You are on page 1of 7

Doc.

N: CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

PEDIDO N:
PO N

P0927048-SROP-OC-0003

DESCRIPCIN :
Description

Fin Fan Cooler

Referencia
Project
FECHA:
Date

CERRO DRAGON

29/07/15

REVISIN N:
Revision N

Hoja N:
Sheet N
0

FECHA:
Date

PROVEEDOR:
Vendor

GEA do Brasil Intercambiadores

LOCALIDAD :
Place

Franco da Rocha / SP / BR

SUBPROVEEDOR:

NA

LOCALIDAD :
Place

NA

13, November, 2015

DIRECCIN :
Address

Road SP345, km 43,5

Subvendor
FECHA DE VISITA:
Visit dated on
1.

DE

29/07/2015

SITUACION GENERAL / GENERAL STATUS

1.1 ASUNTO DE LA VISITA Y ASISTENTES / AIM OF VISIT AND ATTENDEES

Lidia Telles Contract Coordinator

1.2 AVANCE DEL PEDIDO / PURCHASE ORDER PROGRESS


FECHA DE ENTREGA
DELIVERY DATE
CONTRACTUAL
PROMETIDA
CONTRACTUAL
PROMISED

ITEM
ITEM
21PGA20AN001

PROGRESO
PROGRESS (%)

PLANIFICADO

10/02/2016

ACTUAL

PLANNED

CURRENT

INGENIERA

100%

80%

SUBPEDIDOS

100%

99%

ACOPIOS

100%

100%

FABRICACIN

17%

17%

ENSAYOS / PRUEBAS

0%

0%

ENTREGA

0%

0%

ENGINEERING
SUB-ORDERS
STORE-UP

MANUFACTURING
TESTING

DELIVERY

10/02/2016

ESPERADA
EXPECTED
10/02/2016

Indicar si el pedido cumple con el programa o est


retrasado (indicar las causas) / Indicate if the PO is
proceeding according to schedule or it is delayed
(delay reasons)

The only delay that was found is in the


documentation certification, but isnt impacting
the manufacturing process.

TOTAL
TOTAL

1.3 ESTADO DEL TALLER (INDICAR CARGA DE TRABAJO) / WORKSHOP STATUS (WORKLOAD TO BE INDICATED)

It was verified that GEA have a great demand from another client, ODEBRECHT. They have several air coolers in the
manufacturing process, and it is a concern. This concern was reported to Lidia, and she said that there will not be a
delay in the delivery of the SENER project.
1.4 CONCLUSIN DE LA VISITA / CONCLUSION OF VISIT

SENER Ingeniera y Sistemas, S.A. - Getxo 2015


La informacin facilitada en este documento es confidencial y de uso restringido, pudiendo ser utilizada, nica y exclusivamente, a los efectos objeto del
mismo. Queda terminantemente prohibida la modificacin, explotacin, reproduccin, comunicacin a terceros o distribucin de la totalidad o parte de los
contenidos del mismo sin el consentimiento expreso y por escrito de SENER Ingeniera y Sistemas, S.A. En ningn caso la no contestacin a la
correspondiente solicitud, podr ser entendida como autorizacin presunta para su utilizacin.

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client
2.

Sener Ingenieria y Sistemas, S.A

Referencia
Project

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

DE

ACCIONES A REALIZAR / ACTIONS TO BE TAKEN


- POR EL PROVEEDOR (BY SUPPLIER):

GEA must revise the drawing mentioned below and submit it for SENER certification.
GEA need to prepare the FIN FAN DRIVER ASSEMBLY drawing as soon as possible. They informed us that they will
issue this on 16-Nov-15.

Description

Document n#

Rev.

SCHEDULE
MONTHLY PROGRESS REPORT
HIDROSTATIC TEST PROCEDURE
PAINTING PROCEDURE
WELDING MAP
WELDING "WPS"
WELDING "PQR"
WELDER QUALIFICATION "WPQ"
JUNCTION BOX - TRAYS AND CABLES
WIRING
JUNCTION BOX - JUNCTION
JUNCTION BOX - CABLE LIST
QUALITY DOSSIER
DATA BOOK
TREATMENT THERMAL PLAN

CDR-S009-PL-0001
CDR-S009-PL-0002
CDR-S009-PR-0002
CDR-S009-PR-0003
CDR-S009-PR-0004
CDR-S009-PR-0005
CDR-S009-PR-0006
CDR-S009-PR-0007

0
B
B
0
B
B
B
B

CDR-S009-PE-0004
CDR-S009-PE-0005
CDR-S009-PE-0006
CDR-S009-VV-0002
CDR-S009-VV-0003
CDR-S009-PR-0008

0
0
0
A
A
B

POR SENER (BY SENER):


SENER needs to approve the documents issued by GEA.

3.

