Jour / Day Tools needed for the 3 days

Du/ From June 5th-9th - Bobcat/tractor


Preparing the site - Sand for leveling
- Moving the pea gravel
- Leveling the terrain
not more than a 2%
slope
Lundi/Monday June 12th
Components arrive @5PM
- Unload
- Supervise overnight
Mardi / Tuesday June 13th For concrete work
8 AM - 4PM - 68-80 bags of redi-mix
4 – 6 volunteers concrete
- Able to lift 100lbs - 8 wheelbarrows
- Lay out stringers - Tampers-for bottom of
- Place posts and decks holes
- Weld stringers and posts - 8-10 shovels
- Dig 17 holes ( 12” x 36”) - 6 sono tube
- Fill holes with cement - 12” auger
2-3 volunteers - Bobcat/tractor
prepare lunch, snacks - 2” x 4” for any cribbing
/bracing
- 1 stickwelder 200amp gas
powered
- 7014 BlueShield welding
rod ( 4 boxes)
- Spray paint- tremclad

Mercredi/Wednesday June For general installation


14th 8AM-2PM - 4-6 mesuring tapes
4-6 volunteers -4 4’ levels
- Measuring and marking -4 torpedo levels
all components -4-6 Impact guns
- Placing and counting all -4 -6 cordless drills
components -6 each 21/64” and 5/32”
2-3 volunteers drill bits
- prepare lunch, snacks - 2 wheelbarrows
- 3 sets standard
wrench/ratchet
- 2 8’ ladders

Jeudi/Thursday June 15th


8AM-3PM - 4-6 measuring tapes
3 sergents - 4 4’ levels
20-40 volunteers - 4 torpedo levels
( 2 shifts) - 4-6 Impact guns
- 4 -6 cordless drills
- Building, attaching the - 6 each 21/64” and 5/32”
components drill bits
- Moving the pea gravel - 20 wheelbarrows
- 10-20 shovels
5-10 volunteers - 3 sets standard
prepare lunch, snacks wrench/ratchet
- 2 8’ ladders

SVP contacter l’école pour vous inscrire. Please contact the school to
register or go online.