You are on page 1of 4

integrated modeling

A New Slant
BY MATT JACKSON, P.E., ATILA ZEKIOGLU, P.E., S.E., EDWIN SHLEMON, P.E., S.E., AND CURTIS MAYES, P.E.

Complex geometry made 3D modeling and structural steel musts for the skeleton
of the Denver Art Museum’s recent expansion.

T
The Denver Art Museum recently completed a dramatic expansion project with were coordinated into a single model. This
the addition of the new Frederic C. Hamilton Building. This new wing, completed holistic working model was manipulated
last October, adds about 50% more exhibit space for the museum’s 60,000-piece throughout the design and construction
permanent collection, a 280-seat auditorium, display areas for traveling exhibi- phase, with the contractor producing com-
tions, and an art storage area. plete and exact 3D detailing and erection
models of the structure. The model was
The original seven-story museum challenges for the design team. The struc- created and maintained by the architect
building, designed by Gio Ponti and James tural design process began with a close col- with a general-purpose 3D solid and sur-
Sudler, opened in 1971 and fronts Denver’s laboration between structural engineers at face modeling software called Form-Z,
Civic Center Park near the Colorado State Arup and the architects to develop a viable used primarily as a geometry and visual-
Capitol and the Denver City and County structural scheme for the complex form. ization tool. By importing all disciplines’
building. The Hamilton building, which The City of Denver also chose to contract work into the master model, the architect
serves as the new grand entrance into the with M.A. Mortenson Company early in was able to achieve 3D coordination in a
art museum complex, is located south of the design stage to provide guidance on way that would otherwise not have been
the original museum across 13th Avenue. A construction issues related to the design. possible.
100-ft-long glass and steel footbridge con- A structural steel “preconstruction team” For structural design, the centerline
nects the second floor of the expansion to was then selected to participate early in the planes of each wall were defined by the
the two original buildings. design of the structure. architect, and then a 3D wireframe model
Studio Daniel Libeskind, in a joint ven- was developed and exported to structural
ture with Denver-based Davis Partnership, 3D Modeling analysis packages. Once the structural
was selected to design the new wing in the It was clear from the start that a build- members had been designed, these shapes
summer of 2000, as the result of an inter- ing as complex as the new Hamilton wing were manually “hung” onto the 3D wire-
national design competition. The resulting could not be completed using conventional frame model so that the actual member
titanium-clad structure, a complex, angular, 2D design and documentation methods, sizes, together with an allowance for fire-
jagged form, was inspired by views of the so the whole design team was required to proofing, could be coordinated with other
Rocky Mountains and presented unique produce 3D models of their work, which disciplines. This 3D coordination was

MODERN STEEL CONSTRUCTION APRIL 2007


Davis Partnership

particularly important for the mechanical


ductwork, as it was also routed through the
inclined walls and closely integrated with
the structure.
The project’s documentation consisted
of 2D drawings together with the 3D model.
The structural geometry was defined by a
series of approximately 700 node points in
3D space, which were also identified on the
2D plans and elevations, so that the geom-
etry, member sizes, and connections could
be fully defined.
Jeff Goldberg/Esto. Courtesy of the Denver Art Museum

Structural Design
Due to the severely inclined walls and
large cantilevers—including the “prow” of
the building, which extends out over 13th
Avenue—it was decided early on that the
dead weight of the building would need to PROJECT FACTS
be minimized, thus making structural steel Area Total Steel Weight
the material of choice. 146,000 sq. ft 2,750 tons
The walls of the building generally
Primary Steel Pieces Bolts
lean outwards, so to some extent, the lat-
3,100 50,000
eral loads balance each other. Thus the
floors act as tension ties for the inclined Total Steel Pieces Field and Shop Welds
walls, with the steel beams helping with 16,500 28,500 lb

APRIL 2007 MODERN STEEL CONSTRUCTION


Column-free spaces inside the building led to
the placement of large amounts of structural
steel inside the titanium-clad inclined exterior
walls.

