No. 68/SE/TAS/Building cost index. /Apr- 2010/163-E

ISSUED BY AUTHORITY OF DIRECTOR GENERAL OF WORKS

NIRMAN BHAVAN, NEW DELHI DATED: 22/06/2010

Subject: Building cost index for Delhi with reference to plinth area rates 01/10/07 (as base 100)

The Director General of Works is pleased to approve the cost index of Delhi as 136 on
01-04-2010 over plinth area rates 01/10/07 as base 100.

Encl: Calculation Sheets of Cost Index

Sd/-
(A K Agarwal)
Executive Engineer (S&S)-I

Copy forwarded to:

1) All ADGs )
2) All Chief Engineers ) in CPWD and PWD (Govt. of N.C.T.D.)
3) All SE’.s )
4) All Executive Engineers)
Sd/-
Executive Engineer (S&S)-I

DELHI COST INDEX apr


CALCULATION SHEET

BUILDING COST INDEX AT DELHI AS ON 01-04-2010 w.r.t. PAR 01-10-2007

RATE as Rate as
Sl. Weigh- RATE as Cost
Description Unit on approved by Remarks
No. tage on 01/10/2009 Index
01/10/2007 CE(CSQ)

1 Bricks 1000 Nos. 2000.00 8.00 2800.00 2800.00 11.20

2 CEMENT (OPC) QTL. 457.00 14.50 500.00 500.00 15.86

STEEL

3 a) 8 & 10 MM(TMT STEEL) 50% QTL. 3280.00 19.50 3780.00 3740.00 22.23

b) 12 & 16 MM(TMT STEEL) 50% 3700.00

4 AGGREGATES 20 MM SIZE CUM 700.00 6.50 1000.00 1000.00 9.29

5 SAND (COARSE SAND) CUM 650.00 3.00 1000.00 1000.00 4.62

FLOORING ITEMS:

a) MOSAIC TILES 40% 225.00

b) CERAMIC TILES 40% 380.00


6 SQM. 381.10 3.00 443.00 3.49

c) KOTA STONE 10% 285.00

d) GRANITE STONE 10% 1725.00

PAINTS:

a) SYNTHETIC ENAMEL PAINT 33.33% 135.00


7 LIT. 100.00 3.00 110.00 3.30
b) O.B.D. 33.33% 45.00

c) PLASTIC EMULSION PAINT 33.33% 150.00

PLY AND COMM. WOOD: The rate of


Aluminium
a) 12 MM THICK PARTICLE window is
33.33% 420.00 converted into
BOARD
8 SQM. 1281.30 5.00 1589.00 6.20 per SQM from
b) STEEL WINDOW STANDARD per Kg by
33.33% 1275.00
'Z' SECTION multiplying
c) ALUMINIUM WINDOW 33.33% 175.00 (Per Kg) 17.55
(40.02/2.28).

PIPES:

a) 15 MM GI PIPE 33.33% 78.00


9 METRE 144.50 2.50 175.00 3.03
b) 100 MM SCI PIPES 33.33% 380.00

c) 20 MM BLACK CONDUITS 33.33% 66.00

LAMPS & FANS:

10 a) CEILING FANS 48" 50.00% EACH 655.00 3.50 1186.00 893.00 4.77

b) 1.20 M FLOURESCENT TUBE


50.00% 600.00
WITH FITTINGS
ELECT. MACHINERY MOTOR 7.5
11 BHP (PUMP SET) 1500 RPM EACH 35000.00 2.50 29500.00 29500.00 2.11
(KIRLOSKAR)
WIRES & CABLES:

12 a) COPPER WIRES 1.5 SQMM 70.00% 100 MTR. 825.00 4.00 925.00 1383.00 6.71

b) COPPER WIRES 4.0 SQMM 30.00% 2450.00

LABOUR:

13 a) SKILLED 50.00% EACH 143.38 25.00 273.00 249.00 43.42

b) UNSKILLED 50.00% 224.00

Total = 100.00 136.22

Say = 136
Sd/-
(A K AGARWAL)

EXECUTIVE ENGINEER (S&S)-I