2x660MW NTPC SOLAPUR STPP : UNIT # 1

PROTOCOL FOR AUX. COOLING WATER SKID FOUNDATION ELEVATIO

Protocol for ACW PUMP

Title

SLP/STG/TURB/U#1/ACWP/003

PLAN VIEW

A-Row Center line


Colume A4
2196(2198)

PUMP-A

PUMP-B

Elev. +0.192 (0.200) MT.

Elev. +0.165(0.200)MT

5600(5600)

5635(5635)

Colume B4

B-Row Center

NOTE: Drawing Values are in Bracket.


All Dimensions are in MM.

IVRCL

NTPC- CIVIL

NTPC-MECH

TPP : UNIT # 1

NDATION ELEVATION & POSITION


Date: 28.01.2015

Colume A5

8740(8740)

PUMP-C
Elev. +0.184(0.200)MT

5635(5635)

Colume B5

ABFPL

SHEL