Please “Switch OFF” IDU, Remove all connections PCM E1 cable, Power cable,
Grounding cable, Alarm Cables, NMS Cables etc & Remove the IDU from Rack.
4. In case of Pasolink V4 1+1, “Switch OFF” IDU & Remove “Switch Unit”.
Remove all Screws to Remove Top Cover of Switch Unit.
5. In case of Pasolink V4 1+0 , Remove all Screws to open TOP Cover.
6. Remove TOP Cover of V4 1+0 IDU or TOP cover of “Switch Unit” of V4 1+1
7. Identify the LAN Interface Connector in IDU.
9. Remove the “two screws” from inside the IDU to open Front Plate.
10.Install “Support Stud” which comes with LAN INTF Module.
11.Remove the “Screw” to install the Support Stud for LAN Interface.
14.Fix the “Screw” on LAN INTF Mod. which is removed before for Support Stud.
15.Fix the “Two Screws” from where the Front Plate has been removed.
16.Install the Top Cover of IDU In case of V4 1+0 & Switch Unit in case of V4
1+1
17.Install V4 1+0 IDU in Rack or Install V4 1+1 Switch Unit in IDU Chassis.
a) Pasolink V4 1+0 with “LAN INTF Module”
18.Connect Grounding Cable, IF cable, Power Cable, PCM E1 Cable, LAN Cable,
NMS Cable, AUX alarm cable if it is there before switch ON the IDU.
-----------------------------------------------------END-----------------------------------------------
LAN Interface Settings with PNMTj
1) After Installation of LAN Interface in IDU, Login to Pasolink V4 by PNMTj
2) Click ON “Configuration” & Go to “Equipment Setup”
Additional Information :
1) IF Port1 & Port2 are being used, while configuring Port 2 Bandwidth should
be equal to or less than Port1.
2) Ethernet Port - Bandwidth should be same at Both the End in Hop.