Project Schedule

Name of Project:

1 Architecture
1.2 Plot Plan
1.3 Planning Conditions
1.4 Setting Layout
2 Soil Test
3 SEWA
4.1 Water
4.2 Electricity
4.3 Gas
4 Etisalat
5 Muncipality
5.1 Architecture
5.2 Structure
5.3 Drainage

Date of
Submission

Approval
Duration

Approved
Date

Already Have
Already Have
05-Jun
05-Jun

2 WEEKS
5 Days

19-Jun
10-Jun

22-Jun

2 weeks

06 ju

19-Jun

5 days

23-Jun

26-Jun

2 weeks

10-Jul