Memo

Date: 02/24/2010

To: Stu DʼZiura Smoot Construction

From: Dean Hutchison CORE

Project: Mt Pleasant Library

Project #: 08002

Copies: David Chenery CORE


Central file

The following is a narrative for the Architectural changes issued in Addendum 1 to the Issued
for Bid Set.

DRAWING REVISION

D3.03 Extent of DEMO changed, demo note 6 added, general note H removed,
general note J added.

D3.04 Extent of DEMO changed, demo note 6 added, general note H removed,
general note J added.

A3.03 Extent of new ceiling changed, rcp note 1 changed, general note D added,
typical detail markers for A8.65/4 and A8.65/5 added.

A3.04 Extent of new ceiling changed, rcp note 1 changed, general note D added,
typical detail markers for A8.65/4 and A8.65/5 added.

A8.65 Details 4 and 5 added.