Agenda
Introduction to Work In Process Overview of Work In Progress Setting Up & Implementing WIP Create and Update Discrete Jobs Scheduling Discrete jobs Create and Update Repetitive Schedules Scheduling Repetitive production Work in Process Transactions - Moves and Resources Complete Discrete Jobs and Repetitive Schedules Work In Process Interfaces

Introduction to Work in Process


Oracle Work In Process is a complete production
management system. Work In Process supports discrete, project, repetitive, assemble-to-order, and work order-less manufacturing. Inquiries and reports give a complete picture of transactions, materials, resources, costs and job/schedule progress on the shop floor.

Introduction to Work in Process


Production Methods Discrete Discrete production records all production activities against a discrete job. It represents a plan to produce a specific quantity of an item on a specific date. All material issues (Manual and Backflush), and all resource charges (Automatic and Manual) are charged to a specific job Discrete job can produce Assemble to Order (ATO) items and Configure to Order (CTO) item.

Introduction to Work in Process


Production Methods Repetitive Repetitive production models high-volume production of standard items over a period of time. Production is recorded against a repetitive schedule that represents a plan to produce an item at a given daily rate for a period of time.

Overview of Work in Process


Overview of Manufacturing Support
Following types of jobs and schedules can be used to support specific manufacturing needs: Standard and Non-Standard Discrete Jobs Standard and Non-Standard Project Jobs Repetitive Schedules by Production Line/Assembly Final Assembly Orders Work order less completions

Overvi ew of Wo rk in Pr oc ess
Overview of Production Scheduling
Oracle Work In Process can be used to schedule production resources and materials, to meet customer delivery requirements and to maintain a smooth production flow. Scheduling establishes expected dates and times for material and resource requirements, as well as for the supply availability of assemblies built on the jobs and repetitive schedules.

Overview of Production Scheduling (Cntd..)


Production Scheduling includes: Loading/sequencing repetitive production by assembly/production line. Scheduling start / stop times for jobs, operations and resources to the minute. Scheduling fixed, variable and overlapping time elements. Forward, backward, manual and midpoint forward rescheduling. Automatically updating the master schedule.

Overvi ew of Wo rk in Pr oc ess

Overvi ew of Wo rk in Pr oc ess
Overview of Production Scheduling (Cntd..)
Work In Process uses two scheduling methods: Detailed Scheduling Repetitive Line Scheduling Note: Oracle Work In Process only provides unconstrained scheduling.

Overvi ew of Wo rk in Pr oc ess
Overview of Material Control
Oracle Work In Process gives the ability to control and monitor the materials used for production and to view how they flow from inventory to discrete jobs/schedules, and from the discrete jobs/schedules to inventory. Material transactions: Issue and Return Material to Inventory Back flush Material Replenish Material

Overvi ew of Wo rk in Pr oc ess
Overview of Material Control (Cntd.)
While defining jobs and repetitive schedules, Material can be controlled by: Combining bills of material with routings to create specific material requirements. Specifying when and where materials are to be issued or back flushed. Assigning Supply Types to control how materials are supplied.

Overvi ew of Wo rk in Pr oc ess
Overview of Shop Floor Control
Shop floor control helps manage the flow of production in a plant leading to efficiencies that can lower costs and help to meet the delivery commitments. Shop floor control options: Move assemblies within operations. Load move transaction information from external systems. Define and assign shop floor statuses. Auto-create purchase requisitions for outside processing operations . Rework problem assemblies. Scrap assemblies.

Overvi ew of Wo rk in Pr oc ess
Overview of Shop Floor Control (Cntd.)
There are five available intra-operation steps. Queue: Default intra-operation step for every operation in a routing Run: Assemblies which are ready to be worked on. To Move: Assemblies waiting to be picked up for next operation. Reject: Rejected Assemblies Scrap: Scrapped Assemblies

Overvi ew of Wo rk in Pr oc ess
Overview of Shop Floor Control (Cntd.)
Oracle Work In Process considers an assembly to have completed an operation if the assembly is at To Move, Reject, or Scrap steps. Oracle Work In Process considers an assembly to have not completed an operation if the assembly is at Queue or Run steps.

Overvi ew of Wo rk in Pr oc ess
Overview of Resource Tracking
A resource can be assigned to each operation on a Work In Process routing. A resource can be assigned manually, after creating a job or can be added to the operation while creating the routing. A resource resides within an operation, it can be a person, a machine, tools, services, etc. There are three resource charge types: -WIP Move
-Manual -PO Move/PO Receipt

Overvi ew of Wo rk in Pr oc ess
Overview of Importing Transactions
Import transactions enables users to: Access real time and accurate information to increase efficiency through out the fulfillment process. Key technology enablers Mobile Computing & Process Critical devices Wireless Networks Bar code Technology

Overvi ew of Wo rk in Pr oc ess
Overview of Work In Process Costing
Use WIP accounting classes to establish valuation and variance accounts. Use Standard, Average or LIFO/FIFO costing. Cost standard and non-standard asset discrete production by job. Cost jobs by project in Oracle Project Manufacturing Costing. Cost and report repetitive and non-standard expense production by period.

Overvi ew of Wo rk in Pr oc ess
Overview of Work In Process Costing (Cntd.)
Charge and report resource, outside processing, and overhead costs by activity. Track repetitive production costs by assembly on a line/ individual repetitive schedule. Track and report costs through the various stages of production. Period close costs are calculated when an accounting period is closed.

Setting Up & Implementing WIP


WIP Set up
1.Define WIP parameters (Req.) 2.Define WIP Accounting Classes (Req.) 3.Set WIP Profile Options (Req.) 4.Define Production Lines (Optional) 5.Define Repetitive assembly (Optional)

Setting Up & Implementing WIP


A
6.Define Schedule Groups (Optional) 7. Define Employees (Optional) 8.Define Employee Labor Rates (Opt.) 9. Define Shop Floor Statuses (Optional) 10.Define Job/Schedule Docs (Optional)

Setting Up & Implementing WIP


C
11.Define Operation Documents (Optional)

Setting Up & Implementing WIP


WIP Parameters WIP parameters define modes of operation and default
values that affect Work in Process WIP parameters can be used to define modes of operation and assign default values for various work in process functions. Only one set of WIP parameters can be defined per organization.

