECT)
8- HAND PUMP TO OPEN 4 1/16"-5K SOLID BLOCK TREE ACTUATOR.
9- 4 1/16"-5K FLANGE x 15O2 THREAD TO INSTALL IT ON THE S.BLOCK TREE WING VALVE.
10- 2 1/16" -10K FLANGE x 15O2 THREAD TO INSTALL IT ON THE T.H.S. 2 1/16"-10K VALVE IN CASE.
YOU NEED KILL THE WELL REVERSE OUT.
11- TBG PROTECTORS FOR THE STRG YOU ARE GOING TO RETREIVE IT.

Ali Sobhy Seddik


Khalda Petroleum Company
Drilling and Workover Rig Supervisor
Mob: - +2- 0100 267 1122
E-mail:- Ali.Seddik@khalda-eg.com
Ali.Seddik@ymail.com