ABSTRACT

Devianto, B. 2016. Methods Of Implementation and The Budgeting of Bridge


Box Culvert Type at Biu River Paser District East Borneo. Final Project.
Civil Engineering Department, State Polytechnic of Malang. Advisor I:
Drs. Susapto, MT Advisor II: Drs. Armin Naibaho, ST., MT.

The bridge box culvert at Biu river Paser District with length 55 m, width
17 m, and high 4,5 m. The shapes of this bridge is bottom slab, wall, slab top and
wing wall. The purpose of this final project is to find out the Work Breakdown
Structure (WBS), implementation method, working duration, and estimate the
cost.
The required data were of tecnical drawings and material and work unit
price Standard National Indonesia 2016. Precedence Diagram Method (PDM),
and S-Curve was used for scheduling.
The planning results in Work Breakdown Structure (WBS) based on the
planned work to arrange work item of preparation, excavation, sructure, and
refill, on level 1; ready mix using pump, 334 work days or 57 weeks on at IDR
16,335,411,000.

Key words : planning the costs, implementation schedule, PDM, S-curve

vi