Professional Documents
Culture Documents
Alex Tajirian
Alex Tajirian
CAPITAL
BUDGETING
PROCESS
Alex Tajirian
9-2
1. INTRODUCTION
#
"
Capital:
"
Budget:
"
Capital Budget:
"
"
"
"
morevalue.com, 1997
Alex Tajirian
9-3
"
Upper management
M&As
Correct-sizing
Other
morevalue.com, 1997
Alex Tajirian
9-4
morevalue.com, 1997
Alex Tajirian
9-5
FINANCIAL MANAGEMENT
PROCESS
Given your
Line of Business
Type of Business
List Potential
Projects
Type of
Projects
Internal
Expansion
External
(M&A)
Divestitures
& Spin Offs
Capital Budgeting
Choose Viable
Projects
Capital Structure
Choose Appropriate
Financing
Short-term financial
Management
Choose Appropriate
Working capital
Dividend Policy
Optimal
Dividend policy
morevalue.com, 1997
Alex Tajirian
9-6
INVESTMENT
DECISION
morevalue.com, 1997
FINANCING
DECISION
Alex Tajirian
9-7
Capital
Budgeting
morevalue.com, 1997
Managerial &
Entrepreneurial
Skills
Alex Tajirian
9-8
A word of Caution
A manager needs to make a decision today (t=0) given
estimated/forecasted cash flows. Obviously there is no
guarantee that the decision would always turn out as
anticipated. However, what is important is that the manager
has to make the best decision at t=0 given all the relevant
information.
Independent:
Example:
#
Example:
9-9
2.3 TOOLS
3.1 Payback Period Method:
Criterion:
Investment
Initial cost
CF1
CF2
$10,000
$14,400
10,000
$10,000
2,400
morevalue.com, 1997
Alex Tajirian
9-10
'
CF2
%
1
(1%k)
j
n
'
t'1
' j
(1%k)
CF t
t
(1%k)
CFt
t'0
(1%k)t
% ...%
CF n
n
(1%k)
& I0
& I0
where,
CFt / Net cash flow (inflow - outflow) at time t
I0
/ Initial cost or investment outlays
k
/ cost of capital (financing)
/ required return reflecting risk of use of CFs
Note: CF0 / I0
morevalue.com, 1997
Alex Tajirian
9-11
Thus,
NPV measures the additional market value that
management expects the project to create (or destroy) if
it is undertaken.
NPV Criteria:
Since the objective of the manager is to maximize value, then for
Independent Projects :
Mutually Exclusive:
Note:
morevalue.com, 1997
Alex Tajirian
9-12
Investment
Initial cost
CF1
CF2
$10,000
$14,400
10,000
$10,000
2,400
Solution:
NPVA '
$14,400
NPVB '
10,000
(1%k)
(1%.1)
2,400
2
(1%.1)
morevalue.com, 1997
Alex Tajirian
9-13
morevalue.com, 1997
Alex Tajirian
9-14
NPV
# of shares outstanding
$1,901
' $1.901
1,000
If the project is adopted then the price of the stock should increase by
$1.90.
morevalue.com, 1997
Alex Tajirian
9-15
Motivation:
!
Internal in that it is a rate of return that depends on the CFs
of the project.
!
profit
investment
Periods
CF from project
-100
10
60
80
morevalue.com, 1997
Alex Tajirian
9-16
Definition of IRR :
CF1
(1 % IRR)
CF2
(1 % IRR)2
% ... %
CF N
(1 % IRR)N
Decision Rule:
9-17
CF($)
-100
300
Solution:
&100 %
Y
300
' 0
(1%IRR)
300
' 100
(1%IRR)
300&100
200
'
' 2 ' 200%
100
100
morevalue.com, 1997
Alex Tajirian
9-18
CF from project F
-100
10
60
80
IRRF = ?
morevalue.com, 1997
Alex Tajirian
9-19
Solution:
CF0 %
!
CF1
(1% IRR)
% ... %
(1% IRR)
' 0
10
60
80
%
< 0
%
2
3
(1% .19)
(1% .19)
(1% .19)
You have guessed a number too high. Try a smaller #, say IRR =
17%, thus
& 100 %
(1% IRR)
CFN
& 100 %
CF2
10
60
80
%
> 0
%
2
3
(1% .17)
(1% .17)
(1% .17)
morevalue.com, 1997
Alex Tajirian
9-20
morevalue.com, 1997
Alex Tajirian
9-21
Problem 2:
Problem 3:
morevalue.com, 1997
Alex Tajirian
9-22
% use of each
Tool
Primary method
NPV
21%
IRR
49
payback
19
AROR
Secondary method
NPV
24%
IRR
15
payback
35
AROR
19
t'1
Source:
Kim, Crick, and Kim, "Do executives Practice What Academics Preach?"
Management Accounting (November 1986), pp. 49-52.
morevalue.com, 1997
Alex Tajirian
9-23
percentage results are more intuitive than a $NPV; 50% return vs.