Description

Document n#

Rev.

DRAWING - GENERAL ARRANGEMENT + FUNDATION AND FORCES


DRAWING - PROJECT OF TRANSPORT/ASSEMBLY IN THE FIELD
THERMICAL DESIGN
MECHANICAL DESIGN
STRUCTURAL DESIGN CALCULATIONS
DATA SHEET EQUIPMENT
TEST AND INSPECTION PLAN
NDT PROCEDURE
MOTOR DATA SHEET
MOTOR -DIMENSIONAL DRAWING
MOTOR - TERMINAL BOX DRAWING DIMENSIONAL
MOTOR - CONNECTION SCHEME
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
DRAWING - FAN AND DRIVE ASSEMBLY

CDR-S009-PM-0001
CDR-S009-PM-0008
CDR-S009-MC-0001
CDR-S009-MC-0002
CDR-S009-MC-0003
CDR-S009-HD-0001
CDR-S009-PL-0003
CDR-S009-PR-0001
CDR-S009-HD-0004
CDR-S009-PE-0001
CDR-S009-PE-0002
CDR-S009-PE-0003
CDR-S009-MA-0001
CDR-S009-PM-0010

1
0
0
0
B
0
C
B
B
B
B
B
0
A

DOCUMENTACION / ENGINEERING AND DOCUMENTATION

PLANOS Y CLCULOS / DRAWINGS AND CALCULATIONS


GEA informs us that they have 11 drawings with the status VSC, which they mention below. The other drawings are
mentioned above in section 2 of this report.
3.1

Description

Document n#

Rev.

DOCUMENT LIST

CDR-S009-LW-0001

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

DRAWING - NAME PLATE


DRAWING - HEADERS
DRAWING - BUNDLE SIDE WALLS
DRAWING - FINNED TUBES
DRAWING - PLUG HEADERS
DRAWING - GASKET OF PLUG
SPARE PARTS LIST "START UP"
VIBRATION SWITCH - Data Sheet
FAN - Data Sheet
DRAWING - DIMENSIONAL FANS

Referencia
Project

CDR-S009-PM-0002
CDR-S009-PM-0003
CDR-S009-PM-0004
CDR-S009-PM-0005
CDR-S009-PM-0006
CDR-S009-PM-0007
CDR-S009-LT-0001
CDR-S009-HD-0002
CDR-S009-HD-0003
CDR-S009-PM-0009

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

DE

0
0
1
0
0
0
0
0
0
0

3.2

PROGRAMA DE FABRICACIN / MANUFACTURING PLANNING


GEA provide the new revision of the schedule, and this schedule is attached to this report. Below are mentioned
some manufacture points.
Cutting process finished on 09/11/2015
Bevel machining Conclusion schedule 18/11/2015
Shop and weld - Conclusion schedule 02/12/2015
Heat Treatment - Conclusion schedule 09/12/2015
Machining - Conclusion schedule 18/12/2015
Piping Finned process 08/12/2015
Bundle assembly 28/12/2015
Bundle H.T. 31/12/2015
Structural assembly 08/01/2016
Drive test 11/01/2016
Painting 14/01/2016
Packing 18/01/2016
3.3

PROGRAMA DE PUNTOS DE INSPECCIN (PPI) / INSPECTION AND TEST PLAN (ITP)


The ITP was approved with comments. GEA has revised the IPT n# CDR-S009-PL-0003 rev. C. and submitted it to
SENER for approval on 11-Nov-15. Awaiting return.
3.4

DOSSIER DE SOLDADURA / WELDING DOSSIER


GEA informed us that they are revising the WPS/PQR according to the comments issued by SENER.
The WPS/PQR n# CDR-S009-PR-0005 rev. B and CDR-S009-PR-0006 rev. B
Welding Map is CDR-S009-PR-0004 rev. B

3.5

PROCEDIMIENTOS DE FABRICACIN Y PRUEBAS / MANUFACTURING & TESTS PROCEDURES


GEA revised the NDT procedure n# CDR-S009-PR-0001 rev. B and submitted it to SENER for approval on 11-Nov-15.
The Hydrostatic Test procedure n# CDR-S009-PR-0002 rev. B, GEA informs us that they are revising the procedure to
meet the comments issued by SENER and will submit on 16-Nov-15 for certification of the document.

4.

