You are on page 1of 7

DEEP SEA control DG and Commercial power

operation manual
1Checking first
Before installation and configuration to ATS, It should first
confirm that the ATS can control DG turn on and turn off by itself.
And also confirm the ATS can working under the automatic mode, If
not ,it should connect ZTE MS team to repair the ATS and DG in
order to the ATS can working normal.

2DEEP SEA ATS struction


This document only suitable for the DEEP SEA ATS to control DG
and commercial power by RMS

1) First open ATS panel, then find 12 interface and 16 interface in


the PCB board. Add two cables to 12 interface and 16 interface.

2) Find 12 interface, and add one cable to 12 interface. Named


cable 12.

3) Find 16 interface, and add one cable to 16 interface. Named


cable
16.

3 Cut off commercial power solution


1) Find the relay near F3 in the DEEP SEA cabinet:

2) Take out the NO.6 cable from the relay.

2) Connect the blue cable of AC CTR to the 6 interface of relay.


And also connect the cable that cable 16 get from ATS panel to 6
interface of relay.
3) Connect the black cable of AC CTR to the 6 cable that take
out from the relay . as the following picture

RMS-(AC CTR)
Blue cable
Black cable

contactor
Interface 6
NO.6 cable

4Control DG connection
1) First find the cable RMS DG Manual
2) Connect blue cable of DG Manual to NO 12 cable which get
form ATS panel.
3) Connect black cable of DG Manual to the 1 interface, as the
following picture.

DG manual connection
RMS-(DG manual)
Blue cable
Black cable

ATS
No.12 cable from ATS pannel
1 interface

5Take care of the DG model


After configuration and checking finished .Before leave the
site, make sure the DG are working under the automatic model.

You might also like