Setting Up & Implementing WIP


WIP Parameters Screen shots
(N) WIP > Set up > parameters
Determines how lot numbers are assigned to discrete jobs Options are job name & based on inventory rules

Determines which accounting class is used as the default if category default WIP accounting classes are not set up. Used to default in Standard/non-standard Discrete jobs & Work order-less completions

Determines whether the WIP jobs respond to Sales order changes .Options are Always/never /When linked 1 to 1 (ATO)

Setting Up & Implementing WIP


WIP Parameters Screen shots
Applicable only for average costing organizations Determines how resource costs are determined as assemblies are completed from jobs into inventory. System Calculated : resources can be costed at either the actual resource costs or at resource predefined cost depending on the System Option parameter . For assemblies from a non standard job with no routing, the resource rate from the Average Rates cost type is used. User Defined: you must choose a userdefined cost type using the Cost Type Parameter. This cost type is then used to determine the resource cost for the assemblies being completed.

Determines whether the Final Completion in the Completion Transaction window defaults o checked

Used only when system calculated option is selected. Use Actual Resources: Resources costs are determined based on the actual costs charged to the job. Use Predefined Resources: Resources costs are determined using the predefined resource cost.

Setting Up & Implementing WIP


WIP Parameters Screen shots
Determines which repetitive schedule variances are posted to the general ledger when an accounting period is closed.

Determines the time period within which the system automatically releases the next Unreleased schedule.

Setting Up & Implementing WIP


WIP Parameters Screen shots
Determines whether a scrap account is required when you use the Move Transactions window to move job and repetitive assemblies into and out of the Scrap intra-operation step of an operation. also determines how scrap transactions are processed.

Determines whether you can or cannot add an operation to a discrete job work in process routing during a move transaction.

Determines whether moves are disallowed if an intra-operation step that disallows moves exists at an auto charge operation and Intra-operation step between the From and To operations or at intervening intra-operation step at the From and To operations if they are direct charge.

Setting Up & Implementing WIP


WIP Parameters Screen shots
Determines which supply subinventory and, if required by the subinventory, locator are used when back flushing Operation Pull and Assembly Pull components that do not have defaults defined at the bill of material/item level

Determines how lots that are automatically selected, based on whether the Lot Selection Method parameter is set to Receipt Date or Expiration Date, are verified during back-flush transactions.

Determines how lot controlled Assembly Pull and Component Pull component items are selected during back-flush transactions. Not used for lot/serial controlled items

Setting Up & Implementing WIP


WIP Parameters Screen shots

Determines which intra-operation steps are enabled in WIP routing operations. The options are Queue, Run, To Move, Reject and Scrap. The Queue intra-operation step is automatically enabled for all operations and cannot be disabled. The To Move intra-operation step, even if disabled here, is automatically enabled for the final operations in routings so that assemblies can be completed into inventory.

Setting Up & Implementing WIP


WIP Parameters Screen shots floor status is assigned to the Determines which shop
Queue intra-operation step of an outside processing operation when you create discrete jobs and repetitive schedules. This status ensures that assembly moves from an outside processing resource operation can only be launched by the receipt of a purchase order in Oracle Purchasing.

Determines whether purchase requisitions are created for outside processing operations automatically or manually, and when in the manufacturing process they are created

Setting Up & Implementing WIP


WIP Accounting Classes
Accounting classes are assigned when jobs are defined and when repetitive assemblies are associated with production lines. Any number of WIP Accounting Classes can be defined and updated. The valuation and variance accounts that are associated with these accounting classes determine which accounts are charged.

Setting Up & Implementing WIP


WIP Accounting Classes Screen shots
(N) WIP > Set up > WIP accounting classes

Setting Up & Implementing WIP


WIP Accounting Classes
Standard Discrete Accounting Class An accounting class must be assigned to every discrete job, schedule and work order-less completion Accounting classes can be defined for each type of discrete production used: Standard Discrete Asset Non-Standard Discrete Expense Non-Standard Discrete Flow Manufacturing

Setting Up & Implementing WIP


WIP Accounting Classes
Expense Non-Standard Discrete Accounting Class Non-Standard Discrete Accounting classes can be used to group and report various types of non-standard production costs. Example: To track recurring expenses -- machine maintenance or projects with non-standard jobs. The valuation accounts carry the costs incurred on these expense jobs as an asset during the period and automatically write them off to variance accounts at period close.

Setting Up & Implementing WIP


WIP Accounting Classes
Asset Non-Standard Discrete Accounting Class If non-standard discrete jobs are used to track production costs as assets, an accounting class with a type of asset non-standard can be assigned . Asset non-standard discrete jobs are costed the same as standard discrete jobs.

Setting Up & Implementing WIP


WIP Accounting Classes
Repetitive Accounting Class These are used to group production costs and must be assigned to each repetitive line/assembly association that is created. Every schedule for that assembly on that line uses these accounts. Repetitive manufacturing costs can be analyzed by assembly regardless of the line on which it was manufactured by using the same accounting class for all lines that build that assembly.

Setting Up & Implementing WIP


WIP Accounting Class -Accounts
Material Valuation Account This is an asset account and tracks material costs. Under Standard Costing, it is debited at std cost at material issue to a job/schedule and credited when assemblies are completed, close a job/accounting period. Under Average Costing, this account is debited at the average cost at the time of issue transaction and is credited at assembly completion.

Setting Up & Implementing WIP


WIP Accounting Class
Material Overhead Valuation Account This tracks material overhead costs. Under Std Costing, it is debited at std cost at material issue with a overhead to a job. Under average costing, this account is debited at the average cost at the time of the issue transaction. When assemblies are completed and material overhead is earned, the material overhead account for the completion sub-inventory is debited.

Setting Up & Implementing WIP


WIP Accounting Class
Resource Valuation Account This tracks resource costs. Under Standard Costing, it is debited at std cost when resources are charged to a job/schedule and credited on completion of assembly. Under Average Costing, this account is debited and credited at the resource rate at the time the resource is charged.

Setting Up & Implementing WIP


WIP Accounting Class
Outside Processing Valuation Account This tracks outside processing costs. Under Standard Costing, it is debited at standard or PO cost when items are received for a job/schedule and credited at standard cost on completion of assembly. Under Average Costing, the behavior is the same as in Standard Costing.

Setting Up & Implementing WIP


WIP Accounting Class
Overhead Valuation Account This is an asset account and tracks resource or department overhead cost.

Setting Up & Implementing WIP


WIP Accounting Class
Material Variance Account This account tracks variances that occur when the previous level material costs charged to the job or schedule do not equal the previous level material costs that are relieved. This calculation gives you a net material usage and configuration variance.

