Professional Documents
Culture Documents
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
METHOD STATEMENT
INSTALLATION OF FENCE BRIDGES AND DROP STRUCTURES
Documents Attached
1 Method Statement
2 QCP/ITP
3 Risk Assessment
Signature
Approved
by:
Project
Manager
SA Fence & Gate
Approved
by:
Project
Manager
Kusile Power Station
Page 1 of 36
Date
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
INTRODUCTION
THE PURPOSE OF THIS DOCUMENT IS TO OUT LINE ALL THE WORK THAT SA
FENCE AND GATE WILL BE DOING DURING THE KUSILE PROJECT. THIS WILL
INCUDE ALL THE WORK PROCEDURES AND INSTRUCTION THAT ARE MADE BY
THE SHE AND KUSILE SPECIFICATIONS
SCOPE
THIS METHOD STATEMENT WILL APPLY TO THE INSTALATION OF BRIDGES AND
DROP STRUCTURES AS PER DRAWINGS SUPPLIED BY ESKOM KUSILE.
1.
2.
3.
4.
5.
6.
7.
8.
SITE ESTABLISHMENT
MATERIAL DELIVERY
DEFINITIONS,TERMS,ABBREVIATION
REFERENCES
RESPONSIBILITIES, AUTHORITY, ACCOUNTABILITY
STRIPPING AND STOCKPILLING AREAS
PLANT & TOOLS REQUIRED FOR THE ACTIVITY
EXCAVATION
8.1
Preparation for Excavations
8.1.1 Permission
8.1.2 Definitions (Excavations)
8.2
Layout of the area of construction
8.3
Excavation
8.4
Bedding
8.4.1
Levelling
8.4.2
Main Fill
8.4.3
Stockpiling of Surplus Material
9. CONCRETE WORKS
9.1
Definitions
9.2
Resources
9.3
Fixing of Reinforcing Steel
9.3.1
Cutting of Steel Reinforcement
9.3.2
Delivery and offloading of steel
9.3.3
Area of offloading
9.3.4
Fixing of Reinforcing Steel
9.4
Storage and transport on site of Reinforcing Steel
9.4.1
Area of storage
9.5
Placing and Fixing
9.5.1
Placing and Fixing
9.5.2 Corrective Action (if any)
9.6
Erection of Formwork
Page 2 of 36
9.6.1
9.6.2
9.6.3
9.6.4
9.6.5
9.6.6
9.6.7
9.6.8
10.
11.
12.
13.
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
14. ENVIRONMENTAL
14.1
Vegetation Clearing and Topsoil Removal
14.2
Noise
14.3
Dust
14.4
Emergency preparedness
14.5
Accidental leaks and spillages
14.6
Flora and Fauna
14.7
Ablution facilities
14.8
Solid waste management
14.9
Accommodation of traffic
14.10
Landscaping and Rehabilitation
14.11
Prevention of fire
14.12
Installation
Page 4 of 36
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
1. SITE ESTABLISHMENT
Site Establishment was executed as per approved method statement.
2. MATERIAL DELIVERY
All material delivered to Kusile site will be delivered to SA Fence and
Gate site lay down area. All material will be inspected and approved by
client before installation as per quality control procedures (refer to Risk
Assessment RA 003) and transported to site by LDV with a trailer.
3. DEFINITIONS, TERMS, ABBREVIATIONS
4. REFERENCES
PROJECT KUSILE POWER STATION STANDARDS ENVIROMENTAL
SPECIFICATION
ENVIROMENTAL MANAGEMENT PLAN
CONSTRUCTION REGULATION 2003
OCCUPATIONAL HEALTH AND SAFETY ACT, ACT NO 85 OF 1993
Page 5 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Extension leads
Grinder
Skill saw
Hilti Drill (sps)
Breaker electrical
Picks
Shovels
Rakes
Shuttering
Scaffolding
Electric welder
Reinforcement
Dumpy Level
Theodolite
Hammers (14 Pound, 4 Pound and carpenter hammer)
Page 7 of 36
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
8. EXCAVATION
8.1 Preparation for Excavations
8.1.1 Permission
Before any excavations starts, the contractor shall apply for permission
from the client (Eskom). Permission will be obtained by way of a permit to
excavate. It must be determined if any unknown services are present inside
the perimeter of the proposed excavation area. To do this the services of
expert detection equipment or personnel will be utilised and will be
included in the excavation permit.
8.1.2 Definitions (Excavations)
Excavation: The act of ground-breaking, digging and taking out of
earth; whether by hand or machine.
