TRANSMISSION
SYSTEM PLANNING
1.1 INTRODUCTION
An electrical power system can be considered to consist of a generation
system, a transmission system, a subtransmission system, and a distribution
system. In general, the generation and transmission systems are referred to
as bulk power supply, and the subtransmission and distribution systems are
considered to be the final means to transfer the electric power to the
ultimate customer. Bulk power transmission is made of a high-voltage
network, generally 138-765 kV alternating current, designed to interconnect
TABLE 1.1 Standard System Voltages
Rating
Nominal (kV) Maximum (kV)
34.5 36.5
46 48.3
69 72.5
us 1
138 145
161 169
230 242
345 362
500 550
700 765
1.2 PRESENT TRANSMISSION-SYSTEM-PLANNING
TECHNIQUES
As aforementioned, the purpose of transmission system planning is to
determine the timing and type of new transmission facilities required in
order to provide adequate transmission network capability to cope with the
future generating capacity additions and load-flow requirements. Figure 1.3Lod
forecast
‘Good
system
performance
(teadystate)
Feedback
Feedback
Design
new system
configuration
Planning,
decision
Total
cost
acceptable
15-20 year
expansion
pian complete
Figure 1.3, Block diagram of typical transmission system planning process.
Figure 1.3, Block diagram of typical transmission system planning process.shows a functional block diagram of a typical transmission-system-planning
Process. This process may be repeated, with diminishing detail, for each
year of a long-range (15-20-year) planning horizon. The key objective is to
minimize the long-range capital and operating costs involved in providing an
adequate level of system reliability, with due consideration of environmental
and other relevant issues. Transmission planning may include not only
existing but also new service areas. The starting point of the planning
Procedure is to develop load forecasts in terms of annual peak demand for
the entire system, as well as for each region and each major present and
future substation, and then finding specific alternatives that satisfy the new
load conditions. The system performance is tested under steady-state and
contingency conditions.
‘The logic diagram for transmission expansion study is shown in Figure
1.4. The main objective is to identify the potential problems, in terms of
unacceptable voltage conditions, overloading of facilities, decreasing re-
liability, or any failure of the transmission system to meet performance
criteria. After this analysis stage, the planner develops alternative plans or
scenarios that not only will prevent the foreseen problems but also will best
meet the long-term objectives of system reliability and economy.
After determining the best system configuration from load-flow studies,
the planner studies the system behavior under fault conditions. The main
objectives of short-circuit studies can be expressed as (1) to determine the
current-interrupting capacity of the circuit breaker so that the faulted
equipment can be disconnected successfully, therefore clearing the fault
from the system, and (2) to establish the relay requirements and settings to
detect the fault and cause the circuit breaker to operate when the current
flowing through it exceeds the maximum allowable current. The short-circuit
studies can also be used to (1) calculate voltages during faulted conditions
that affect insulation coordination and lightning arrester applications; (2)
design the grounding systems, and (3) determine the clectromechanical
forces affecting the facilities of the system.
Finally, the planner performs stability studies in order to be sure that the
system will remain stable following a severe fault or disturbance. Here, the
Stability analysis is defincd ay the transient behavior of the power system
following a disturbance, It can be classified as transient stability analysis.
The transient stability is defined as the ability of the system to maintain* Future load forecast
* Future generation
expansion plans
* Present network
Load-fiow siugy
* Conside: all generation and load patterns
* Pick out new lines
“ Comect low voltages and overloads with
new sources and circuit acditions
Shorea oa Satya |
fav pape ret Ayn grt
Sata asiyer
“ut contet Sat
Both fault
and stability
studies
satisfactory
‘Add all additions
te the network
Figure 1.4. Logic diagram for transmission expansion study.1.5 TRANSMISSION SYSTEM EXPANSION PLANNING
Today, the system planner, as mentioned in Section 1.2, mostly uses tools
such as load-flow, stability, and short-circuit programs in analyzing the
performance of specific transmission system alternatives. However, some
utilities also employ the use of so-called automatic expansion models to
determine the optimum system. Here, the optimality claim is in the mathe-
matical sense; that is, the optimum system is the one that minimizes an
objective function (performance function) subject to restrictions. In general,
the automatic expansion models can be classified into three basic groups:
1. Heuristic models.
2. Single-stage optimization models.
3. Time-phased optimization models.
1.5.1 Heuristic Models
‘The primary advantage of the heuristic models is interactive planning; that
is, the system planner can observe the expansion process and direct its
direction as it is desired. According to Meckiff et al. [4], the characteristics
of the heuristic models are (1) simple model and logic, (2) user interaction,
and (3) families of feasible, near optimal plans, Whereas the characteristics
of the mathematical programming models are (1) no user interaction, (2)
fixed model by program formulation, (3) detailed logic or restriction set
definition, and (4) single “global” solution. The heuristic models can be
considered to be custom-made, contrary to mathematical models. Some help
to simulate the way a system planner employs analytical tools such as
load-flow programs [5, 6] and reliability analysis [6] involving simulations of
the planning process through automated design logic. The classical paper by
Garver [7] describes a method that unites heuristic logic for circuit selection
with optimization techniques. The proposed method is to determine the
most direct route transmission network from the generation to load without
causing any circuit overloads, In heuristic approach, the best circuit addition
or exchange is given to the planner by the computer program automatically
at each stage of the synthesis process. The planner may select to accept it or
modify it as he desires. Further information on heuristic models is given in
Baldwin et al. [8-11].
