TIME MANAGEMENT
& SCHEDULING
INCLD PROGRESS REPORTING

K Builders Training & Consulting

1 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

COURSE DESCRIPTION :
This learning package enables trainees to acquire
knowledge and develop skill on planning and scheduling.
At the end of the learning package, the trainees will be
able to :
Analyse Contract Document
Study project scope of work
Review method statement
Produce civil and structural work programme and targeted

schedule
Submit civil and structural work programme and targeted
schedule

K Builders Training & Consulting

2 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

COURSE OBJECTIVE ( TPO ) :


Prepare civil and structural engineering work
programme using Contract Document, Construction
Drawings,
Method
Statement,
Master
Work
Programme,
Technical
Brochures,
Material
Specification, Code of Practice, Project Organisation
Structure and Relevant Computer Softwares so that
Contract Document analysed, project scope of work
studied, method statement reviewed, civil and
structural work programme and target schedule
produced and submitted.

PENYEDIAAN PROGRAM KERJA (WORKS


PROGRAMME)
PENGENALAN
Bidang perancangan untuk sesuatu projek pembinaan

adalah satu pekerjaan khas bagi seorang perancang


kerana ianya merangkumi satu aspek yang luas.
Lantaran itu, ia amat penting difahami serta diketahui
oleh setiap personel tapak agar kerja-kerja
perancangan ini adalah berterusan sehingga sesebuah
projek itu disiap sepenuhnya

K Builders Training & Consulting

3 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

WORK PROGRAMME
Merupakan satu jadual perancangan pelaksanaan kerja dalam satu

tempoh yang ditetapkan.


Penyusunan aktiviti kerja mengikut keutamaan dan bergantung
diantara satu sama lain di mana menyebabkan sesuatu aktiviti kerja
hanya akan dapat bermula apabila aktiviti kerja sebelumnya
disiapkan.
Carta bar biasanya digunakan bagi mewakili aktiviti kerja dan
mengandungi maklumat seperti tarikh mula/siap sesuatuaktiviti.
Mempunyai aktiviti kerja dalam laluan genting yang akan
mempengaruhi tempoh penyiapan keseluruhan projek.
Sebagai panduan perolehan sumber binaan seperti buruh, peralatan
dan bahan, serta kuantiti, tarikh tempahan dan hantaran.

KONSEP PERANCANGAN
Perancangan ialah aktiviti yang dilakukan melalui perbincangan,

perundingan dan pengiraan untuk membuat persediaan yang


lengkap mengenai tindakan-tindakan yang akan diambil untuk
mencapai matlamat-matlamat pembinaan dan pembangunan.
Perancangan adalah asas kepada tindakan untuk suatu projek dan
program kerja kerana kerja-kerja pembinaan adalah proses yang
mungkin berterusan dan serupa maka sewajarlah perancangan
dijadikan sebahagian daripada proses tersebut, maka program kerja
dan perancangan masa boleh dianggap sebagai satu proses yang
bersepadu.

K Builders Training & Consulting

4 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

PERINGKAT-PERINGKAT
PERANCANGAN
Peringkat pertimbangkan, mengenal pasti, merancang, menilai

dan mereka bentuk sebelum ianya dilaksanakan.


Peringkat pentadbiran yang merangkumi amalan tentang :
Kaedah-kaedah dalam pembinaan
Susunan dan jangkamasa operasi sesuatu aktiviti.
Kuantiti bahan, bilangan dan jenis pekerja (mahir atau

separuh mahir) dan peralatan jentera yang diperlukan.

PERINGKAT-PERINGKAT PERANCANGAN (SAMB.)

Perancangan diperlukan adalah atas sebab-sebab berikut :


Kesukaran untuk mendapatkan pekerja dimana ianya akan
melibatkan undang-undang pekerja dan kaedah pengambilan
pekerja.
Keperluan pekerja menggunakan peralatan-peralatan
pembinaan yang selalunya mahal secara ekonomi.
Untuk mendapatkan bahan yang sukar diperolehi dan mahal
memerlukan masa yang panjang.

K Builders Training & Consulting

5 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

PERTIMBANGKAN SEMASA
MEMBUAT PERANCANG
Keadaan tapak bina, yang melibatkan pengankutan

serta sekitar kawasan cadangan binaan dan cuaca.


