Professional Documents
Culture Documents
Project Energy Home Part 1-2
Project Energy Home Part 1-2
Energy Home
The procured materials will be allocated from multiple manufacturers and experts will have to be contracted for
certain instillations such as the solar panels, insulation, water heating system, and water recycling system.
SOW
Project Energy home is a 2 month project with a budget of $205,000. Innovative contractors will
procure innovative energy efficient technology that reduces utility bills and certifies the Gonzalez
home a 15 rating on the LEED energy rating scale. Local contractors will be contracted to install:
• Windows
• Solar panels
• High Efficiency HVAC
• Tankless water heaters
• Geothermal Unit
• Water recycling system
• H2O Floor heating
• Drip irrigation system
• Propane generator
Additional experts will be contracted to complete any additional work such as the instillation of
certain appliances. To attain the most efficiency quality is of the upmost importance and for that
reason only contractors who are highly qualified with excellent recommendations will be
contracted. Inspections will done by inspectors and the QA manager to evaluate the completed
deliverables or the quality of the amount completed .
Deliverables
Solar Panels(Kyocera) 72,000
Anderson 100 series windows 30,696
Skylights
Geothermal Unit 8,339.44
High efficiency HVAC 6,000
Demolition 2,800
Appliances 16,000
Spray Insulation 8,402.56
Drywall 7,000
water recycling system 6,325.12
Drip irrigation system
Total 175,513
RACI
TEAM MEMBER MANAGEMENT QUALITY CONTRACT RESEARCH
CHRISTIAN GONZALEZ R A C I
TAMIKA ROLAND A C R I
ALEX TORRES I R A C
TERIA EDWARDS I A C R
• 10 Anderson 100 series triple pane window 5’10”x2’9.5” (item number 32454900) for $765
• 1 Anderson 100 series triple pane window 3’x 4’6” (item number 458401-2A) for $385
• 2 Anderson 100 series triple pane window 5’10”x 1’ 10.5” (item number 32495600) for $565
• 3 Anderson 100 series triple pane window 5’10”x 4’6.5” (item number 33182210) for $915 each
• 4 Velux electric skylights 22.5”x 22.5” (item number 54622-5WS) for $4,100
Anderson Windows and Doors company will deliver and install all the windows on April 21,2011 through April 25, 2011 as stated in the signed
contract for a cost of $30,696 at 12602 Bayou Mead Ct Humble Texas 77346. Payments will be made at 25 percent completion, 50 percent
completion, 75 percent completion, and after the project manager Christian Gonzalez signs off on the 100 percent completion of the deliverable as
agreed upon in the contract.
Sow’s for Appliances
Light switches, receptacles, light bulbs, washer, dryer, tubs, faucets, and toilets will be delivered to the 12602
Bayou Mead Ct., Humble Tx 77346 on April 17, 2011 at 9:45 am at a total cost of $16,000.
Innovative Contractors will purchase from LOWES six Lutron 600- Watt White Preset Dimmer switches with standard light
switch (item number 295068) for $24.99 each, 22 Somerset Collection rotating duplex receptacles with plates(item number
29669) at a cost of $25.00 each, and two cases of Bright Effects 24 pack light bulb commercial box(item number 88959) for
$39.99 per pack. The total cost for the light switches, receptacles, and light bulbs is $780 and they will be delivered to the
12602 Bayou Mead Ct., Humble Tx 77346 on April 17, 2011 at 9:45 am.
Innovative Contractors will procure from LOWES an Electrolux 5.1 cubic foot electric washer (model EWMGD70JSS) and an
Electrolux 8.1 cubic foot electric dryer (EWMGO80JSC) for $1299.99 each. A two warranty is also purchased for the washer
and dryer for $700.00 each or $1,400.00, bringing the total $4000.00. The washer and dryer will be delivered to the 12602
Bayou Mead Ct., Humble Tx 77346 on April 17, 2011 at 9:45 am.
Innovative Contractors will purchase four Kohler Cimarron White High-Efficiency Water Sense Round Toilets(item number
39090) for $199.00 each, 7 sink faucets for 98.58 each, 3 Delta chrome tub faucets(item number 89235) for $84.99 each, and 3
Delta chrome shower faucets(item number 253503) for $115.00 each. The toilets and faucets will be delivered to the 12602
Bayou Mead Ct., Humble Tx 77346 on April 17, 2011 at 9:45 am.
