OBP005301

From: (b) (6)


To: (b) (6)
Subject: FW: Tasker info needed by AM on Tuesday
Date: Tuesday, February 26, 2008 9:59:37 AM
Attachments: 2008859.Kyl Response v3.doc

In case you want to see the numbers SBI is reporting. Apparently this paper had already been done by
SBI.

From: (b) (6)


Sent: Tuesday, February 26, 2008 9:32 AM
To: (b) (6)
Cc: (b) (6)
Subject: FW: Tasker info needed by AM on Tuesday

(b) – Sorry I didn’t get back to you earlier on this. This is the response we already drafted for
(6)
Congressman Kyl. Please let me know if you have any questions.

(b) (6)
Metrics and Reporting Analyst
Office: (b) (6)
B.B.: (b) (6)
(b) (6)
(b) (6)

From: (b) (6)


Sent: Monday, February 25, 2008 5:43 PM
To: (b) (6)
Cc: (b) (6)
Subject: Tasker info needed by AM on Tuesday

(b) (6) ,
These are needed for a congressional response due right away.

· Total number of miles of ped fencing DHS intends to complete this calendar year in AZ
(indicate # of miles that will be double-layered)

· Total number of miles of ped fencing DHS intends to complete this calendar year on
SOUTHERN BORDER (indicate # of miles that will be double-layered)

· Total number of miles of vehicle fence DHS intends to complete this calendar year in AZ

· Total number of miles of vehicle fence DHS intends to complete this calendar year on
SOUTHERN BORDER

· Total number of miles of ped fencing and vehicle fencing projects will exist on the southern
border at the end of this calendar year and what portion of that total DHS regards as satisfying
the 700 miles of fencing mandated by the Secure Fence Act.

Thanks,
(b)
(6)
OBP005302

(b) (6)
Assistant Chief
Headquarters U.S. Border Patrol
Office: (b) (6)
Cell: (b) (6)