Bedding: The act of preparing earth with machines, to specified
standards, to ensure that the earth serves the desired purpose.
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Page 11 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
ACTIVITIES:
9.3 Fixing of Reinforcing Steel
9.3.1 Cutting of Steel Reinforcement
Steels will be cut using a portable grinder or pliers used by somebody with
experience and who has been inducted.
All waste generated from grinding of reinforcement shall be disposed of at
demarcated areas as indicated by client.
All cutting equipment complied with OHS act in terms of safe guarding.
Safety goggles shall be used at all times to protect employees eyes from
sparks or hazardous material entering eyes.
9.3.2 Delivery and offloading of steel
All reinforcing steel will be delivered to the site offices and then delivered
to site with a LDV. Offloading will take place under supervision and the
required plant will be used to ensure safe and effective offloading. The
steel will be tagged for easy identification. Steel will be measured and
verified during offloading to comply with the quality standards of the
Contractor and the Client. The steel certificate will also be verified and kept
on record at time of delivery.
9.3.3 Area of offloading
To ensure safe and effective offloading the delivery vehicle will be situated
as close as possible to the offloading or storage area. Offloading will take
place in such a manner to ensure that the movement of plant and people
in site is not obstructed. Correct rigging practise will be implemented and
followed at all times.
Care will be taken not to damage the steel or the delivery vehicle while
offloading.
Page 12 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
means of tying the elements together with binding wire, suitable clips or by
welding where necessary. All reinforcing steel fixed in place will be cleaned
of mud, oil, loose rust or any other substances prior to concrete being
placed. Offcuts generated during fixing and installation of reinforcing steel
will be collected and removed for disposal prior to concrete being poured.
Where spacer/cover blocks are necessary, they will be cut to the required
size and shape and they will be off the required material. The blocks will be
secured to ensure that the necessary clearance, cover and spacing are
achieved.
Laps, joints and splices will be as indicated on the drawings or as directed
by the Engineer.
Protruding bars that will be exposed to the elements for prolonged periods
of time will be protected against corrosion with end caps in place.
9.5.2 Corrective Action (if any)
Any material utilised incorrectly will be removed and replaced correctly.
Any material that has been contaminated will be removed and disposed of
in the correct manner.
9.6 Erection of Formwork
9.6.1 Delivery and offloading
All formwork and false work will be delivered to site by the approved
supplier/contractor. Offloading will take under supervision and by utilising
the necessary resources.
9.6.2 Area of offloading
To ensure safe and effective offloading the delivery vehicle will be situated
as close as possible to the offloading or storage area. Offloading will take
place in such a manner to ensure that the movement of plant and people
in site is not obstructed. Correct rigging practise will be implemented and
followed at all times.
Page 14 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Care will be taken not to damage the steel or the delivery vehicle while
offloading.
9.6.3 Outside Shuttering (Bottom slab - Bridges)
Start by setting out the outer layout of the bridge by chalking the outer
measurements (0.90/23490 rev 0; 0.90/25019 rev 0; 0.90/23491 rev 0;
0.90/23492 rev 0), then proceed to construct shuttering according to
layout.
Shuttering will be put in place, placed in line and stayed.
Shutter oil will be applied to shutters before the steel fixers commences
with work.
Steel fixers will then start with the bottom layer of steel which will be
placed on 50mm cover blocks.
Eskom will then inspect and after approval concrete will be placed by
concrete hands.
Concrete will be placed with shovels and concrete will be vibrated with a
drive unit with a 50mm poker.
Concrete will then be levelled and flouted.
After concrete has set, curing compound will be applied with a block
brush.
For full concrete specifications refer to clause 9.7 of this document.
9.6.4 Outside Shuttering (Drop Structures)
Start by setting out the outer layout of the drop structure by chalking
the outer measurements (Refer to drawings: K5406-027; K5406-034;
K5406-051; K5406-053), then proceed to construct shuttering according
to layout.
Shuttering will be put in place, placed in line and stayed.
Shutter oil will be applied with a block brush.
Steel fixers will then plait the steel horizontally and vertically.
Eskom will then inspect the work.
Concrete will then be poured with a crane or straight discharge.
Concrete will be vibrated with drive unit and 50 mm poker.
Page 15 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Walls
0.75
0.5
Slabs (propped)
Slab props
10
Page 17 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
9.7.2 Placing
The necessary approval for concrete placing will be obtained prior to
placing and the element that needs to be cast will be inspected
beforehand. All unwanted debris and material such as water and loose soil
will be removed from the element before concrete placing. 2 Hours after
mixing the concrete, it will be placed in its final position.
