TIME MANAGEMENT
& SCHEDULING
INCLD PROGRESS REPORTING
1 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
COURSE DESCRIPTION :
This learning package enables trainees to acquire
knowledge and develop skill on planning and scheduling.
At the end of the learning package, the trainees will be
able to :
Analyse Contract Document
Study project scope of work
Review method statement
Produce civil and structural work programme and targeted
schedule
Submit civil and structural work programme and targeted
schedule
2 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
3 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
WORK PROGRAMME
Merupakan satu jadual perancangan pelaksanaan kerja dalam satu
KONSEP PERANCANGAN
Perancangan ialah aktiviti yang dilakukan melalui perbincangan,
4 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
PERINGKAT-PERINGKAT
PERANCANGAN
Peringkat pertimbangkan, mengenal pasti, merancang, menilai
5 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
PERTIMBANGKAN SEMASA
MEMBUAT PERANCANG
Keadaan tapak bina, yang melibatkan pengankutan
6 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
14
K Builders Training & Consulting
7 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Activity
Responsibility
Start
Project Manager
Project Manager
Project Manager
Project Manager
Area Contracts
Manager
A
Project Manager
8 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Activity
Responsibility
A
Where required, submit construction
Works programme to client for
approval
Project Manager
Revise Construction
Works Programme
as per Clients
requirements
Does Client
approve
Construction
Works
Programme
Project Manager
No
Project Manager
Yes
Maintain Construction works programme as a
controlled document with relevant Revision No.,
Issue No., and Effective Date pass one copy to client,
copies to relevant consultants and other parties, and
maintain one copy at site
Project Manager
End
Contract Document
9 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Contract Document
CONTRACT
DOCUMENT
SCOPE OF WORKS
(Base on Case Study)
SLOT BUNKER SUPPORT STRUCTURE
REPAIR WORKS
10 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Contract Document
Contract Document
11 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Contract Document
12 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Spesifikasi
Keterangan & huraian mengenai kualiti bahan & kerja serta kaedah
pembinaan .
Sebahagian daripada Dokumen Tender / Dokumen Kontrak.
Terdapat di dalam lukisan & Senarai Bahan yang menerangkan sesuatu
kerja yang tidak dapat dilukis.
Terbahagi kepad 2 kategori ;
Spesifikasi Am - asas bagi semua kategori kerja pembinaan.
Spesifikasi Tambahan - memperincikan secara khusus atas
Spesikasi Am & disediakan oleh Perunding atau Pengilang.
Spesifikasi Tambahan dan Spesifikasi dalam Lukisan Pembinaan
mendahului Spesifikasi Am.
Keterangan spesifikasi hendaklah seragam. Sebarang percanggahan , kontraktor
bertanggungjawab merujuk dan mendapat pengesahan daripada pihak Pemilik
atau Perunding.
13 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
14 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
15 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
16 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
berkenaan.
Bahan binaan yang diperlukan serta kuantitinya yang boleh didapati dari taking
off list.
Dengan adanya MS, satu perancangan kerja yang baik dapat dihasilkan.
Idea dapat didokumenkan sbg panduan menjalankan kerja.
Keperluan beserta cara terbaik melaksanakan kerja dikenalpasti
Kuantiti bahan binaan yang diperlukan berdasarkan pengiraan yang telah
2.
Kuantiti Kerja
3.
Kaedah Pembinaan
4.
Turutan Operasi
5.
6.
Hasil / Produktiviti
7.
Tempoh
17 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
STANBY CLAMP
FOR
INSTALLATION
WROPE TO PULL UP
STEEL ANGLE FOR
INSTALLATION OF
TEMPORARY SUPPORT
STRUCTURE & WORKING
PLATFORM
STEEL PIPE
INSTALLATION
SAFETY CLAMP
SAFETY CLAMP
INSTALLATION OF 4
WAYS SAFETY
HANGGER CLAMP
TO BOTH SIDE OF
EXISTING STEEL
STRUCTURE
18 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
ALL JOINT BY
BOLT & NUT
JOINT
TEMPORARY TOP SUPPORT FRAME IN POSIOTION
19 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
INSTALLATION OF L
ANGLE BRACING
INSTALLATION OF
SAFETY NETTING
20 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
WELDERS
BLANKET
A
INSTALLATION OF
WELDERS BLANKET
10 12 11 13 15 14 16 18 17 19
21 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Sequence of replacement
Safety Manager
Surveyor
Madi Arahan
Competent Scaffolder
(Mohd Sofiani Bin Mohd Noor No
Pend. : WP/08/PP/02/23)
Installer
Chainman
Welder
Labour
Fitter
22 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
23 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Penjadualan Masa
1. Road The Contract (RTC)
Fahami keperluan kontrak.