SOW
Innovative Contractors will purchase from LOWES the SOK 72” x 42” high efficiency tub (item number k-1100-2G) and a 2
year warranty for $8,000. Also procured is two KOHLER Villager 60” x 32” tubs(item number 333860) for $328.00 each. The
total cost for the three tubs is $9,000 and the tubs will be delivered to the 12602 Bayou Mead Ct., Humble Tx 77346 on April
17, 2011 at 9:45 am.
SOW’s
•Innovative Contractors contracted JTB Services to Demolish and remove sheetrock, insulation,
windows and siding for $2,800 and a schedule of two days.
•Also contracted is X-RAIN to install the water recycling system and the drip irrigation system for
$6,325.12 with a schedule of three days.
Innovative Contractors will contract the JTB Services for the Demolition of sheetrock and removal of windows at 12602 Bayou Mead Ct
Humble Texas 77346.
• Removal of sheetrock at all exterior walls
• Removal of any existing insulation in exterior walls
• Removal of any existing insulation in attic cavity
• Removal of windows and siding
• Removal of trash off site
JTB Services will be demolishing and removing insulation and sheetrock for $2,800.00 and have the work completed in two days. An
initial payment of $500.00 was made and the final payment of $2,300.00 will be made after the project manager Christian Gonzalez
signs off on the 100 percent completion of the deliverable as agreed upon in the contract.
Innovative Contractors will contract the X-RAIN for the installation of water recycling system and the drip irrigation system for 12602
Bayou Mead Ct Humble Texas 77346.
• Use of Drip line for shrubs and trees
• Use of “brown hose” placed around flower beds
• Installation of collection tanks
• Installation of area drains throughout property
• Installation of water pumps for drip line
• Final grading after installation
X-RAIN will install the in three days at a cost of $6,325.12. Payments will be made at 35 percent completion, 70 percent completion, and
the final payment will be made after the project manager Christian Gonzalez signs off on the 100 percent completion of the deliverable as
agreed upon in the contract.
Constraints
Budget:$205,000
Time: 2 months
Local Contractors
On-Grid Power
LEED Certified
15 rating
Quality
TQM
Attention to Detail
Customer Satisfaction
Return On Investment(ROI)
Rebates and tax Credits
Risks
PROBABILITY OF LOW MEDUIM HIGH
IMPACT
Failed Permit Schedule: + 1 week
retrieval Cost: $2,000
Contractor failing to Schedule: + 1 week
complete work Cost: +$4,000
No local suppliers or Schedule: + 1 week
contractors Cost: +$4,000
Contractor failing to complete work- Research has been done to locate contractors with excellent work history and
good recommendations from previous clients.
Unsealed valves- pressure tight valves will be used when constructing the deliverables. Clamps will also be
installed to reduce the risk of a leak.
No local suppliers or contractors- Research was made through the internet, phone calls, faxes, and expert
judgment to locate suppliers and contractors within 30 miles.
Hitting a cable, gas line- The cable and gas companies have marked all locations of any lines that are buried.
Electrical problem- A professional electrician with extensive work history has been contracted to complete any and
all electrical connections.
Theft- The house has an alarm system that has been activated and will be running through the duration of the
project. Materials procured will be delivered 2 days before installation and will be left within the house.
Solar Panel Damage- Makrolon will be installed on top of the solar panels to protect it from weather and debris.
Received Damaged Material- QA will inspect the materials when received and in the event it is unnoticed
contractual obligations deem the supplier the one to replace it.
Organizational Chart
Catalina & Rafael Gonzalez
David Belton
Clients
Teria Edwards
Tamika Roland Alex Torres Research Analyst
WBS
Project Energy Home
1.0 Research 2.0 Preparation 3.0 Execution 4.0 Efficiency Test 5.0 Closing
WBS
Project Energy Home
1.0 Research 2.0 Preparation 3.0 Execution 4.0 Efficiency Test 5.0 Closing
WBS
Project Energy Home
1.0 Research 2.0 Preparation 3.0 Execution 4.0 Efficiency Test 5.0 Closing
Project Schedule
EVM
CALCULATING EARNED VALUE (ALL NUMBERS ARE IN THOUSAND)
Cumulative Actual 9.6 9.6 9.6 9.6 9.6 9.6 9.6 Value
Website
http://687842294512203611.weebly.com/index.html
Work Cited
http://www.apowersolutions.com/
http://www.hgtvpro.com/hpro/bp_green_building/article/0,3140,HPRO_29336_549997
5,00.html
http://www.geocomfort.com/products/model/gtc-two-stage-split-series
http://www.GE.com
Expert Judgment
Christian Gonzalez
Alex Torres