1. After a count of 12, a paint spray operation becomes off for 25 seconds. Write a ladder
program for same.
2. An alarm is to sound for 17 seconds after a machine is started to alert personnel in
the area that the machine has been started. The alarm goes on when the machine is
started. The alarm stays on for 17 seconds, even if the input is turned off during the
17 second timing period.
3. Explain the working and construction of Thermocouple?
4. Explain the construction and working of LVDT with neat diagram?
5. Explain the working of Rotameter with neat diagram?
6. Explain the method for PH Measurement?

Lovely Professional University


Class Test-II
Industrial Automation (ECE-361)
MM:30

Time allowed: 1 hour


Note: Attempt all questions. Each question has a weightage of 5 marks.

1. A motor and its lubrication pump motor are both running. Lubrication for
main motor bearings is required during motor coast-down. After the main motor
is shut-off, the lubricating pump remains on for a time corresponding to coastdown time (e.g. 10sec).
2. Write a ladder program for calculates the number of parts in 1hour.
3. Which material is made RTD made of? Explain the working of RTD and how we
will measure the resistance?
4. Explain the construction and working of Bourdon Tube with Neat diagram?
5. Explain how orifice plate is used to measure flow rate?
6. Explain any two different methods for level measurement?