NPV = $500,000
<
<
morevalue.com, 1997
Alex Tajirian
9-24
3. SUMMARY
T
Payback Period
NPV
Independent Projects
Mutually exclusive
NPV =
IRR
# Criterion
Two equivalent ways to look at it
Break-even or ROI > cost of financing project
# Calculation
! Trial & error
! Calculator
morevalue.com, 1997
Alex Tajirian
9-25
4. QUESTIONS
I. True/Disagree-Explain
1.
According to the NPV criterion, you should choose all projects with NPV > 0.
2.
According to the IRR criterion, you should choose projects with IRR < cost of financing.
3.
Ignoring brokerage fees, purchasing a stock in an efficient market is a zero NPV transaction.
4.
5.
A NPV > 0 project might not be undertaken because of its high risk, despite the manager's
confidence in the accuracy of the CF estimates.
6.
7.
If buying stocks is a NPV = 0 transaction, then no one would profit from them as an investor's
profits would be zero.
II. Problems
1) Given:
Project S
Project L
Cost
$10,000
25,000
Annual Benefits
$4,000
8,000
# of years
14%
14%
Which of these mutually exclusive projects is better based on NPV and IRR?
morevalue.com, 1997
Alex Tajirian
9-26
ANSWERS TO QUESTIONS
I. Agree/Disagree-Explain
1.
Disagree. Only if the projects are independent. If they are mutually exclusive, then you
choose the one with the highest NPV.
2.
Disagree. If IRR < cost of financing, then the project would be losing money as it costs more
to finance than to break-even. Such a project will have NPV < 0.
3.
Agree. NPV = -market price + PV of dividends. Present value of a stock would be its Agree
worth--value. If you pay (market price) exactly its worth (PV of dividends), then NPV = 0.
4.
Agree. Analyzing flextime corresponds to analyzing its impact on a firm's CFs. However, in
practice it is difficult to obtain good estimates of the incremental CFs. Thus, if "flextime"
makes sense, then you would be undertaking a NPV > 0 project.
5.
Disagree. The risk of CFs is reflected in the cost of capital (k). Thus, the fact that you obtain
a NPV > 0, and assuming you did the correct calculation, the project should be accepted.
6.
Disagree. Only if it is re-investing revenue at a rate higher than the required rate of return.
A simple example would be a company borrowing to finance projects that are not profitable,
NPV <0. Thus, expansion does not necessarily translate into shareholder value creation.
7.
morevalue.com, 1997
Alex Tajirian
II. Problems
1)
Step 1
9-27
Step 2
Calculate NPV
NPVS = -10,000 + 4,000(PVIFA14%,5) = 3,732
NPVL = -25,000 + 8,000(PVIFA14%,5) = 2,465
Using IRR:
Since cost of capital for each = 14% < IRR. Y Accept S as it has a higher IRR.
Obviously, you should choose both if they were independent.
morevalue.com, 1997
Alex Tajirian
9-28
ELIMINATIONS
morevalue.com, 1997
Alex Tajirian
9-29
choose $107 as
PVATT '
$107
' 100.94 > $100 Y
(1 % .06)
PVATT '
1.06
300
' $172.7
Total NPVindependent
Case 2:
morevalue.com, 1997
Alex Tajirian
9-30
300
(1 % 4)
morevalue.com, 1997
Alex Tajirian
9-31
Obviously, in this case you are better off taking $100 from ATT. Thus,
NPV ' & 100 %
300
' & 100 % 267.8 ' 167.8 < NPVindependent
1% .12
morevalue.com, 1997
Alex Tajirian
9-32
% NPVGO
..................................................
Let RR' Retention Ratio Y D1 ' (1& RR)(EPS1)
(RR)(EPS1)(ROE)
k
ROE
. .
k
.......(( ( )
NPV1
k & g
p0 '
EPS1
k
NPV1
k & g
'
D1
k & g
b.
c.
d.
9-33
RR
Relative magnitudes of ROE and k; see equation (**) above.
Growth, (RR)(ROE), does not necessarily imply NPV _.
morevalue.com, 1997
Alex Tajirian
9-34
Observations:
#
Firms use cost of capital "hurdle rate" in NPV > 3 times cost of
capital ] firms invest only if price is substantially > LRAC
(Summers '87)
#
9-35
U.S. firms abandon project earlier than Japanese (TV, VCR, semiconductors)
Explanation:
Agree NPV = NPV + flexibility option
Sources of option value:
#
sunk costs in abandonment decision
!
Severance pay for workers (-)
!
scarp value (+) (Myers & Majd '85)
"
capital used is industry specific (eg. steel mills) Y Who
is going to buy machinery when entire industry is
suffering?!
"
lemon problem
"
stop and re-start needs additional costs (McDonald &
Siegel '85)
#
9-36
Remarks
!
If 400% (in above illustration) is the cost of borrowing, maybe
that is the Agree cost of financing.
!
If a project sounds "too good to be Agree," it probably is "too
good to be Agree."
!
Role of market in information processing vs. personal
borrowing market.
morevalue.com, 1997
Alex Tajirian