Professional Documents
Culture Documents
rating of 45 MW, a firing temperature of 900C (1650 F) and an air flow of 0.8 million kgs (1.8 million lbs) per hour. Through many changes and upgrades the latest Model F of the same Frame 7 series has a rating of 147 MW, a firing temperature of 1260C (2300F) and an air flow of 1.5 million kgs (3.3 million lbs) per hour. One of the major advances made was to air cool nozzles and buckets using bleed air from the compressor to increase the firing temperature while limiting the metal temperatures of the nozzles and buckets to withstand hot corrosion and creep. This limiting of the maximum temperature through air cooling while simultaneously increasing the mass flow with more air compressor capacity permits higher power output. To increase the final compressor pressure additional compressor stages are added on the compressor rotor assembly to give higher compression ratio thus providing additional turbine power output. Typical industrial gas turbine compression ratios are 16:1 and aeroderivative ratios are 30:1 with roughly 50 percent of the total turbine power of either type being required just to drive the compressor. Compressor blading is special stainless steel, possibly coated by electroplating with nickel and cadmium to resist pitting in salt and acid environments. Compressor designs have been quite effective, as evident by the 200,000-hour life of some early compressors installed in the 1950s. The gas turbine has the inherent disadvantage that reduced air density with high ambient temperature or high elevation causes a significant reduction in power output and efficiency, because the mass flow through the gas turbine is reduced. A 28C (50F) results in about a 25 percent output reduction and a 10 percent higher heat rate. Similarly, at 1000 meter (3300 ft) elevation the gas turbine output would be 15 percent lower than at sea level. Steam plants and diesels are not affected to the same degree by ambient air temperature and elevation changes.
However, there are weight and size limitations to aircraft engine designs, whereas the stationary power gas turbine designers are seeking ever larger unit sizes and higher efficiency. To emphasize this difference in approach, today the largest aeroderivative power gas turbine is probably General Electric's 40 MW LM6000 engine with a 40 percent simple-cycle efficiency and a weight of only 6 tons. This engine is adapted from the CF6-80C2 engine that is used on the CF6 military transport aircraft. By comparison, General Electric's largest industrial gas turbine, the Frame 9 Model F has an output of about 200 MW, an open-cycle efficiency of 34 percent, but is huge compared to the LM6000 and weights 400 tons. The aeroderivative is a light weight, close clearance, high efficiency power gas turbine suited to smaller systems. The industrial or frame type gas turbine tends to be a larger, more rugged, slightly less efficient power source, better suited to base-load operation, particularly if arranged in a combined-cycle block on large systems. There is no significant difference in availability of two types of gas turbines for power use, based on the August 1990 Generation Availability Report of the North American Electric Reliability Council. For the period 1985-1989 the average availability of 347 jet engines (1587 unit years) was 92 percent and that for 575 industrial gas turbines (2658 unit years) was 91 percent.
The control system on combined-cycle units is largely automatic so, after a start is initiated by an operator, the unit accelerates, synchronizes and loads with automatic monitoring and adjustment of unit conditions in accordance with present programs. The number of operators required in a combined-cycle plant therefore is lower than in a steam plant.
Refer To: World Bank, IEN Working Paper #35: "Prospects for Gas-Fueled Combined-Cycle Power Generation in the Developing Countries", May 1991.
has not been resolved, giving some uncertainty concerning the load dispatching of the combined-cycle units. 3 x 300 MW Gas Turbine Installation in Malaysia The Paka 900 MW (3 x 300 MW Alsthom-Hitachi blocks) gas-fueled combined-cycle plant in Malaysia has had serious problems due to gas bypass damper jamming and gas turbine start-up train torque converter bearing faults. Availability reportedly has been only 55 to 60 percent in the past, but corrections have been made and higher availability is expected. Some of the problems have been attributed to split contracts for the gas turbine, boiler and steam unit components with interface difficulties, particularly on control systems. The country is still planning to install a large amount of combined-cycle capacity in the 1990s (3,840 MW by 1999) expecting that "teething troubles" with the technology will be overcome. However, some gas-fueled steam capacity will also be installed, so that future power supply is not dependent on only one technology. 2 x 300 MW Installation in Pakistan 2 x 300 MW blocks of gas-fired combined cycle gas turbines were installed at Guddu, Pakistan. According to USAID's consultant, RCG/Hagler Bailley, Inc. the availability of the plant has been good in the 80-85 percent range but efficiency has been lower then expected. No clear explanation of the reasons for the shortfall is provided. Refer To: Annex 8 of the World Bank, IEN Working Paper #35: "Prospects for Gas-Fueled Combined-Cycle Power Generation in the Developing Countries", May 1991
Five Combined Cycle Plants in Mexico Mexico has the largest amount of combined-cycle capacity in any developing country totaling almost 1,900 MW at five plants. The units were installed in 1975-1986 and are typically dual-fueled, natural gas and distillate. The operating performance has not been good; unit availability factors range from 38 percent to 83 percent; efficiencies vary from 20 percent for units installed in 1975 to 39 percent for later units. Comision Federal de Electricidad does not plan to install any additional combined-cycle units, partly because of their poor operating record and also because there is surplus residual oil which can be used in steam plants. 300 MW Installation in Egypt A 100 MW steam addition to 8 x 25 MW General Electric gas turbines. This plant is a 300 MW Talkha gas/distillate-fueled combined-cycle in Egypt. USAID's consultant, RCG/Hagler, Bailley, Inc. has reviewed the operational performance of this plant and concluded that the availability of the plants has been quite reasonable -- in the 80-85 percent range -- but efficiency has been lower than expected without a clear explanation of the reasons for the shortfall. Gas turbine component failures are the cause of most of the forced outages on these two combined-cycle plants. Refer To: Annex 8 of the World Bank, IEN Working Paper #35: "Prospects for Gas-Fueled Combined-Cycle Power Generation in the Developing Countries", May 1991 772 MW Installation in Thailand The early operation of the gas-fueled, Bang Pakong 772 MW combinedcycle addition reportedly was troubled by low gas turbine start-up reliability, difficulties in fuel changeover, vibration, gas damper distortion, gas supply problems, and the lower system inertia of the combined-cycle units. The plant availability is understood to be only about 70 percent at present. Nevertheless, the Electricity Generating Authority of Thailand is planning to install more gas-fueled combinedcycled units to almost triple this type of capacity on its system by the end of the 1990s. Combined Cycle Installation in Bangladesh There are substantial gas reserved in the eastern half of Bangladesh, so combined-cycle technology should be a logical generation candidate
for this country. Unfortunately, the operating experience has been poor on a small, UK-fi.anced GEC combined-cycle unit installed at Ashuganj in the early 1980s. Based on this experience, the Bangladesh Power Development Board (BPDB) prefers to install gas-fired steam units. This situation is reflected in a recent article by a consultant on system planning activities in Bangladesh: "The BPDB have rather limited and somewhat unsatisfactory experience of their one CC unit, and their FORs for the smaller gas turbines which they have operated for a much longer period of time seem to be higher than average by a factor of at least two, and possibly more than three. Faced with these facts a cautious approach to planning was adopted using base-load regime but with high FORs for CC plant. With this approach, selection of CC plant by the program is limited and gas-fired steam plant claims most of the gas allocation available."