Estimate Activity Duration and Estimate Cost uses same T&T except EC uses

bottom-up estimating

Plan Quality and Perform Quality Control uses same T&T except Plan Quality

uses benchmarking and Design of Experiments

Perform Quality user Quality Audit as T&T

Perform Qualitative Risk Analysis :

 P&I
 Risk Data Quality Assessment
 Risk Urgency Assessment
 Risk Categorization

Conflict Management in Procurement:

Procurement Manager is the authority to make changes in contract


Causes of Conflict