Pass the export hose to Romic Tide from FSO Stbd quarter
Heave up the export hose pick up rope by Romic Tides mooring roller form Romic
Tide Port quarter
Romic Tide will secure the export hose by using the Tugger Winch
FSO to lower the deck crane hook attached with 10 Ton x 6 meter Web Sling
Romic Tide will connect the web sling into export hose pick up ring
As soon as pick up ring is connected to the deck crane FSO crane will start taking the
weight
FSO crew will pick up the rope (8 x 100 Meter) by hand on to FSO main deck
FSO will lift the export hose end on the Main deck and secure
Soon after completion of export hose end inspection call Romic Tide to transfer
export hose
Romic Tide will return alongside to position and pass pick up mooring line to Romic
Tide
FSO deck crane will lower the hose end into the sea
Pass pick up line to Romic Tide with hose end on Romic Tide deck near stern roller
Heave up the export hose pick up rope by Romic Tides mooring roller form Romic
Tide Port quarter
1
Romic Tide will secure the export hose by using the Tugger Winch
Once export hose is secured Romic tide crew will disconnect the web sling from pick
up ring
FSO deck crane will finally pass and clear from the export hose
Romic Tide will pay out pick up rope appropriate distance about 10 meter to 20
meter depending on the prevailing weather condition
Romic Tide will manoeuvring the vessel and turn around to FSO Stbd quarter
FSO crew will receive the pick-up line and relocate the export hose to FSO normal
stowage position at Stbd quarter