Teknik, iaitu dari segi pembekalan dan penggunaan
bahan-bahan binaan dan jentera serta kemahiran
pekerja.
Magnitud projek yang merangkumi jumlah tingkat,
keluasan bangunan, jenis binaan, bahan dan kemasan.

K Builders Training & Consulting

6 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

14
K Builders Training & Consulting

7 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Activity

Responsibility
Start

Project Manager

Identify milestones, time frames and activities.


Define activity sequence

Compute constraints between activities and


create construction works programme as per
work instruction

Project Manager

For all activities, note awarding and


mobilization time need in the procurement of
relevant sub-contractor /supplier

Project Manager

Prepare the Resource Schedule as per work


instruction, where required

Project Manager

Prepare the Procurement Schedule as per


work instruction

Verify & sign the following documents:


Construction works programme
Resource Schedule
Procurement schedule

K Builders Training & Consulting

Area Contracts
Manager
A
Project Manager

8 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Activity

Responsibility
A
Where required, submit construction
Works programme to client for
approval

Project Manager
Revise Construction
Works Programme
as per Clients
requirements

Does Client
approve
Construction
Works
Programme

Project Manager

No
Project Manager

Yes
Maintain Construction works programme as a
controlled document with relevant Revision No.,
Issue No., and Effective Date pass one copy to client,
copies to relevant consultants and other parties, and
maintain one copy at site

Project Manager

End

Contract Document

K Builders Training & Consulting

9 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Contract Document

CONTRACT
DOCUMENT
SCOPE OF WORKS
(Base on Case Study)
SLOT BUNKER SUPPORT STRUCTURE
REPAIR WORKS

K Builders Training & Consulting

10 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Contract Document

Contract Document

K Builders Training & Consulting

11 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Contract Document

K Builders Training & Consulting

12 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Spesifikasi
Keterangan & huraian mengenai kualiti bahan & kerja serta kaedah
pembinaan .
Sebahagian daripada Dokumen Tender / Dokumen Kontrak.
Terdapat di dalam lukisan & Senarai Bahan yang menerangkan sesuatu
kerja yang tidak dapat dilukis.
Terbahagi kepad 2 kategori ;
Spesifikasi Am - asas bagi semua kategori kerja pembinaan.
Spesifikasi Tambahan - memperincikan secara khusus atas
Spesikasi Am & disediakan oleh Perunding atau Pengilang.
Spesifikasi Tambahan dan Spesifikasi dalam Lukisan Pembinaan
mendahului Spesifikasi Am.
Keterangan spesifikasi hendaklah seragam. Sebarang percanggahan , kontraktor
bertanggungjawab merujuk dan mendapat pengesahan daripada pihak Pemilik
atau Perunding.

K Builders Training & Consulting

13 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

14 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

15 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Detail Design & Structure Drawing


All replacement member specification as of KEVs Drawing

Part of reference drawing for the repair works

K Builders Training & Consulting

16 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

METHOD STATEMENT (MS)


Gambarajah turutan kerja (squence diagram)
Jentera yang diperlukan
Bilangan pekerja yang diperlukan dan tahap produktivi mereka dalam bidang

berkenaan.
Bahan binaan yang diperlukan serta kuantitinya yang boleh didapati dari taking

off list.
Dengan adanya MS, satu perancangan kerja yang baik dapat dihasilkan.
Idea dapat didokumenkan sbg panduan menjalankan kerja.
Keperluan beserta cara terbaik melaksanakan kerja dikenalpasti
Kuantiti bahan binaan yang diperlukan berdasarkan pengiraan yang telah

dilakukan. Disinilah pengiraan secara terperinci untuk setiap elemen bahan


binaan di buat untuk mendapat kuantitinya secara tepat untuk digunakan dalam
perancangan kelak.

MAKLUMAT UNTUK PENYEDIAAN


PENYATA KAEDAH KERJA
1.

Peringkat Operasi atau Kerja

2.

Kuantiti Kerja

3.

Kaedah Pembinaan

4.

Turutan Operasi

5.

Ringkasan Jentera dan Buruh

6.

Hasil / Produktiviti

7.