Setting Up & Implementing WIP


WIP Accounting Class
Resource Variance Account This account tracks variances that occur when the this level resource costs charged to the job or schedule do not equal the this level resource costs that are relieved. Outside Processing Variance Account This account tracks the variances that are occur when the outside processing costs charged to the job or schedule do not equal the outside processing costs that are relieved.

Setting Up & Implementing WIP


WIP Accounting Class
Overhead Variance Account This account tracks the variances that are occur when the overhead costs charged to the job or schedule do not equal the overhead costs relieved from the job or schedule. Standard Cost Variance Account Applies only to Standard Discrete and Asset NonStandard. Its charged for the sum of all the elemental standard cost adjustments when standard cost update impacts an active job. Cost updates are not performed for repetitive schedules or expense nonstandard jobs.

Setting Up & Implementing WIP


WIP Accounting Class
Expense Variance Account Normally an expense account, this account is debited and credited when issuing and completing nonstandard expense jobs under both standard and average costing.

Setting Up & Implementing WIP


Shop Floor Statuses
Move transactions are controlled by assigning Shop Floor Statuses to intra-operation steps on the work in process routing. For example a Hold for Quality Check status can be assigned to an intra-operation step before moving to the next assembly step. Shop Floor Statuses can be assigned to any Intra operation step associated with a job/repetitive line/assembly.

Setting Up & Implementing WIP


Shop Floor Statuses
(N) WIP > Move Transactions > Shop Floor Statuses > Shop floor status

Setting Up & Implementing WIP


Schedule Groups
Flow schedules and discrete jobs can be assigned to the schedule groups defined. Jobs and flow schedules within a given schedule group can be sequenced. Sequencing jobs and flow schedules within a schedule group makes it possible to prioritize, for example, by customer. Schedule groups can be updated. Schedule groups that are assigned to jobs and flow schedules cannot be deleted.

Setting Up & Implementing WIP


Schedule Groups
(N) WIP > Setup > Schedule Group Screen shots

Setting Up & Implementing WIP


Labor Rates
Used for defining hourly labor raters to reflect the actual labor rates. The effective date of the hourly labor rates can be added, deleted, and updated for person-type resources (employees). Multiple hourly labor rates can be defined for the same employee, as long as each rate has a different effective date.

Setting Up & Implementing WIP


Labor Rates
(N) WIP > Setup > Employees > Labor Rates Screen shots

Setting Up & Implementing WIP


Production Lines
A production line describes a unique set of operations, departments, and/or manufacturing cells that produce one or more of products. Production lines can be associated with repetitive assemblies, discrete jobs, flow routings, schedules, and work order-less completions. Production lines can be defined and updated but cannot be deleted.

Setting Up & Implementing WIP


Production Lines
(N) WIP > Setup > Production Lines Screen shots

Setting Up & Implementing WIP


Operation Documents
Operation Documents can be defined for discrete jobs, repetitive schedules, and job/schedule operations. Operation Documents can then be attached to discrete jobs, repetitive schedules, and operations as required.

Setting Up & Implementing WIP


Operation Documents
(N) Oracle Work in Process > Set Up > Defining Operation Documents

Setting Up & Implementing WIP


Profile Options
TP:WIP: Background Shop Floor Material Processing: Used only when the TP: Move Transaction profile is set to Background processing & for a move completion/move return /operation pull back-flush transaction. Available Values: Background Processing: Periodic Processing Concurrent Processing: Inventory Transaction processor is launched. Online Processing (Default): Move transaction processor processes the shop floor material back-flush transactions online by calling the inventory material transaction processor.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Completion Material Processing Controls material processing of assembly completion, assembly return, and assembly completion back-flush transactions initiated using the Completion Transactions window Available Values: Background Processing, Concurrent Processing & Online Processing (Default) Note: If TP:WIP: Completion Transactions Form profile is set to Background processing, this profile is not used. Also, if TP:INV: Transaction Processing Mode profile is set to Form level processing in average costing scenario , this profile must be set to Online for sequential transaction procession.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Completion Transaction Form Determines whether completion transactions are processed online or in the background when transacting assembly completions using the Completion Transactions window. Available Values: Background Processing, Online Processing (Default) Note: Also, if TP:INV: Transaction Processing Mode profile is set to Form level processing in average costing scenario , this profile must be set to Online for sequential transaction procession.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Completion Transactions first field Determines which field the cursor defaults to when you first enter the Completion Transactions window. Set this option based on your predominant manufacturing environment Available Values: Line, Assembly, Job (Default) , or Sales Order.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Concurrent Message Level Determines the level of detail reported in the move transaction concurrent log file during move transaction validation and processing. Available Values: -Message level 0 (Default) : Reports errors only. -Message level 1 : Reports processing activities and errors. -Message level 2 : Reports and time stamps processing activities and errors.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Material Transaction Form Controls the processing of component issue and return transactions entered in the WIP Material Transactions window. Available Values: Background Processing, Concurrent Processing & Online Processing (Default) Note: Also, if TP:INV: Transaction Processing Mode profile is set to Form level processing in average costing scenario , this profile must be set to Online for sequential transaction procession

Setting Up & Implementing WIP


Profile Options
TP:WIP: Material Transactions First Field Determines which field the cursor defaults to when you first enter the WIP Material Transactions window. Set this option based on your predominant manufacturing environment Available Values: Line, Assembly, Job (Default) , or Sales Order.

Setting Up & Implementing WIP


Profile options
TP:WIP: Move Transactions: Determines How move transactions performed using the Move Transactions form Available values - Background processing: Processed on a periodic basis -(Default) Online processing: The transaction is processed while saving and control is returned once transaction processing is done. Note: Also, if TP:INV: Transaction Processing Mode profile is set to Form level processing in average costing scenario , this profile must be set to Online for sequential transaction procession.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Move Transactions First Field Determines which field the cursor defaults to when you first enter the WIP move Transactions window. Set this option based on your predominant manufacturing environment Available Values: Line, Assembly, Job (Default) , or Sales Order.

Setting Up & Implementing WIP


Profile Options
TP:WIP: Move Transaction Quantity Default Indicates if and how move transaction quantities are defaulted. Available Values: None: No transaction quantity is defaulted. Minimum Transfer Quantity: Transaction quantity defaults if the minimum transfer quantity is less than or equal to the available quantity. If the minimum transfer quantity is more than the available quantity then the available quantity is defaulted Available Quantity: If the available quantity is not zero, the transaction quantity defaults to the available quantity. .