A slump test will be conducted on the batch of cement when it arrives on
site. The measured slump will be within the following limits:
For reinforced walls and slabs - 70mm +- 25mm (or otherwise specified)
For reinforced floors - between 80mm +- 25mm (or otherwise specified)
The slump test will be carried out in accordance with SABS method 862 and
shall be determined from the approved average slump of the approved
trial mix as per Kusile specifications for structural concrete doc 203 770 Rev
04, clause VA.G.5.5.1.2.
In order to achieve the required slump, no additional water will be added
to the mix. In order to ensure that the concrete can be placed in the
corners of the formwork and around the reinforcing without segregation,
the consistency of the concrete will be of such standard to achieve this,
without segregation of the mix or the bleeding of water.
The concrete will be placed vertically, where possible, to prevent
segregation of the mix or the displacement of the reinforcing. The
concrete will not be allowed to free fall a height exceeding 1.5m unless
approved by the Engineer. The concrete will be brought in in layers of
450mm thickness and will not be worked by means of a vibrator to flow
laterally, so as to prevent segregation.
The angle of the shoot (if one is used) will be controlled to prevent
segregation. Baffles will be used to control the rate of discharge of the
cement when using a shoot. If a pump is used it will be approved by the
Engineer.
Page 19 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
A vibrating poker will be used to compact the concrete and the poker will
be inserted into the concrete to ensure vibration takes place from the
lower layer into upper layer. Attention will be given to ensure over
vibration does not take place. Concrete placing will take place in
accordance with compaction equipment available.
Finishing will take place by floating a wood or steel float depending on the
required surface finish. Construction joints will only be permitted where
indicated on the drawings. In the case of a plant breakdown, an emergency
construction joint will be finished in a way that least impairs the durability,
appearance and functioning of the concrete element.
In the event of heavy or prolonged rainfall, no concrete will be placed.
9.7.2.1 Placing concrete in cold weather conditions
Note: Cold weather is defined as a period when, for more than three
consecutive days, the average daily temperature is less than 4.44C [ACI
306.1-90]. When cold weather conditions are anticipated to be present the
concrete suppliers will be contacted to take the necessary precautions for
mixing the concrete.
No concrete will be placed on frozen sub grade due to bulking and freeze
thaw. Frozen sub grade material will be thawed thoroughly using external
heat and insulation prior to concreting. All concrete placements will be
vibrated mechanically.
9.7.2.2 Placing concrete in hot weather conditions
Note: Where the air temperature is above 30C, the temperature of the
placed concrete should not exceed 30C. Hot weather conditions are
therefore considered to be temperatures that exceed 30C. When hot
weather conditions are anticipated to be present the concrete suppliers
will be contacted to take the necessary precautions for mixing the
concrete.
To ensure that the concrete is placed at the right temperature the
following precautions will be taken:
Page 20 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
To ensure that the concrete cures correctly in hot weather the following
precautions will be taken:
Shade netting will be installed over the formwork to get the
temperature down.
After concrete has been floated, curing compound will be applied to
prevent cracks.
Programme concreting for the cooler parts of the day (early
morning, late afternoon).
Cooling formwork with water spray can also be considered.
9.7.4. Monitoring of Temperature
Thermostats will be used to determine the temperature and care will be
taken to ensure the temperature of the concrete, from the time of
hardening is maintained at not less than 5C for cold weather and not more
than 30C for hot weather.
9.7.5 Testing
The tolerances set out in the specifications by Eskom will be adhered to at
all time. These tolerances will apply to the fixing of reinforcing steel,
erecting the formwork and concreting of elements. Any deviations from
these tolerances will be approved by the Engineer.
In order to determine and ensure that the concrete is of the required
strength, cube moulds will be made of the placed concrete. Samples will be
taken as follows: 6 cube moulds will be made for each days cast element
and for at least every 50m placed. Only one sample will be taken of a
batch and only after 3 batches of the same strength concrete has been
mixed, will another sample be taken, unless otherwise instructed. The first
set of 3 cubes will be tested at 7 days curing and the second 3 cubes at 28
days. This is in accordance with Kusile Specifications for structural
concrete, clause VA.G.7.1.2. Sufficient slump cones and cube moulds will
be provided to ensure the correct frequency of sampling. The crushing of
the cubes will be conducted at an approved laboratory. All tests will be in
accordance with project specifications.