Wujudkan
Float hak kontraktor @ klien
Tugas & tanggungjawab klien- RFI / kemudahan asas
Tuntutan bayaran- kelewatan kerja
Tuntutan loss and expences
Perancangan
Masa
Pengawalan
Masa
24 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Perancangan Masa
Kenapa?
Merancang aturan setiap elemen kerja
dalam tempoh munasabah dan boleh
dilaksanakan.
Bila?
Peringkat tender & pra-kontrak sebelum
operasi di tapak.
Perancangan Mencukupi
25 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Pengawalan Masa
Memastikan perancangan kerja dilaksanakan mengikut
tempoh yang ditetapkan.
26 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Lukisan / Pelan
Dokumen Kontrak
27 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
28 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Penghantaran
bahan
Kehadiran
buruh
Elemen- elemen
yang tidak dapat
kita kawal
Keupayaan
jentera
29 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Tarikh
siap
pasang di
tapak
Kelulusan
Shop
drawing
Bermula
Fabrikasi
Tempoh
pemasangan
penghantaran
Siap di
kilang
Penerimaan
Di tapak
Tarikh
diperlukan
Penyimpanan
Penjagaan (Protection)
Kos Pengurusan
30 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
Change order
out off date
Perolehan
Sub-kontraktor
Kelulusan
shop drawing
A/E
Tiidak
lulus
lakukan
pembetul
an
ITEM
UNIT
KUANTITI
KADAR HARGA
JUMLAH
m2
262
4.00
1,048.00
m2
262
6.00
1,572.00
Asas Rakit
m2
262
7.00
1,834.00
m2
262
8.00
2,096.00
Waterproof System
Satu lapisan 'Polythene' sebagai lapisan kalis air
m2
262
3.40
890.80
m2
262
8.50
2,227.00
m2
48
14.80
710.40
m2
33
23.40
772.20
m3
26
180.00
4,680.00
33
135.00
4,455.00
Ba w a ke Ha da pa n
20,285.40
31 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
MERANCANG AKTIVITI
Memancang
tanda
Pengorekan
Menanggalkan
acuan
Menyediakan
aras
Menuang
konkrit
SUSUNAN
AKTIVITI
BRC
Lapisan Tegar
(hardcore)
Acuan
Water proof
System
Lean
Concrete
32 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
AKTIVITI
TRED
KUANTITI
JENTERA
BURUH
Theodolite(1 Unit)
Pengorekan
Syarikat
46M
Menyediakan
aras
Syarikat
Lapisan tegar
ANGKATAP
PENGIRAAN
TEMPOH (HARI)
Backhoe(1 Unit)
4M /jam
46 =12jam
4
Alat Aras
(1 Unit)
Tukang
Konkrit
39M3
1.5M3/jam
39 = 13jam
1.5 x 2
1 1/2
Acuan
Tukang
Kayu
33M2
3M2/jam
33 = 5.5jam
3x2
Lean Con
Gred 15
Tukang
Konkrit
13M3
Mesin Pembancuh
Konkrit (1Unit)
1.6M3/jam
13 = 4jam
1.6 x 2
Water
Protection
Tukang
Konkrit
262M2
35M2/jam
262 = 8jam
35
BRC
Tukang
Besi
310M2
20M2/jam
310 = 8jam
20 x 2
Konkrit Asas
Tukang
Konkrit
51M3
Mesin Pembancuh
Konkrit (1 Unit)
1.6M3/jam
50 = 8jam
1.6 x 4
10
Gred 30
Menanggalkan
Acuan
Tukang
Kayu
33M2
6M2/jam
33 = 3jam
6x2
1/2
1 1/2
1/2
1/2
33 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
PROGRESS REPORTING
34 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
35 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
36 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
37 /38
Civil Engineering Structural Site Management & Contract And Procurement Procedures
38 /38