Setting Up & Implementing WIP


Profile Options
TP:WIP: Operation Back flush Setup Controls the back-flush setup used in the Move Transactions Window. It also determines how component lot numbers are derived. Available Values: -Background processing: Use this option only when lot numbers are automatically assigned. -Online processing: Use this option when lot/serial numbers must be manually assigned

Setting Up & Implementing WIP


Profile Options
TP:WIP: Shop Floor Material Processing Controls processing of operation and assembly pull back-flush, assembly scrap, move completion, and move return transactions from the Move Transactions window. Available Values: -Background processing: Use this option only when lot numbers are automatically assigned. -Concurrent processing: -Online processing: Use this option when lot/serial numbers must be manually assigned

Setting Up & Implementing WIP


Profile Options
TP:WIP: Work Order-less Default Completion Determines the default for the Scheduled flag in the Work Orderless Completions window. Available Values: -Scheduled : The Schedule flag defaults to checked. Use this option if most of the work orderless completions are based upon flow schedules. -(Default) Unscheduled : The Scheduled flag defaults to unchecked. Use this option if most of the work orderless completions are manually entered .

Setting Up & Implementing WIP


Profile Options
WIP: Default Job Start Date Determines whether the start dates for jobs default to the current date and time or not at all when defining jobs in the Discrete Jobs window. Available Values are Yes or No (Default) WIP: Define Discrete Job Form Indicates how to load the bill of material and routing information when defining jobs in the Discrete Jobs window. Available Values: -Concurrent definition: -(Default) Interactive definition:

Setting Up & Implementing WIP


Profile Options
WIP: Discrete Job Prefix Specifies the job prefix to use when auto-generating job names in the Discrete Jobs, Simulate Discrete Jobs, Import Jobs and Schedules, and Auto-Create windows in Work in Process, and in the Planner Workbench window in Oracle Master Scheduling/MRP and Oracle Supply Chain Planning. WIP: Enable Outside Processing Workflows Determines whether or not outside processing workflows are enabled. The options are Yes and No (Default)

Setting Up & Implementing WIP


Profile Options
WIP: Exclude Open ECOs Determines whether engineering change orders (ECOs) with Open statuses are excluded while defining jobs/schedules. If so, only ECOs with Release, Schedule, and Implement statuses are implemented when you choose a bill of material revision or revision date and the bill of material is exploded. This profile option also controls whether revisions associated with open ECOs can be selected in the WIP Material Transactions. WIP: Job Name Updateable Determines whether you can update the names of existing jobs in the Discrete Jobs window.

Setting Up & Implementing WIP


Profile Options
WIP: Move Completion Default Determines the default transaction type for the Move Transactions window. If you Yes is specified , the transaction type defaults to Complete. Otherwise, the transaction type defaults to Move. WIP: Requirement Nettable Option Determines which sub-inventories to include when displaying onhand quantities in the Material Requirements and View Material Requirements windows. Available values -View only nettable subinventories: -View all subinventories (Default) :

Setting Up & Implementing WIP


Profile Options
WIP: See Engineering Items Determines whether jobs and schedules for engineering items can be defined and whether engineering items can be added as material requirements.

Cr eate and Update Di sc rete Jobs


Discrete Life Cycle
START

1.Set up discrete manufacturing 2. Define Discrete Jobs 3.Update Discrete Jobs 4.Build Discrete Jobs 4.Close Discrete Jobs

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
(N) WIP > Discrete > Discrete Jobs
Job Quantities are used to determine: Material requirements, Department schedules, Resource load & Job dates. Job Name uniquely identifies the job for the Issuing components, Moving/scrapping/ completing assemblies ,Charging resources/ overheads and Defining/ updating job definition

Various stages in the life cycle of the discrete job. When defining a job, only Unreleased/ Released/On Hold statuses exist

Standard - A discrete job controlling material/ operation requirements to build assemblies/collect manufacturing costs Nonstandard A discrete job controlling material and collects costs for miscellaneous activities, such as Rework, service repair ,Upgrade etc

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
Routing revision allows you to select which version of the routing you want to use to schedule the operations and resources.

subinventory in which completed assemblies will be housed.

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
Bill Revision allows you to select any valid version of the bill of material you want to use to determine the material requirements for the job

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
You can view material requirements and operations from the Discrete Jobs window as you define and update jobs

Create and Update D iscrete Jobs


Creating Components
When a job is defined , WIP copies the assembly bill created in BOM. It then creates material requirements for the copied bill of material components. Supply types can be used to control how to supply the components for the material requirements on the job.

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
When you click the Components button on the discrete jobs form, the Material Requirements window is displayed with the component information. Here you can view each components Main, Quantity, Supply, Comment, and ATP information. For those components with ATP rules, you can perform an ATP check from this window

Create and Update D iscrete Jobs


WIP Supply Types
Supply types are defined in the bill of material. If the supply type is changed on discrete job, it overrides the supply types for all the components on that job.
NAME Based on bill Assembly Pull Bulk Operation Pull Push Vendor DESCRIPTION Component requirements with supply types from BOM or those on the Item Master are defaulted when a job is defined. Assembly pull components are issued to the job when the assembly is completed into inventory. These components are not transacted automatically in a job. Operation pull components are issued to the job when the operation is completed. Material is issued manually before consumption Vendor supplies material directly to WIP

Create and Update D iscrete Jobs


WIP Supply Types
For Phantom supply type , Phantom subassemblies are exploded and their components become material requirements. Following BOM parameters to control the inheritance of a parent phantoms operation sequence and whether or not resources and overheads on phantom routings are recognized for costing and capacity planning purposes. Use Phantom Routings Inherit Phantom Inherit Phantom Operation Sequence

Create and Update D iscrete Jobs


Creating Operations
When a job is defined , operations and resource requirements are created based on the assembly routing. The routing created in BOM is copied to become a work in process routing that can be modified without affecting the BOM routing. Dates and times for the operations, resource requirements, and material requirements needed to build the job can be scheduled using detailed scheduling.

Cr eate and Update Di sc rete Jobs


Discrete Job Definition
When you click the Operations button, the Operations window is displayed. Here you can view each operations Main, Quantities, Dates, and Description. Also, from this window, you can display the resource requirements for a selected operation.