Jeff Wells. Courtesy of the Denver Art Museum

tension and compression. However, where RAM Steel analyses were combined into a tor, and detailer until the final connection
these forces are not balanced, they must spreadsheet to design these members. was solidified for a single condition.
be taken to ground through the building’s The interaction of the steel-framed At the request of the fabricator, the con-
lateral stability system. This requirement, structure with the concrete floor dia- nection plans were revised to use bolted
together with the architect’s desire for phragms necessitated the inclusion of the connections in the field wherever possible,
dramatic column-free spaces inside the effects of cracking, creep, and shrinkage except at the column splices. Eventually, a
building, lead to the decision to place as of the concrete. This was accomplished “structural claw angle”-type connection was
much of the structure as possible within by running several analysis models with a developed for most brace members. A very
the inclined walls. range of concrete stiffnesses and ensuring unusual connection for the rotated beams
The floor system consists of steel with every member design was adequate for the in the walls was developed, using end plates
a composite floor deck. The design of the forces from each of the models. in combination with double angles to con-
floor system was complicated by the forces nect to the massive inclined gusset plates.
of the inclined structural walls, which create Connection Design In a project of this type, virtually every
very significant in-plane forces under dead The design of the connections pre- connection is unique, and there is no such
load. To deal with these forces, additional sented a particular challenge, with some thing as a “typical” detail. To address this
reinforcement was required within the connections requiring the joining of up to problem the contractor initiated a pre-
concrete floor slabs. In areas of particularly 10 structural members in three different detailing request system, which clarified
high stress, the metal deck was replaced planes. In addition, where the members in geometry connection design and fabrica-
with a ½-in. steel plate welded directly to the walls also support the floors, they were tion concepts for every connection in the
the beams. Similarly, a substantial amount generally rotated to be in a web vertical building prior to the start of actual connec-
of steel diagonal bracing in the roof plane plane for bending efficiency, thus further tion detailing. The final connection design
was required to supplement the roof fram- complicating the connection design. was then performed by Structural Consul-
ing in areas where concrete diaphragms For the first few months, the precon- tants, Inc. of Denver, who designed each
were not an option. struction team debated erection concepts, connection individually, eliminating wasted
The main analysis of the structure various connection designs, orientation of fabrication costs caused by conservative
was carried out in SAP2000 and eventu- members, and edge conditions. Eventually, “grouping of the connections.” Calculations
ally developed into a very detailed model the final connection design and detailing were then submitted to Arup for review.
containing every member in the building, commenced. Input from the detailer and
including floor diaphragms. Several addi- the fabricator was paramount throughout Substructure Foundations
tional models were also required for the the entire process in order to assure that The foundation system is typical for
complex stair framing, which winds its way the details being drawn were not only pos- the Denver area, consisting of individual
around the atrium space. The composite sible to fabricate, but also as economical drilled piers with pier caps. Load-carrying
floor framing was modeled in RAM Steel, as practical for such an extreme structure. capacity of the piers is developed from the
as the primary floor beams also carry sig- In many cases there were several interac- bearing of the piers into the rock, plus the
nificant axial loads from the inclined walls. tive rounds of 3D details and connection skin friction developed from the portion
The results of the global SAP2000 and designs going back and forth between Arup embedded into the very hard shale bedrock.
engineers, the connection designer, fabrica- All exterior bracing walls are supported on

