Professional Documents
Culture Documents
Formulas For PMP
Formulas For PMP
2. Standard Deviation (P - O) / 6
5. Cost Variance EV - AC
6. Schedule Variance EV - PV
12. To Complete Performance Index Values for the TCPI index of less then 1.0 is good
TCPI because it indicates the efficiency to complete is
less than planned. How efficient must the project
team be to complete the remaining work with the
remaining money?
( BAC - EV ) / ( BAC - AC )
16. Benefit Cost Ratio Bigger is better ((BCR or Benefit / Cost) revenue
or payback VS. cost)
Or PV or Revenue / PV of Cost
17. Payback Period Less is better
18. BCWS PV
19. BCWP EV
20. ACWP AC
26. Point of Total Assumption (PTA) ((Ceiling Price - Target Price)/buyer's Share Ratio)
+ Target Cost
1σ = 68.27%
2σ = 95.45%
Sigma σ 3σ = 99.73%
6σ = 99.99985%