Create and Update D iscrete Jobs


Update Discrete Job Data
In a discrete job, following information can be updated: Header information, based on the job status Routing information Bill information Sales order information Job operations Job requirements Note: If the profile option WIP: Job Name Updatable is set to No, the name of the existing job cannot be updated .

Create and Update D iscrete Jobs


Update/Delete Discrete Job Operations
An operation from a discrete job can be updated /deleted if: There are no assemblies at the operation. No assemblies have been completed at the operation. There are no pending transactions in the open move interface table. No resources at the operation have been charged. There are no pending transactions in the open resource interface If an operation is deleted , WIP reassigns its material requirements to the first operation in the routing, or to operation sequence 1 if there are no operations in the routing.

Create and Update D iscrete Jobs


Update/Delete Resources
A resource requirement from a discrete job can be deleted if: That resource has not been charged to the operation. There are no pending transactions in the open resource interface table.

Create and Update D iscrete Jobs


Discrete Work Station
Tool to graphically view and perform manufacturing activities on the shop floor. This workstation enables to quickly and easily obtain information critical to supporting business decisions and controlling daily shop floor activities. Production operators can: Quickly and easily obtain component and resource requirements, as well as performance measurements. Perform shop floor transactions without returning to the WIP menu.

Create and Update D iscrete Jobs


Discrete Work Station
(N) WIP > Discrete > Discrete Workstation

Create and Update D iscrete Jobs


Using Non standard Discrete Jobs
Advantages: Control materials and resources for nonstandard projects. Track costs for various activities. Report on all aspects of production. Manage the activities like :
Rework Upgrades Field service repair and maintenance Disassemblies Engineering prototypes miscellaneous activities

Create and Update D iscrete Jobs


Features of Nonstandard Jobs
Assign any predefined bill/routing of material to a nonstandard job. Specify an assembly on a nonstandard job. Include a job quantity on a nonstandard job. Add the same assembly which is being built as a material requirement on the jobs bill of material. Use expense costing to periodically write nonstandard production costs to expense accounts Define the WIP accounting class as an asset or as an expense to the job.

Scheduling Discrete Jobs


Scheduling Jobs
Business Needs Planning material and resources quickly and accurately Establishing appropriate planning time fences for products Creating purchase orders for material accounting for vendor lead time Scheduling material to arrive at the operation where it is consumed Scheduling each resource at the operation where it is consumed Promising accurate product shipment dates

Scheduling Discrete Jobs


Scheduling Methods:
Oracle Manufacturing supports two scheduling methods for discrete production: dynamic lead-time offsetting and detailed scheduling. Dynamic Lead-Time Offsetting: Estimating the start date of an order, an operation, or a resource based on order quantity, lead times, and the workday calendar.

Scheduling Discrete Jobs


Scheduling Methods:
Detailed scheduling: Jobs are scheduled to the minute based on detailed resource availability and usages. Oracle Bills of Material calculates manufacturing lead times using detailed scheduling. Detailed scheduling is the most precise method in Oracle Manufacturing.

Scheduling Discrete Jobs


Lead Time Elements
Preprocessing lead time: The time required to release a purchase order or a job from the time the requirement is known. Post processing lead time: The time to make a purchased item available in inventory from the time its received. Processing lead time: The time required to procure or manufacture an item. Processing lead time includes the fixed and variable portions of lead times.

Scheduling Discrete Jobs


Lead Time Elements
Cumulative manufacturing lead time: Total time required to make an item if all raw materials are in stock but all subassemblies will have to be made level by level; Oracle Bills of Material automatically calculates this value. Cumulative total lead time: Total time required to make an item if no inventory existed and all the raw materials and make all subassemblies will have to be ordered level by level; Oracle Bills of Material automatically calculates this value.

Scheduling Discrete Jobs


Lead Time Elements
Processing Lead time: Oracle Bills of Material computes the fixed and variable portions of processing lead time using routings and detailed scheduling. Fixed lead time: That portion of time required to build an assembly that is independent of order quantityfor example, setup or teardown. Variable lead time: That time required to produce one additional unit of an assembly. These lead times are used by Oracle Manufacturing in dynamic lead-time offset calculations

Scheduling Discrete Jobs


Lead Time Elements
Calculating Processing Lead Time for Manufactured Items: The algorithm schedules one discrete job for a quantity of zero (fixed lead time) and a second discrete job for the leadtime lot-size quantity (variable lead time). When computing processing lead time, all calendar days are considered as workdays, regardless of days off or workday exceptions.

Scheduling Discrete Jobs


Detailed Scheduling
Business Needs Detailed scheduling is a method of scheduling production that considers minute-to-minute resource availability information as well as exact routing resource requirements Job completion dates and times for assembly supply availability Job start dates and times for job release Operation starts and completion dates and times . Operation start dates and times for component demand requirements Resource load information for capacity planning

Scheduling Discrete Jobs


Detailed Scheduling: Key Terms
Resource requirement: The amount of a resource that is required to perform an activity in a routing of a job. Resource availability: The availability of a resource, taking into account the manufacturing calendar, including workday exceptions, shifts, and shift exceptions. Critical path: The sequence of resources in the routing of a job that are used to schedule the job. Overlap: A situation in which two or more scheduled resources can operate at the same time. This can be in one operation or across consecutive operations.

Scheduling Discrete Jobs


Scheduling Rules
All resources that have the Scheduled attribute set to Yes, Prior, or Next must have a time-based unit of measure. All resources that have a unit of measure that is not timebased, such as U.S. dollars, kilograms, or gallons, must have the Scheduled attribute set to No. Oracle Capacity performs resource load analysis only for resources with a time-based unit of measure.

Scheduling Discrete Jobs


Scheduling Methods: Oracle WIP Versus Oracle Planning
Oracle WIP Schedules all discrete jobs backward or forward Oracle Planning Schedules all planned orders backward from the due date

Schedules jobs into the past if Compresses jobs to start on the backward scheduling past the current current date if the calculated date start date would be in the past Uses detailed scheduling to schedule discrete jobs with routings to the minute Uses lead-time offset to schedule discrete jobs without routings to the day Uses lead-time offset to schedule planned orders for assemblies with routings and without routings to the day

Create and update Repetitive schedules


Repetitive Schedule

A repetitive schedule builds an assembly on a production line at a specific daily rate for a specific number of processing days.

