You are on page 1of 14

ICC500 cabinet air condition installation aqueduct operation

instructions
Remove the air condition
1open the door and fix it

2Remove the screws of the air inlet of wind deflector of air-condition, and remove wind
deflector (Notes: the screws are M3, removed the screws are kept separate)

3Remove the air condition part of the deck baffle screws and remove subdivision baffle(Notes:
the screws are M3, removed the screws are kept separate)
2016-5-12

1 , 14

4Remove the air-condition power cable and alarm cable: Note: when remove the alarm cable,
insert a little down firmly with a slotted screwdriver;

5 Cut off the ties

2016-5-12

2 , 14

6Remove the screw in the edge of the air condition, Note: the screws are M5, pay attention to
save;

7Carry out the air condition. Note: Must two or three people to carry out the air condition (air
condition is estimated more than 80kg), pull out the top of air condition and then carry out the
bottom;

2016-5-12

3 , 14

pull out

carry out

8lying the air condition on the ground, Note: air condition lying on the ground could not be a
long time, the entire operation is expected to be completed in about 20 minutes;

9fix the flange

2016-5-12

4 , 14

10Use a Phillips screwdriver to disassemble the shell insect nets; directly with screw drop
down, and pay attention to get smooth around the hole;

2016-5-12

5 , 14

Attention: Note: actually apart of the hole is the hole as shown:

11Move air condition near to the door, and go through the drain from the hole;

2016-5-12

6 , 14

Obverse plan view: the holes of the second row, fourth column

12Gently pull the drain pipe, try to straighten;

2016-5-12

7 , 14

13Installation air condition, Note that: first, put the aqueduct flange into the door, do not bump
and leak, and then put air condition into the hood;

2016-5-12

8 , 14

14Fixed the air condition screws, the subdivision wind board screws, the air inlet baffle screws,
2016-5-12

9 , 14

(as shown below step by step operation)

2016-5-12

10 , 14

2016-5-12

11 , 14

2016-5-12

12 , 14

2016-5-12

13 , 14

Lead the drain out of the door, and the operation is completed;

2016-5-12

14 , 14