Page 22 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
curing process is complete two coats of sealant will be applied with a paint
roller.
9.7.6.4 Curling
In the event of Curling appearing the following will be implemented to
rectify the problem:
Grinding and grouting will be typically used on slabs. At the elevated edges
and corners and under slab voids holes will be drilled and filled with grout.
After the grout hardens, the curled edges shall be ground to the desired
profile. After the voids under the slab are grouted, the curled are will be
repaired by saw cutting around the area to be patched, chipping out
concrete below the desired profile, and patching to the required elevation.
9.7.6.5 Fine Dust forming on the surface
In the event of Fine Dust appearing the following will be implemented to
rectify the problem:
A chemical floor hardener will be applied. In severe cases the method of
grinding and polishing the surface can be utilised.
9.7.6.6 Pop - Outs
In the event of Pop-Outs appearing the following will be implemented to
rectify the problem:
Pop-outs will be repaired by first cleaning the holes out with a broom or
shop vacuum and a drill will be used to remove any unstable material. Each
hole will be filled with concrete using a trowel. Patching concrete with a
bonding agent will be used. Larger holes will be cleaned and a chisel will be
used to remove any loose material. Concrete will then be poured over the
area and spread with a trowel and left to cure.
9.7.6.7 Flaking
In the event of Flaking the following will be implemented to rectify the
problem:
Page 24 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
A pressure washer will be used to clean the surface of the concrete. Any
depressions caused by the flaking will be filled with epoxy mortar; all cracks
will be repaired using mortar. An acid wash will be applied which will
roughen up the floor surface so the primer will stick. The primer will be
applied and spread with a broom and concrete will be applied while the
floor is still wet. The concrete finish will be spread with a sponge while a
trowel will be used to detail the edges. A trowel or broom will be used to
create a finish texture. The finish will be allowed to cure for 24 hours.
10. CONTROLS AND CHECKS
The QC will continually perform spot checks on all working sites to ensure
adherence to all Method Statements/Process Controls. Refer to ITP. Should
a non-conformance be noted, a Non Conformance Report will be
completed and handed to the applicable person. A Non Conformance
Report register will be kept.
11. CONSTRUCTION OF TEMPORARY DAMS
Prior to commencement of bridges and drop structures temporarily
retaining dam walls will be constructed to ensure dry working space.
Gabions filled with dump rock (2m x 1m x 1m) will be used to form the
temporarily structure. Fill obtained from fence excavations will be
imported and compacted in layers at inner side of gabion wall 4m wide.
USB Green DPM will be inserted between gabions and filling to ensure a
water tight construction. To ensure the natural flow of water when
experience heavy rainfall, two 160mm diameter drains / overflows will be
inserted 800mm from the top of the temporarily structure. Water pumps
will also be used to ensure that rising water levels is not affecting
construction of permanent work. Permission and approval from the
Engineer will be obtained before constructing the temporary dam walls.
12. QUALITY CONTROL AND ASSURANCE
All quality control will be executed by SA Fence and Gate in conjunction
with prescribed specifications of Eskom.
Page 25 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
A Quality control officer of SA Fence and Gate will liaise with Eskoms
quality department to ensure that all requirements are met.
13. HEALTH AND SAFETY
This method statement will apply to the clearing, excavating, compacting
and loading of material, waste management, casting concrete, plant
equipment and PPE to be worn on site when carrying out this tasks/works
by SA FENCE AND GATE.
13.1 Terms, Definitions, Abbreviations
QA/QC Means Quality Assurance / Quality control Officer.
PPE Means Personal Protective Equipment.
SO Means Safety Officer
OHSA Means Occupational Health and Safety Act
EO Means Environmental Officer.
Excavation works Means the making of any man made cavity, trench,
pit or depression formed by cutting, digging, or scooping.
MSDS MEANS Material Safety Data Sheet.
13.2 Responsibilities, Authority and Accountability SHEQ will ensure :
Tool box talks will be carried out at the beginning of each work day with
all employees prior to work commencing.
No employee will be allowed access within the excavation area while the
TLB/Excavators are busy working.
Adherence to the 3m rule is compulsory at all times
Protection around the excavations will be installed. A barrier fence of at
least 1m high and as close to the excavations as possible will be
installed. Warning signs are to be posted on these barriers/fences.
All employees and contractors involved in this activity are competent to
do so.
All employees and contractors are required to conduct this work
undergo a SHEQ induction.
Employees must ensure that they were their PPE at all times.
