Professional Documents
Culture Documents
No. 92-1313
PROFESSIONAL BUILDING CONCEPTS, INC.,
Plaintiff, Appellant,
v.
THE CITY OF CENTRAL FALLS, ET AL.,
Defendants, Appellees.
_____________________
No. 92-1314
PROFESSIONAL BUILDING CONCEPTS, INC.,
Plaintiff, Appellee,
v.
THE CITY OF CENTRAL FALLS, ET AL.,
Defendants, Appellees,
_____
PROMAC, INC.,
Plaintiff-Intervenor, Appellant.
____________________
APPEALS FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF RHODE ISLAND
[Hon. Francis J. Boyle, U.S. District Judge]
___________________
____________________
Before
Selya, Circuit Judge,
_____________
Roney,* Senior Circuit Judge,
____________________
and Pieras,** District Judge.
______________
____________________
Housing
Authority and
U.S. Department
of Housing
and Ur
Development.
Albert A. DiFiore with whom Beals & DiFiore was on brief
___________________
________________
Maron Construction Company, Inc.
____________________
____________________
_____________________
* Of the Eleventh Circuit, sitting by designation.
** Of the District of Puerto Rico, sitting by designation.
PER CURIAM:
sought an
injunction
Contrary to the
The lowest
court
law.
approving
the contract
award
on a
bid
that it
contends
was
dispute
Department
Authority
of Housing
improvements to
Island.
is
In
contract
and Urban
We affirm.
funded by
the
United
Development (HUD)
States
for general
two housing
projects
in Central
Falls,
February 1991,
the City
of Central
Falls Housing
(the
Authority)
issued
an
invitation
Rhode
for
bids,
prior
required submission of
a bid
guarantee
Professional Building
certified
corporate check.
the Authority
PBC's
and HUD
guarantee.
officials
After
recognized the
review
of
HUD's
deficiency
in
manual
and
allow
company check.
bidders,
Maron
Promac,
PBC,
Inc. (Promac).
Construction Company,
Inc.
(Maron),
and
the low
the Authority.
and engaged
in
"bid shopping."
letter
recommended
19, HUD
dated
April
4,
the
Authority's
architect
On April
contract to PBC.
On April
the bid
opening.
Promac
filed a new
bid protest,
although the
advised the
borderline, PBC's
was a material
Authority
failure to
defect requiring
rejection of
its bid.
and seeking
PBC's claim
decision
an injunction.
the award of
the contract to
The district
court rejected
noncompliance in the
bidding process.
The materiality
by HUD
of a bid guarantee
requirement is governed
in
See 48 C.F.R.
___
sealed
requirement for
bidding,
a bid
noncompliance
guarantee
with
requires rejection
provides
solicitation
of a
bid,
except in certain
this
case.
(1989)
See
___
(quoting 48 C.F.R.
Cl.Ct. 812
Cir. 1990).
No
we
Decisions of the
issue. See
___
bid
to
be
F. Supp.
supported
by
bid
guarantee
shall be rejected."
bids
and
To the Heads
_____________
38
Comp. Gen.
532 (1959);
see
___
In re Castle Floor
___________________
Gen.
43
submission
(1976).
reasons
that
"the
which a bid
time of bid
The Authority
not
Comptroller
responsiveness with
opening."
The
a minor
after opening.
informality which
PBC could have
could be
sufficiently corrected
guarantee requirement
by stopping payment
on its corporate
check.
the
bids of
commitment
to
guarantee
is to
perform
competitors
the contract.
provide
commitment, that
contract.
the other
assurances
the bidder
will,
before making
The
in
the
purpose
form
if successful,
a firm
of a
bid
firm
of
perform
the
such a firm
commitment.
PBC argues that
there was
in addition
to
24 C.F.R.
a bid
maintains
that
no defect in
bond
company
contract, however,
or a
check
certified
specify
check a
bid
negotiable instrument.
satisfies
The invitation
guarantee
85.36(h)(1) (1991),
its bid
the
"other
to bid
of, at
for
least, a
comply
with
informality
the
guarantee
requirement
failure
is
not
an
According to the
substance.
can be corrected
the exact
or waived
48 C.F.R.
14.405
documents,
such as
(1991).
failure to
Typically, defects
sign
the bid
in
bid reply
under some
circumstances, failure
14.405 (1991);
as minor
goes beyond
informalities.
a mere
informality, so
The defect in
it is
required
to
of no
before
PBC
bidder."
writing
the
lowest
at the
to
Authority
"responsive
At that meeting
precluding the
made
award will be
and
responsible
85.36(d)(2)(ii)(D) (1991).
that, before
executing
the
the
determined to be
nonresponsive.
After
The
has
procurement
clear
and
regulations.
failed
to
demonstrate
that
the
challenged
violation
of
applicable
statutes
and
F.2d 1052, 1054 (1st Cir. 1987); Smith & Wesson v. United States,
_______________________________
Maron's Bid
___________
second
lowest
bidder,
Maron
Construction
Company,
Inc.
Authority that it
The
district court
untimely
on the
merits.
Paragraph 7
prices for
damaged
Authority's form of
with respect to
additional
of the
(1) the
areas of
stucco
bid requires
finish, (3)
unit
the
of individual brick,
re-pointing
for repair of
unit price
for
the
price
Of the eight
to the four.
Maron added
an extra line
item
concrete
because use of
bid uncertain in
work in its
did it provide
section
03732
of
the
specifications,
how a contractor
is to
entitled
accomplish
sheet
which
cautions
5 of the
bidders
to
bid package
pay
particular
complied with
awarding the
these instructions.
bid to Maron
clear violation
had a
of applicable
The Authority's
rational basis and
statutes
note
since it
action
in
was not
and regulations.
See
___
not
Promac's protest
filed.
reflected in
the district
of Maron's bid
appears to
objection
or protest as
court's decision,
have been
to Maron's written
untimely
party filed an
10
the
bid opening and after this court case had already commenced.
The
Authority
summarily dismissed
the protest
do not set
at that time
Although the
on the
period of
to
address
the Authority
the
merits,
the
district
court
any formal
bid
Promac
filing procedures.
with any
guidelines
relating
to its
protest
23, 1991.
under the
Freedom of
the
In addition, Promac
Information Act
on
check.
Knowledge of
seem to be
a reasonable
event
1991.
Nevertheless,
limit for a
reasonable time to
for 90
Thus,
the
Affirmed.
Affirmed
________
12