Date Activity Remaining


25-02-2011 IMS Rack Installation MGW Rack Installation

28-02-2011

4/3/2011 Installation Finished


7/3/2011 Powered On
8/3/2011 V3 MGW shifted to J block.
9/3/2011 Configuration
GSM Test Status

Date Activity Remaining


28-02-2011 Equipment arrived at DAKC