Create and update Repetitive schedules


Discrete Life Cycle
START

1.Set up Repetitive manufacturing 2. Define Repetitive Schedules 3.Update Repetitive Schedules 4.Build Repetitive Assemblies 5.Stop repetitive schedules and analyze repetitive Costs

Create and update Repetitive schedules


Repetitive Schedule Elements
Daily Quantity: The number of completed assemblies that are planned to be produced each day. The daily rate can be any positive number/decimals. Days: The planned number of working days, from the first unit start date to the last unit start date. The processing days can be any positive number/decimals. Total Quantity: The number of completed assemblies that are planned to be produced. Note: If you enter any two of the three values, the third one is automatically computed.

Create and update Repetitive schedules


Repetitive Schedule Dates
First Unit Start Date (FUSD): The date and time to begin production of the first assembly on a repetitive schedule. Equal to start of lead time First Unit Completion Date (FUCD): The date and time to complete production of the first assembly on a repetitive schedule. Equal to FUSD plus the lead time Last Unit Start Date (LUSD): The date and time to begin production of the last assembly on a repetitive schedule Calculated based on the FUSD, repetitive processing days, and hourly production rate

Create and update Repetitive schedules


Repetitive Schedule Dates
Last Unit Completion Date (LUCD): The date and time to complete production of the last assembly on a repetitive schedule. Equal to LUSD plus the lead time

Create and update Repetitive schedules


Repetitive Schedule Definition
(N) WIP> Repetitive Manufacturing > Associating Lines and Assemblies

The hourly production rate determines how fast each line can produce this assembly.

Create and update Repetitive schedules


Repetitive Schedule Definition
(N) WIP> Repetitive> Repetitive Schedules

Various stages in the life cycle of the Repetitive schedule. When defining a schedule , only Unreleased/ Released/On Hold statuses exist

Scheduling Repetitive production


Business needs:
Optimized use of line capacity Effectively sequenced repetitive production Time-phase repetitive component demand and assembly availability

Scheduling Repetitive production


Elements of Repetitive Line Scheduling
Minimum rate: The minimum number of completed assemblies a production line can produce per hour. Maximum rate: The maximum number of completed assemblies a production line can produce per hour. Line lead time: Time required to complete the 1st assembly on a production line starting from the 1st operation to completion into inventory. Hourly production rate: The rate at which the production line can assemble items.

Scheduling Repetitive production


Elements of Repetitive Line Scheduling
Line start time: The time a production line starts running every day. The line start time is used to schedule repetitive schedules on a line. Line stop time: The time a production line stops running every day. The line stop time is used to schedule repetitive schedules on a line. Daily line capacity: The daily production rate of assemblies on a production line. This is equal to the hourly production rate times the line production hours.

Scheduling Repetitive production


Elements of Repetitive Line Scheduling
Daily rate: The number of completed assemblies a repetitive schedule plans to produce per day. Also known as a production rate. Repetitive processing days: The number of days you plan to work on a repetitive schedule, from the first unit start date to the last unit start date.

Scheduling Repetitive production


Repetitive Line Scheduling
Daily quantity is used to specify how many assemblies per day to build Days are used to specify for how many days an assembly is to be produced at the specified rate Line minimum and maximum daily rate can be used as a guideline for the daily quantity of schedule

Scheduling Repetitive production


Repetitive Line Scheduling
Can specify to the minute the start and completion dates and times of your repetitive schedule Can schedule to the minute each day the operations and resources of the schedule. Can schedule all the requirements based on operation dates each day of the schedule. Must enter either the first unit start date and time and the first unit completion date and time, or the last unit start date and time and the last unit completion date and time, in order to define the lead time for a routing less assembly running on a routing-based line.

Scheduling Repetitive production


Repetitive Line Scheduling
The top horizontal line indicates the constant hourly production rate that was defined for the line for this assembly. Schedule production hours = quantity per day/ hourly production rate.

Scheduling Repetitive production


Repetitive Line Scheduling
Each shaded area represents the quantity produced (the daily rate) in a day. The un shaded area represents idle time for this assembly on this line. The total quantity for the schedule is processing days times daily rate i.e.. the sum of all the shaded areas.

Scheduling Repetitive production


Repetitive Line Scheduling
Repetitive schedules based on suggestions from Oracle Planning or any other planning system can be defined. Schedules are loaded into Oracle WIP with a status of PendingMass Loaded due to following reasons: -MRP does not consider existing schedules.
Implementing these schedules without looking at existing ones can result in overproduction. -MRP-suggested schedules may overlap with existing schedules, which is not allowed.

Scheduling Repetitive production


Repetitive Line Scheduling
Not allowing overlap enables WIP to perform flow charging for repetitive schedules. (Flow charging is when a repetitive assembly and line is charged rather than a specific job. It is based on FIFO.

Work in Process Transactions Moves and Resources


Work In Process Flow -Definitions
Types of Material Transactions Issue transaction is a material transaction to issue component items from inventory to work in process. Replenishment transaction is a material transaction to stage components in advance of backflushing. Return transaction is a material transaction to return components from WIP back to inventory. Return transactions increase WIP material requirements, inventory balances, and valuation, and decrease WIP valuation.

Work in Process Transactions Moves and Resources


Work In Process Flow -Definitions
Types of Material Transactions Material issue transactions fulfill WIP material requirements on jobs or schedules. These reduce inventory balances and valuation & incur WIP costs and increase WIP valuation. Supply types are used to control how components are supplied to fulfill material requirements. Push issue transaction is a material transaction to issue component items from inventory to work in process before you manufacture the assembly.

Work in Process Transactions Moves and Resources


Work In Process Flow -Definitions
Types of Material Transactions Backflush transaction is a material transaction that automatically issues component items into work in process from inventory when you move or complete the assembly. A backflush transaction is also known as postdeduct or pull.

Work in Process Transactions Moves and Resources


Move Transactions
Move transactions move assemblies from any operation on the routing to any other operation. Moves normally follow the sequence as per routing. Move Transactions can initiate other transactions - Backflush issue transactions for components with supply type Operation Pull - Automatic resource transactions for resources with autocharge type WIP Move - Overhead transactions for overheads with basis type Item or Lot

Work in Process Transactions Moves and Resources


Move Transactions
Intraoperation moves are assembly moves within an operation. Intraoperation steps are phases within an operation used to track assembly locations in detail. The steps are Queue, Run, To Move, Reject, and Scrap. Operation completions occur when quantities move into to move, reject, or scrap. Interoperation moves are assembly moves from one operation to another in a routing.