Tempoh

K Builders Training & Consulting

17 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

STANBY CLAMP
FOR
INSTALLATION

WROPE TO PULL UP
STEEL ANGLE FOR
INSTALLATION OF
TEMPORARY SUPPORT
STRUCTURE & WORKING
PLATFORM

STEEL PIPE

STEP 1 INSTALLATION OF STEEL ANGLE


(To Engineers Design)

INSTALLATION
SAFETY CLAMP
SAFETY CLAMP

INSTALLATION OF 4
WAYS SAFETY
HANGGER CLAMP
TO BOTH SIDE OF
EXISTING STEEL
STRUCTURE

TEMPORARY SUPPORT L ANGLE IN POSITION

STEP 2 : INSTALLATION OF SAFETY HANGGER & CLAMP


(To Engineers Design)

K Builders Training & Consulting

18 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

LAY STEEL PLATFORM

STEP 3 : INSTALLATION OF STEEL PLATFORM


(To Engineers Design)

ALL JOINT BY
BOLT & NUT
JOINT
TEMPORARY TOP SUPPORT FRAME IN POSIOTION

STEP 4 : INSTALLATION OF TOP SUPPORT FRAME


(To Engineers Design)

K Builders Training & Consulting

19 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

INSTALLATION OF L
ANGLE BRACING

STEP 5 : INSTALLATION OF STEEL BRACING


(To Engineers Design)

INSTALLATION OF
SAFETY NETTING

STEP 6 : INSTALLATION OF SAFETY NETTING


(To Engineers Design)

K Builders Training & Consulting

20 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

WELDERS
BLANKET

A
INSTALLATION OF
WELDERS BLANKET

STEP 7 : INSTALLATION OF WELDERS BLANKET


(To Engineers Design)

10 12 11 13 15 14 16 18 17 19

Sequence of dismantle & replacement

REPAIR WORKS PROCEDURE OF GIRDER FRAMES


FLOW OF WORK

K Builders Training & Consulting

21 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

TRIPPER CAR UNDER OPERATION

1ST LOCATION OF TRIPPER CAR

2ND LOCATION OF TRIPPER CAR

Sequence of replacement

METHOD OF REPLACEMENT OF RAIL TRACK FOR TRIPPER CAR

SLOT BUNKER SUPPORT STRUCTURE REPAIR WORKS AT COAL


HANDLING PLANT, SULTAN SALAHUDDIN ABDUL AZIZ SHAH
POWER STATION.
No. Kontrak KEV/KON.48/2009
Project Manager
Sr. Anuar Haron
012-2091669

Safety Manager

Surveyor

Madi Arahan

En. Aris Bin Mohd Ali

Steel Structure Project


Coordinator/ Supervisor
Ching Ai Kok

Competent Scaffolder
(Mohd Sofiani Bin Mohd Noor No
Pend. : WP/08/PP/02/23)

Installer

Chainman

Welder

Labour
Fitter

Nguyen Chi Tam


Gen.
Labour

Project Organisation Chart


Appendix 3

K Builders Training & Consulting

22 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

23 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Penjadualan Masa
1. Road The Contract (RTC)
Fahami keperluan kontrak.
Wujudkan
Float hak kontraktor @ klien
Tugas & tanggungjawab klien- RFI / kemudahan asas
Tuntutan bayaran- kelewatan kerja
Tuntutan loss and expences

2. Penjadualan tugas tanggungjawab


3. Dapatkan info dari estimator
4. Dapatkan tempoh kontrak
5. Target untuk early completion date
6. Penjadualan perolehan sumber binaan

Tujuan Pengiraan Masa


Memastikan projek disiapkan
dalam masa minimum atau
tempoh waktu ditetapkan di
dalam kontrak

Perancangan
Masa

K Builders Training & Consulting

Pengawalan
Masa

24 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Perancangan Masa
Kenapa?
Merancang aturan setiap elemen kerja
dalam tempoh munasabah dan boleh
dilaksanakan.
Bila?
Peringkat tender & pra-kontrak sebelum
operasi di tapak.

Perancangan Mencukupi

Kos Buruh Average

Konsep Fulcum : Kos Buruh VS Perancangan Kerja

KESAN PERANCANGAN MASA TERHADAP


KOS BURUH
Siapa yang anda perlukan?