1.5.2 Single-Stage Optimization Models
‘The single-stage or single-state (or so-called static) optimization models can
be used for determining the optimum network expansion from one stage to
the next. But they do not give the timing of the expansion. Therefore, even
though they provide an optimum solution for year-by-year expansion, theymay not give the optimum solution for overall expansion pattern over a time
horizon. The mathematical programming techniques used in single-state
optimization models include (1) linear programming, (2) integer program-
ming, and (3) gradient scarch method.
Linear Programming
Linear programming (LP) is a mathematical technique that can be used to
minimize or maximize a given lincar function, called the objective function
in which the variables are subject to linear constraints. The objective
function takes the linear form
z= Dex, (ay
where Z is the valuc to be optimized. (In expansion studies, Z is the total
cost that is to be minimized.) The x, represents n unknown quantities, and
the c, are the costs associated with one unit of x,. The c, may be positive or
negative, whereas the x, must be defined in a manner as to assume only
positive values. The constraints, or restrictions, arc limitations on the values
that the unknowns may assume and must be a linear combination of the
unknowns. The constraints assume the form
Lex,
x20 (2)
Gradient Search Method
The gradient search method is « nonlinear mathematical programming
applicable to so-called automated transmission system planning. Here, the
objective function that is to be minimized is a performance index of the
given transmission network. The method starts with a de load-flow solution
for the initial transmission network and future load and generation fore-
casts. The system performance index is calculated and the necessary circuit
modifications are made employing the partial derivatives of the perlormance
index with respect to circuit admittances. Again, a dc load-flow solution is
obiained, and the procedure is repeated as many times as necessary until a
network state is achieved for which no further decrease in the performance
index can be obtained. The method proposed by Fisch! and Puntel [23]
applies Tellegen’s theorem. The gradient information necessary to update
the susceptances i
sociated with effective line additions as aforementioned
was implemented. More detailed information can also be found in Puntel et
al. [24,25]1.6 TRANSMISSION SYSTEM PLANNING IN THE FUTURE’
In the previous sections, some of the past and present techniques used by
the system planning engineers of the utility industry performing transmission
systems planning have been discussed. Also, the factors affecting the
transmission system planning have been reviewed. The purpose of this
section is to examine what today’s trends are likely to bring for the future of
the planning process.
There are several economic factors that will have significant effects on
transmission system planning in the 1980s. The first of these is inflation.
Fueled by energy shortages, energy source conversion costs, environmental
concerns, and large government deficits, inflation will continue to play a
major role, The second important economic factor will be the increasing
expense of acquiring capital. As long as inflation continues to decrease the
1.6.1 New Planning Tools
Tools to be considered fall into two categories: network design tools and
network analysis tools. The analysis tools may become more efficient but are
not expected to undergo any major changes, although the environment in
18 TRANSMISSION SYSTEM PLANNING
which they are used will change significantly. This’ environment will be
discussed in the next section.
‘The design tools, however, are expected to show the greatest develop-
ment since better planning could have a significant impact on the utility
industry. The results of this development will show the following charac-
teristics:
1. Network design will be optimized with respect to many criteria using
programming methods of operations research.
2, Network design will be only one facet of transmission system manage-
ment directed by human engineers using a computer system designed
for such management functions,
3. So-called network editors [32] will be available for designing trial
networks; these designs in digital form will be passed to extensive
simulation programs that will determine if the proposcd network
satisfies performance and load growth criteria.1.6.5 Summary
Future transmission systems will be more complex than those of today. This
‘means that the distribution system planner’s task will be more complex. If
the systems being planned are to be optimal with respect to construction
ization, performance, and operating efficiency, beter planning
While it is impossible to foresee all of the effects that technology will
have on the way in which transmission system planning will be done, it is
possible to identify the major forces beginning to institute a change in the
methodology and extrapolate
‘The most important single influence is that of the computer, which will
permit the automating of more and more of the planning activity. The
automation will proceed along two major avenues. First, increased applica-
tion of operations research techniques will be made to meet performance
requirements in the most economical way. Second, improvements in data
base technology will permit the planner to utilize far more information in an
automatic way than has been possible in the recent past. Interactive
computer systems will display network configurations, cost information,
device ratings, etc., at the whim of the planner. Moreover, this information
will be available to sophisticated planning programs that will modify the
data base as new systems are designed and old ones are modified.
Planning
decision
15-20 year
expansion
plan eamplete
Figure 1.6. Schematic view of transmission planning system.