Work in Process Transactions Moves and Resources


Move Transactions
autocharge flag controls operation completions and associated automatic transactions. Count point determines the default for the next operation for a move transaction. Backflush flag controls when to process Backflush transactions.
Its advisable that the Backflush flag of the last operation on a routing always be set to Yes, to make sure that all components are issued.

Work in Process Transactions Moves and Resources


Backward Move Transactions
Backward move is used to correct a mistake or to perform additional work at a previous operation. An operation can be uncompleted by reversing any of the moves that constitute operation completion When an operation is uncompleted, system automatically reverses any backflushing transactions that have taken place during the forward move. On uncompletion, system automatically reverses WIP move resource charges. Automatic resource charges for Lot-based resources are reversed when all assemblies have been uncompleted at the operation.

Work in Process Transactions Moves and Resources


Move Transactions
WIP (N) Move Transaction > Move Transactions

Work in Process Transactions Moves and Resources


Overcompletions
Can over move or over complete within tolerance Move and complete more assemblies than at operation

Assignment of Shop Floor Statuses


(N) Move Transaction > Shop Floor Statuses > Assign Shop Floor Statuses System provides an option that prevents users from performing move transactions over operations and intraoperation steps that have No Move statuses, depending on the autocharge types of the operations.

Work in Process Transactions Moves and Resources


Costing Move Transactions: Accounting Entries
Costing Backflush Material Transactions Move transactions can automatically launch backflush transactions and charge resources and overheads. Backflush material transactions increase WIP valuation and decrease inventory valuation. The accounting entries for backflush material transactions:
Account Debit WIP accounting class valuation accounts XX Inventory valuation accounts Credit XX

Work in Process Transactions Moves and Resources


Costing Move Transactions: Accounting Entries
Costing Move-Based Resource Transactions Resource charges increase your work in process valuation. The accounting entries for resource transactions:
Account WIP accounting class resource valuation accounts Resource absorption account Debit XX Credit

XX

Work in Process Transactions Moves and Resources


Costing Move Transactions: Accounting Entries
Costing Overhead Charges Overhead charges increase work in process valuation. The accounting entries for overhead transactions:

Account Debit WIP accounting class overhead account XX Overhead absorption account

Credit XX

Work in Process Transactions Moves and Resources


Costing Move Transactions: Accounting Entries
Costing Backward Move Transactions Charges Backflush material Resource charges Overhead charges Reversed. Yes only WIP Move resource charges are reversed. Overhead charges reversed if default basis is Item. Reversed if default basis is Lot only if the move results in zero net assemblies completed in the operation

Work in Process Transactions Moves and Resources


Overhead Charging
Charging Method Default Basis Overhead Charge Fixed amount per item

Item Move-based overhead charging Lot

Fixed amount for first unit completed Resource-based Resource units Fixed amount for each overhead charging resource unit charged Resource value Percentage of the resource value

Work in Process Transactions Moves and Resources


Overhead Charging
Move-Based Overheads Upon completion of an operation, system automatically charges move-based overheads. Move based overheads are overheads that have a default basis of Item or Lot. Upon uncompletion, overhead charges are reversed. For Lot-based overheads, charges are reversed when all assemblies have been uncompleted at the operation.

Work in Process Transactions Moves and Resources


Overhead Charging
Resource-Based Overheads If the operation completion move resulted in automatic resource charges for WIP Move resources, and these resources have associated overheads, the overheads will be charged when the resource is charged. Therefore, a move transaction that completes an operation can result indirectly in resource-based overhead charges. Resource-based overhead charges are reversed when the resource transaction is reversed.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
Definitions: Reject is an intraoperation step in an operation at which assemblies that require rework or need to be scrapped are recorded. Scrap is an intraoperation step at which assemblies that cannot be reworked or completed are moved. Scrap account is an account used to charge scrap transactions.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
There are five ways to manage rejected assemblies in WIP Move rejected assemblies to Reject. Scrap rejected assemblies. Add rework operation. Inline rework. Rework in a nonstandard job.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
Move rejected assemblies to Reject. Rejected assemblies can be moved to the Reject intraoperation step to possibly rework them at that operation or later move them to Scrap. Benefits Isolates questionable assemblies. Works well if there is space near the work center to temporarily store the questionable assemblies (same operation, same department). Option to scrap or recover the questionable assemblies.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
Scrapping Rejected Assemblies Assemblies that cannot be recovered can be moved to the Scrap intraoperation step. Benefits Isolates material. Deducts from MRP supply on standard discrete jobs. Offers the option to write off scrap immediately instead of waiting for the job close (standard discrete/nonstandard asset jobs) or period close (repetitive/nonstandard expense jobs). Offers the option to undo the transaction later if necessary.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
Reworking Rejected Assemblies rejected assemblies can be reworked directly in the job by adding a rework operation in the WIP routing. Benefits Use predefined rework operations for repeatable rework activities. Add the rework operation when necessary. Easily charge incremental material, resource, and overhead costs at rework operation.

Work in Process Transactions Moves and Resources


Managing Rejected Assemblies
Reworking Rejected Assemblies rejected assemblies can be reworked directly in the job by adding a rework operation in the WIP routing. Benefits Use predefined rework operations for repeatable rework activities. Add the rework operation when necessary. Easily charge incremental material, resource, and overhead costs at rework operation.

Inline Rework Can use a routing with a rework operation and rework rejected assemblies directly in the job/schedule. This is a std operation with a Count point No and the resources charge type Manual. Benefits Allows to predefine & use the rework operation on the routing when rework is anticipated. Rework can be performed on a repetitive production line (Previous option applies only to discrete jobs as operations cant be added to a repetitive routing). Can easily charge incremental material/resource/overhead at rework operation.

Managing Rejected Assemblies

Work in Process Transactions Moves and Resources

Managing Rejected Assemblies

Work in Process Transactions Moves and Resources

Using a Nonstandard Job to Rework Assemblies Can rework rejected assemblies currently in an MRB subinventory using a nonstandard job. Optionally you can store the assemblies in that subinventory until you are ready to rework them. Benefits Standardization of Process Can use a separate Accounting class to track such orders

Work in Process Transactions Moves and Resources


Charging Resources
Resource is a thing of value, except material and cash, that is required to manufacture, cost, and schedule products. Resources include people, tools, machines, services purchased from a vendor, and physical space. Resource basis is the basis for resource usage quantity that indicates whether that quantity is required per item or per lot. Lot-based resources are resources whose usage quantity represents the amount required per job or schedule. For example, it could be setup time for a machine.

