Unless otherwise stated, all Performance Guarantees are:
- under steady state, normal operating conditions
- per the conditions as stated in the Design Basis - on a one (1) steam generator basis (steam generator / SCR / ESP); simultaneous operation of two (2) steam generators is required to enable testing of one (1) FGD
The Performance Guarantees will be demonstrated in a test, or series of tests, performed in
accordance with a testing protocol to be submitted by Supplier.
The Design of Lubrication System Shall Ensure Continuous Operation of Mill Bearings. Suitable Arrangement Shall Be Provided For Readily Determining The Oil Level in The Gear Boxes