Page 26 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Page 27 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
13.3.3 Backfilling
During backfilling the following will apply, and be adhered to at all times: The Foreman will be present at all times.
The Foreman is accountable for all employees at all times, and must
therefore be fully aware of the number and work-area of employees.
Spotter in place to direct trucks to the backfilling area.
Spotters to wear full PPE including long sleeve reflective vest, 500mm x
500mm red flag and whistle.
All employees to be cleared from areas where mobile machinery is at
work.
Employees to adhere to the 3m rule from moving machinery.
Trucks not to be overloaded.
Employees are not allowed to stand closer than 1 meter from the edge
of an excavation, to prevent any collapse of the sides of the excavation.
Excavation to remain fully barricaded until backfilling is level.
Backfilling materials will be obtained from approved areas only.
Operators must adhere to demarcated roads. No travelling in veld or
protected areas.
Before trucks discharge backfill material, stop blocks to be applied to
vehicle.
All valve chamber covers will be securely installed & clearly marked.
13.3.4 Delivery and Offloading of Steel
The driver of the delivery vehicle must have a valid drivers licence in
order for him to be allowed on site. All delivery vehicles will be escorted
to the offloading site by a licenced SA Fence and Gate employee. The
delivery truck must be compliant in the sense of not being overloaded
and the load must also be secured on the truck or vehicle.
The appointed stacking and storage foreman will be present to ensure
that stacking and storage is done correctly. Communication of the safe
work procedure for stacking and storage of material (SWP 002) should
be done with employees before work commences.
Page 28 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Page 30 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Dust mask.
Ear plugs (when working in a noisy area).
All employees will be equipped with their PPE and no one shall be
on site without the above required PPE.
The PPE clothing is applicable to everyone coming on site.
13.6 First Aid, emergency equipment and procedure
We will ensure that persons at work receive prompt first aid treatment
in case of injuries or emergency.
We will provide first aid box or boxes at or near the work place which
shall be available and accessible.
No persons are allowed to carry on with their task in case an emergency
siren or alarm sound.
Report any incident/accident immediately to supervisor or safety
representative on site.
Every minor injury shall be treated on site by the competent first aider
as OHS act.
All people working on site will undergo induction, safety awareness
training and environmental training with regarding emergency
procedures, fire, or electrical shut down.
13.7 Housekeeping (on daily basis)
We shall continuously maintain and implement housekeeping on our
construction site to avoid injuries to persons on site, client, visitors
and or sub-contractors.
Everything in its place. No materials or hand tools will be lying on the
ground when not in use.
We shall store them safely in the toolbox on site.
All waste scrap produced on site shall be removed at appropriate
intervals to enhance a healthy and safe environment for persons
working on site.
No smoking or dumping on site shall be permitted unless it is a
demarcated smoking area to avoid cigarette butts on the ground.
Page 32 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
14. ENVIROMENTAL
14.1 Vegetation Clearing and Topsoil Removal
SA Fence and Gate shall ensure that the clearance of vegetation is strictly
restricted to the area required for the work (such as the fence will be
erected, toilets will be placed and access roads where vehicles and workers
will walk).
All cleared vegetation will either be mulched and mixed into the topsoil
or disposed at an approved disposal site.
All disposal of vegetation by burying or burning is prohibited.
Topsoil will be stripped which will include the top 150mm of the soil, for
subsequent use during rehabilitation and re-vegetation.
14.2 Noise
The contractor does envisaged that the project will generate excessive
noise (more than 85 dB), but instances whereby the equipment such drilling
machine will be used, the workers will be advised to wear ear plugs.
14.3 Dust
It will be suppressed according to the clients standard environmental
specification. Eskoms Environmental officer will issue a permit to SA Fence
and Gate for extraction of water to be used for dust suppression. A water
tanker shall be permanently available on site for the control of dust
generation, and SA Fence and Gate shall ensure that the sprays do not
generate excess run off. During high wind conditions, SA Fence and Gate
shall comply with the Engineers instructions regarding dust dumping
measures.
An appropriate number of water tankers shall be permanently available for
the control of dust generation, and the Contractor shall ensure that the
sprays do not generate excess run off. There shall be sufficient water
tankers of adequate capacity to enable the dampening of all working areas
and access/ haul roads. During high wind conditions, the Contractor shall
Page 33 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
II.
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
III.
IV.
V.
VI.
VII.
Page 35 of 36
Eskom Enterprise
Kusile Power station
Date: 2012/10/12
Pages: 36
Page 36 of 36