1. Electrical work Wiring all floors (2 contractors) - 1week, 4 worker = 4*200*5=4000 * 2 contractors = INR 8000 2.

. Final Painting All floors (2 contractors) 2 week, 6 workers, 2 team = 6*200*5=6000*2 =INR 12000 3. Doors all floors - Ordinary commercial doors = 25 * 1000 = INR 25000 4. Door fixing labor 1 team, 3 * 300 * 5 = INR 4500 5. Windows (interior and Exterior) 2 contractors 25Sqft*100 = 2500 * 40 = INR 100000 # 6. Tiles all floors 2 contractors 30 * 50 * 30 = 45000 INR 7. Tiles labor 6 ppl * INR300 * 5 days * 2 team = 18000 INR 8. Exterior finishing (around the building, walls and pathways) 2 contractors , 2 weeks * 5 days * 300 INR * 2 Con * 4 PPL =24000INR 9. Plumbing, water and pipelines all floors 2 contractors (new) = 5 ppl * 5 days * 300 = 1500 * 2 team = 3000 10.