K Builders Training & Consulting

25 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Pengawalan Masa
Memastikan perancangan kerja dilaksanakan mengikut
tempoh yang ditetapkan.

Perancangan Masa Jangka Pendek


Perancangan terperinci berdasarkan Program Induk
(Master Program) yang dipendekkan sama ada secara
Bulanan, 2 Minggu atau Mingguan.

Perancangan Jangka Pendek


Setiap operasi kerja yang dilaksanakan
hendaklah dianalisis masa dengan teliti.
Operasi kerja yang terlewat dari program
kerja induk akan diberi keutamaan pada
setiap peringkat dan membolehkan
tindakan diambil untuk mengisi semula
masa yang tertinggal

K Builders Training & Consulting

26 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Menentukan Tempoh Sesuatu


Operasi Kerja

Penyata Kaedah Kerja


(Method Statement)

Pemilihan teknik pembinaan

Kaedah pengendalian bahan, jentera & buruh

Maklumat yang lengkap dari pihak konsultan


terutamanya:

Lukisan / Pelan
Dokumen Kontrak

K Builders Training & Consulting

27 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Penelitian haruslah dibuat terhadap pelan


tersebut agar program kerja berjalan dengan
baik.
Ini adalah perlu kerana:
Mengelakkan berlakunya kerja bertindih
Menjadikan kerja binaan lebih efektif dari segi kos
pembinaan
Dapat mengawal mutu kerja
Mencapai kapasiti maksimum penggunaan sumber binaan
- bahan, buruh dan jentera

Untuk melancarkan kerja binaan, kita


perlulah membuat :-

Carta Bar / Gantt Chart


di mana kita dapat mentukan masa setiap
operasi kerja (aktiviti) yang akan
dilaksanakan.
Untuk (mencapai objektif program binaan)
memaksimakan produktiviti kerja, kita perlu
mengawal, mengenalpasti dan menganalisa
setiap operasi binaan dengan menyediakan
sub-program yang lebih detail iaitu program
jangka pendek

K Builders Training & Consulting

28 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Meneliti Keperluan Masa


Dalam Sub-program
Kuantiti bahan binaan
Bilangan buruh & tenaga kerja
Jumlah, jenis & kapasiti mesin & jentera

Bagi mencapai objektif sebagaimana yang diprogramkan,


kita perlu meneliti sub-program dari aspek :

Penghantaran
bahan
Kehadiran
buruh

K Builders Training & Consulting

Elemen- elemen
yang tidak dapat
kita kawal
Keupayaan
jentera

29 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Program Penghantaran Bahan


Jenis bahan
Jumlah/kuantiti keseluruhan
Bila diperlukan keseluruhan atau berperingkat
Kuantiti berperingkat
Jika ada perubahan
-Keluarkan keseluruhan program kerja induk baru
-Keluarkan program penghantaran baru

Kesan Kitaran Perolehan Bahan Fabrikasi Terhadap Masa


Bila perlukan?
Tempoh Pemasangan
Tarikh di
Perlukan
di tapak

Tarikh
siap
pasang di
tapak

Berapa lama proses fabrikasi & penghantaran?


Apakah langkah-langkah yang terlibat semasa fasa fabrikasi & penghantaran
Tempoh
fabrikasi
Kelulusan
spesifikasi

Kelulusan
Shop
drawing

Bermula
Fabrikasi

Tempoh
pemasangan

penghantaran
Siap di
kilang

Penerimaan
Di tapak

Tarikh
diperlukan

Penyimpanan

Penjagaan (Protection)
Kos Pengurusan

K Builders Training & Consulting

30 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Change order
out off date

Perolehan
Sub-kontraktor

sub kontrak & Submission shop


issued projet drawing oleh sub
contrak atau pembekal

Kelulusan
shop drawing
A/E

Tiidak
lulus
lakukan
pembetul
an

CONTOH SENARAI BAHAN


KET ERANGAN

ITEM

UNIT

KUANTITI

KADAR HARGA

JUMLAH

ELEMENT NO. 1 - KERJA-KERJA RAFT FOUNDATI ON

Kerja pengorekan tapak bermula dari aras sedia ada dan


membuang bahan korekan keluar dari tapak ke kawasan
buangan kontraktor
A

Merendahkan aras di seluruh tapak purata kedalaman 50mm

m2

262

4.00

1,048.00

Pengorekan kedalaman 125mm untuk asas rakit

m2

262

6.00

1,572.00

Membekal mengaras, meratakan dan memadatkan 'hardcore',


Gred A ketebalan 150mm berserta satu lapisan pasir dirata
dan dipadatkan untuk diletakan konkrit alas(Diukur berasingan)
C

