You are on page 1of 3

July 04, 2011

MRS. MEDELINE J. MALLARI/ DRA.VERONICA MALLARI-DENIEGA President MALLARI-DENIEGA DEVELOPMENT CORPORATION Lapuan, Don Marcelino Davao del Sur

Madame,

We would like to request for a second billing for theConstruction ofPETRON MicrofillingGas bar station located @ Aurora-Corregidor Street,Digos City, in the amount of FIVE HUNDRED FIFTY THOUSAND PESOS ONLY(P 550,000.00) lessOne Hundred Twenty One Thousand Pesos(P 121,000.00), 22% as replenishment/payment from the amount of Five HundredThousand(P 500,000,00)Pesos released last June 16, 2011 as Mobilization/Initial Fee. The expected amount to be released in this billing is Four Hundred Twenty Nine Thousand( P 429,000.00) Pesos Only. As of July 02, 2011, we were able to accomplished 22%of the total agreed work items with the following accomplishments:

ITEMS OF WORK A. 1. 2. 3. 4. B. 1. 2. 3. PRE-CONSTRUCTION

PERCENT ACCOMPLISHED

Plans Preparation(Signature & seals) - 100% Cost estimates (Materials & Labor) - 100% Specifications - 100% Clearances &Permits( Zonal, CNC, Building) - 100% CONSTRUCTION Mobilization - 100% Bunk House - 100% Perimeter Fence(Laminated Sack) - 100%

4.

Laying out stakes

- 100%

C. 1. 2. 3. a. b. c. d. D.

CONSTRUCTION PROPER Excavation (Cashier s Booth) -100% Backfilling and Compaction(Cashier s Booth) - 30% Reinforced Concrete Works Column Footings(Cashier s Booth) - 100% Footing Tie-Beams (Cashier s Booth) -100% Columns (Cashier s Booth) - 100% Reinforced Beams (Cashier s Booth) - 100% FABRICATION OF STEEL TRUSS (WELDING) (Cashier s Booth) - 95% REINFORCED MASONRY WORKS(Concrete Hollow Blocks) (Cashier s Booth) - 60%

E.

ADDITIONAL OR EXTRA WORKS A. CONCRETE FOOTINGS (ZOCALO) CONCRETE HOLLOW BLOCK FENCE/BOUNDARY

- 20%

Respectfully yours,

ROSNATALIE ABUDA MAHINAY

TRISERLITO REMONDE MAHINAY

You might also like