SUBPEDIDOS Y ACOPIOS / SUB-ORDERS AND STORE UP STATUS


MATERIAL
MATERIAL

SUBPROVEEDOR
SUBVENDOR

PEDIDO
P.O.
NMERO
FECHA
NUMBER
DATE

FECHA ENTREGA
DELIVERY DATE
CONTRACTUAL
ACTUAL
CONTRACTUAL
CURRENT

Plates

Paulifer

846039541

30/09/15

27/10/15

27/10/15

Piping

BTL

845063312

20/08/15

24/09/15

24/09/15

Piping

Mercotubos

845064020

21/10/15

10/11/15

09/11/15

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

OBSERVACIONES
REMARKS
Material delivery
Material delivery
Material delivery

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

Referencia
Project

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

DE

Material delivery

Fitting

Ruspristeel

845063930

13/10/15

10/11/15

10/11/15

Fitting

HCI

845063836

05/10/15

13/11/15

13/11/15

Motor

WEG

845063441

02/09/15

23/12/15

23/12/15

Ventilador

Cofimco

845063440

02/09/15

10/12/15

10/12/15

Bundle side wall

WAM

845064133

29/10/15

09/12/15

09/12/15

Structural
Material

WAN

Junction Box

PSS Solutions

845063763

05/10/15

18/12/15

18/12/15

Drive components

Superlyne

845063894

09/10/15

09/12/15

09/12/15

Plug fitting

STAMPINOX

845063526

09/09/15

17/11/15

17/11/15

Bushing

RO-PECAS

846039586

07/10/15

09/12/15

09/12/15

Paint

AkzoNobel

845064206

05/11/15

25/11/15

25/11/15

5.

Expected arrive
Isnt release for WEG
manufacturing yet
Customs clearence

Wanst issue the PO


but will be issue on
16/11/15

15/12/15

FABRICACIN / MANUFACTURING

SITUACIN DE LA FABRICACIN / MANUFACTURING STATUS


The cutting process has been started. GEA cut the plates for manufacturing the bundle heads. The cut plates are in
the machining process for bevel preparation.

5.1

5.2

FECHA PREVISTA Y LUGAR DE PRUEBAS / PLANNED DATE AND LOCATION FOR TESTS
The tests will occur in GEA facilities. They are able to perform the tests there.
For the hydrostatic test GEA are expecting to start the test on 29-Dec-2015.
For the drive test, they are expecting to start the test on 11-Jan-2016.
As they are at the start of the manufacturing process, it isnt possible to evaluate if the GEA schedule may be
delayed.

6. INSPECCIN

/ INSPECTION

6.1.

RESUMEN DE LA INSPECCIN REALIZADA / SUMMARY OF PERFORMED INSPECTION


No inspections have occurred at this vendor.

6.2.

ESTADO DE NO CONFORMIDADES / NON CONFORMANCE STATUS


There have been no non-conformances.

7. ENTREGAS / DELIVERIES
GEA maintain the delivery of the 3 bays and 6 bundles of Fin Fan Cooler TAG 21PGA20AN001 for 10-Feb-2016.

8. OBSERVACIONES

/ REMARKS

As mentioned above there is a concern that there is another project that has an earlier delivery date than the
SENER project. This concern was mentioned to GEA and they inform us that everything is on schedule, and their
only concern is if delays occur with their sub vendors. GEA informs us that they are monitoring the sub vendors and
they will inform us if a delay occurs with the delivery.
During the visit, it was possible to evaluate the GEAs facilities as shown in the photos below. They are able to
supply and have the equipment to manufacture the Fin Fan Cooler. It is believed that they have the organization to
comply with the schedule. The dates set out on the manufacturing plan are too tight and dont allow for delays
during the process.

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

Referencia
Project

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

DE

GEA did not foresee an inspection during this visit, therefore it was not possible to perform an inspection on raw
material available at the GEA factory. It was suggested to GEA to issue an inspection notification for checking the
raw material available.
9.

ADJUNTOS

/ ATTACHMENTS

Documents List
Sub-orders
Manufacturing Planning

10. FOTOS / PHOTOS

Photo 1 Cut plates for heads

Photo 2 Plates for heads waiting for bevel preparation

Photo 3 Shop for heads assembly

Photo 4 Shop for weld heads, SAW machine

Photo 5 Shop for bevel preparation

Photo 6 GEA facilities, machining shop

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

Referencia
Project

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

DE

Photo 7 Aluminium tapes for finned process.

Photo 8 Flanges waiting the assembly of the heads.

Photo 9 Pipes for bundle

Photo 10 Pipes identification

Photo 11 Finned process shop.

Photo 12 Other fan cooler in final assembly for tests

Photo 13 Bundle assembly shop

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

INFORME DE SEGUIMIENTO
EXPEDITING REPORT
Cliente :
Client

Sener Ingenieria y Sistemas, S.A

Referencia
Project

INSPECTOR:
Inspector
FECHA:
Date

SENER Ingeniera y Sistemas, S.A. - Getxo 2015

Doc. N:
CDR-SROI-IN-01OC
Rev.:
00
Fecha/Date:
13-11-15

CERRO DRAGON

Hoja N:
Sheet N

Marcelo Pires

13/11/2015

FIRMA:
Signature

DE

You might also like