Asas Rakit

m2

262

7.00

1,834.00

Lean Concrete Gred 15 (1 : 3 : 6)


Ketebalan 50mm dirata dan diaraskan di bawah asas rakit

m2

262

8.00

2,096.00

Waterproof System
Satu lapisan 'Polythene' sebagai lapisan kalis air

m2

262

3.40

890.80

m2

262

8.50

2,227.00

m2

48

14.80

710.40

m2

33

23.40

772.20

m3

26

180.00

4,680.00

33

135.00

4,455.00

Kepingan besi tetulang (Fabric)


Satu lapisan kepingan besi tetulang - BRC A8 (BS 9483)
dengan lapisan mengikut spesifikasi pengilang diletakan di
dalam lantai konkrit
Dua (2) lapisan kepingan besi tetulang - BRC DA10 (BS 9483)
dengan lapisan mengikut spesifikasi pengilang diletakan di
dalam lantai konkrit
Papan Acuan
Di sekeliling asas rakit
Konkrit
Konkrit tetulang Gred 30 (1 : 2 : 4), dituangkan ke dalam acuan
mengikut spesifikasi dan dipadatkan dengan sempurna
sekeliling tetulang
100mm tebal untuk asas rakit
-'EXT RA OVER' - purata 2000mm lebar x 373mm dalam
termasuk papan acuan, pengorekan dan meletak 'hardcore'
secara manual pada cerun

Ba w a ke Ha da pa n

K Builders Training & Consulting

20,285.40

31 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

MERANCANG AKTIVITI
Memancang
tanda

Pengorekan

Menanggalkan
acuan

Menyediakan
aras

Menuang
konkrit

SUSUNAN
AKTIVITI

BRC

Lapisan Tegar
(hardcore)

Acuan

Water proof
System

Lean
Concrete

Kadar Purata Angkatap Buruh

K Builders Training & Consulting

32 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

Work Method Statement for Raft Foundation


NO

AKTIVITI

TRED

1 Memancang tanda Syarikat

KUANTITI

JENTERA

BURUH

Theodolite(1 Unit)

Pengorekan

Syarikat

46M

Menyediakan
aras

Syarikat

Lapisan tegar

ANGKATAP

PENGIRAAN

TEMPOH (HARI)

Backhoe(1 Unit)

4M /jam

46 =12jam
4

Alat Aras
(1 Unit)

Tukang
Konkrit

39M3

Jentera Pemadat ( 1 Unit)


Backhoe(1 Unit)

1.5M3/jam

39 = 13jam
1.5 x 2

1 1/2

Acuan

Tukang
Kayu

33M2

3M2/jam

33 = 5.5jam
3x2

Lean Con
Gred 15

Tukang
Konkrit

13M3

Mesin Pembancuh
Konkrit (1Unit)

1.6M3/jam

13 = 4jam
1.6 x 2

Water
Protection

Tukang
Konkrit

262M2

35M2/jam

262 = 8jam
35

BRC

Tukang
Besi

310M2

20M2/jam

310 = 8jam
20 x 2

Konkrit Asas

Tukang
Konkrit

51M3

Mesin Pembancuh
Konkrit (1 Unit)

1.6M3/jam

50 = 8jam
1.6 x 4

10

Gred 30
Menanggalkan
Acuan

Tukang
Kayu

33M2

6M2/jam

33 = 3jam
6x2

1/2

1 1/2

1/2

1/2

Shorterm Program for Raft Foundation

K Builders Training & Consulting

33 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

PROGRESS REPORTING

K Builders Training & Consulting

34 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

35 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

36 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting

37 /38

Civil Engineering Structural Site Management & Contract And Procurement Procedures

K Builders Training & Consulting