MODERN STEEL CONSTRUCTION APRIL 2007


Owner
vertical planes, where they intersect the Given the complex geometry of the
The City of Denver and the Denver Art
first floor (at grade). The building shear structure, conventional alignment tech-
Museum
for the perimeter walls is transferred to the niques were not an option. A structural
basement retaining walls to take loads to steel alignment plan was developed by the Lead Architect
the foundation. preconstruction team, that required incor- Studio Daniel Libeskind, New York
poration of XYZ survey coordinates into Executive Architect
Construction the 3D Xsteel detailing model. All the pri- Davis Partnership, Inc., Denver, Colo.
The preconstruction team met with mary columns (sloping and vertical) were Structural Engineer of Record
Arup early in the design process to gain an then detailed and fabricated with shop- Arup, Los Angeles
understanding of the structural design con- drilled “alignment control holes” designed
cepts for the building and to start multiple to hold a surveyor’s prism at a theoretical General Contractor
dialogues concerning connections, interac- point in space. Spreadsheets including the M.A. Mortenson Company, Denver
tion of steel and concrete, design concepts XYZ survey coordinates were electroni- Fabricator
for pre-camber of the structure, shoring cally transmitted from the detailer to the Zimmerman Metals, Inc., Denver (AISC
methods, building deflections, and interac- steel erector in the field, then into total sta- member)
tion with construction means and methods. tions to accurately determine the position Erector
The complex, leaning geometry results and alignment of individual members. LPR Construction Co., Loveland, Colo.
in several areas of the building deflecting The design and detailing of the shor- (AISC member)
significantly. For example, the tip of the ing systems for the project also comprised
Connection Design Engineer
structure, which extends out over 13th an interactive process. In many cases the
Structural Consultants, Inc. - SCI, Denver
Avenue, deflects approximately 4 in. under false-work shores had to be literally laced
(AISC member)
dead load, and consequently some of the through the structure below to support
floors that it supports also deflect consid- upper portions of the building. The steel 3D Modeler and Steel Detailer
erably. The two primary concerns in terms erector precisely modeled all 50 of the (above ground level)
of deflection were levelness of floors and unique shores for the project using 3D Dowco Consultants Ltd., Burnaby, B.C.,
flatness of walls, whereas matching the CAD. These CAD models were sent elec- Canada (AISC member)
exact geometry of such an irregular struc- tronically to the detailer to incorporate
ture was a lesser concern. Early discus- with the Xsteel structural model. Finally,
sions between the engineers, architect, and the interfaces between the shores and the
owner resulted in an understanding of the actual structure were developed through
deflection issues and realistic tolerances, collaboration between the steel erector and
which only required a few of the nodes in the detailer.
the building to be set in a pre-cambered Prior to the start of steel erection for
position. This was accounted for in detail- each area, extremely detailed 3D erection
ing and construction by simply setting the procedures were developed and provided
required nodes higher than the intended to the field, resulting in clarity that could
final geometry. not be accomplished with 2D illustrations
In a structure where the dead loads or mere words. Xsteel viewers were utilized
impose forces on the diaphragms and lat- at the jobsite on a daily basis to help visual-
eral load system, the construction sequence ize the connections and scope of the work,
was critical. The timing of shoring removal clarify the erection procedures, and plan
relative to the placement of concrete slabs the daily operations. The final erection
had a significant effect on the final stresses procedures were meticulously followed on-
in the structure. To address this, the steel site with very few problems, and the struc-
erector developed construction and shor- ture was completed some three months
ing sequences in a 3D CAD model so ahead of schedule.
that the intended construction sequence
could be evaluated. Arup shared their SAP Atila Zekioglu is the principal in charge of
2000 structural model with the steel erec- structural engineering and Edwin Shlemon is
tor, LPR Construction Co. LPR engineers associate principal and lead structural engineer,
then went to work dissecting the model and both for Arup’s Los Angeles office. Matt Jackson
breaking it up into multiple stages of con- is a senior engineer with Arup’s New York office,
struction. Load cases included loads from and Curtis Mayes is a director of pre-construc-
wet concrete slab pours, cured concrete tion and engineering at LPR Construction Co.
slabs, and partially erected portions of the
structure, as well as various stages of shore The Denver Art Museum’s Frederic C.
removal. It became apparent that proper Hamilton building is the winner of a 2007
positioning of the shores was critical to AISC Presidential Award of Excellence
assure that overstress conditions would not in Engineering. This and other AISC
occur in the building throughout the mul- IDEAS2 award-winning projects will be
tiple construction stages. highlighted in the May issue of MSC.

APRIL 2007 MODERN STEEL CONSTRUCTION

You might also like