Work in Process Transactions Moves and Resources


Charging Resources
Item-based resources are resources whose usage quantity represents the amount required per assembly you make. For example, it could be the amount of time required to process each assembly at an operation for the job. Resource transaction is a transaction where resource costs are charged to a discrete job or repetitive schedule. Transacting a resource is synonymous with charging a resource.

Work in Process Transactions Moves and Resources


Charging Resources
WIP Move Resource : A WIP move resource is a resource that is automatically charged to a discrete job or repetitive schedule by a move transaction that completes an operation. The autocharge type for this type of resource is WIP Move. Manual Resource: A manual resource is a resource that you manually charge to a discrete job or repetitive schedule. The autocharge type for this type of resource is Manual.

Work in Process Transactions Moves and Resources


Charging Resources
Manually Charging Resources Resources can manually be charged to a discrete job/repetitive assembly and line with or without an associated move transaction. Manually charging resources without a move Manually charging resources with a move Manually reversing resource charges

Work in Process Transactions Moves and Resources


Charging Resources
Manually Charging Resources with a Move Move transaction can be performed normally . Resources with an autocharge type of Manual assigned to the operations completed during the move can be charged. (WIP displays those resources automatically). If the standard rate flag for a manual resource is No, and the resource type is Person, the resource can be charged at the employee labor rate instead of the standard rate by specifying an employee identifier. This transaction is done from the Move Transactions window using Resources button. WIP (N) Move Transaction > Move Transactions (B) Resources

Work in Process Transactions Moves and Resources


Charging Resources
Manually Charging Resources without a Move Any resource assigned to an operation in a job or schedule can be charged. Any resource not previously assigned to an operation in a job or schedule can be charged. The resource must be defined for the department associated with the operation. It can have autocharge type Manual/WIP move. This transaction is done by navigating to the Resource Transactions window. WIP (N) Resource Transactions > Resource Transactions

Work in Process Transactions Moves and Resources


Charging Resources
Manually reversing Resource charges User can manually reverse resource charges at any time by specifying negative resource units applied. This transaction is done by navigating to the Resource Transactions window. WIP (N) Resource Transactions > Resource Transactions

Work in Process Transactions Moves and Resources


Charging Resources
Automatic Resource Transactions Automatically charging resources at standard rate Completing an operation and automatically charging resources Reversing resource charges

Work in Process Transactions Moves and Resources


Charging Resources
Automatically Charging Resources at Standard Rate Resources can be automatically charged at their standard rate to a discrete job or repetitive assembly and line while performing a move transaction.

Work in Process Transactions Moves and Resources


Charging Resources
Completing an Operation and Automatically Charging Resources All resources with an autocharge type of WIP move are charged at their standard rate. WIP move resources with a basis type of Item are charged upon completion of each assembly at the operation the resource is tied to. WIP move resources with a basis type of Lot are charged upon completion of the first assembly at the operation the resource is tied to.

Work in Process Transactions Moves and Resources


Charging Resources
Reversing Resource Charges If an uncompletion is performed, system automatically reverses any resource charges associated with the completion for WIP move resources. If a WIP move resource has a basis type of Lot, system reverses the resource charges only if all assemblies are uncompleted at the operation.

Work in Process Transactions Moves and Resources


Charging Multiple Schedules
Flow charging is a repetitive transaction method in which system charges material, move, resource, and overhead transactions to a specific assembly on a line rather than a specific repetitive schedule. If more than one schedule has a status that allows charges, user can perform transactions against the consolidated sum of all the schedules. For example, if there are three schedules for 100 units each with status Released for the same assembly and line combination, up to 300 units could be moved with one transaction.

Work in Process Transactions Moves and Resources


Charging Multiple Schedules
Advantages of Flow Charging Flow charging means that shop floor data entry can be performed by charging against the assembly and line. Flow charging means that all transactions against an assembly on a line can be batched and then enter all of them in one transaction. Flow charging supports the idea of a schedule being less of an individual entity than a discrete job is. As long as two schedules build the same assembly on the same line, system does not distinguish between them for transaction purposes.

Work in Process Transactions Moves and Resources


Charging Multiple Schedules
Repetitive Allocation Repetitive allocation is a system technique for applying transaction quantities and costs across several repetitive schedules that are building the same repetitive assembly on the same line. The repetitive allocation algorithm allows the system to allocate the transactions that were flow charged to particular schedules.

Work in Process Transactions Moves and Resources


Costing Resource Charges at Resource Standard
Resource charges increase work in process valuation. The accounting entries for resource transactions are:
Account WIP accounting class resource valuation account Resource absorption account Debit XX XX Credit

The accounting entries for negative manual resource transactions and backward moves for WIP move resources are:
Account Resource absorption account WIP accounting class resource valuation account Debit XX Credit XX

Work in Process Transactions Moves and Resources


Costing Labor Charges at Actual
For labor charges using an actual or employee rate for a resource with the Standard Rate check box clear, the job or schedule is debited at the actual or employee rate. The employee rate used needs to be set up at the organization level. The absorption account is credited at the same rate. The variance between actual and standard is captured at the time of accounting close. accounting entries for resource transactions are:
Account WIP accounting class resource valuation account Resource absorption account Debit XX XX Credit

Work in Process Transactions Moves and Resources


Costing Resource Transactions
If the actual rate is greater than the standard rate, the accounting entries are:
Account Debit WIP accounting class resource valuation account XX Resource rate variance account XX Resource absorption account Credit

XX

If the actual rate is less than the standard rate, the accounting entries are:
Account Debit WIP accounting class resource valuation account XX Resource rate variance account Resource absorption account Credit XX XX

Work in Process Transactions Moves and Resources


Weighted Average costing
Material can be charged to WIP at average cost. Resources can be charged to WIP at actual or average cost. Outside processing resources can be defined under average costing. The average cost of completed assemblies in WIP can be calculated.

Complete Discrete Jobs and Repetitive Schedules


Completing Jobs
Definitions Assembly completion transaction is a material transaction in which assemblies are received into inventory from a job or repetitive assembly/line upon completion of the manufacture of the assembly. Completion subinventory is an inventory location at the end of production line or shop floor routing where completed assemblies from work in process are received . This is often the supply subinventory for subassemblies or finished goods inventories for final assemblies.

Complete Discrete Jobs and Repetitive Schedules


Completing Jobs
Completion Transaction Process The finished assemblies are received into inventory, either to be used as subassemblies or to be shipped as finished goods. All Assembly Pull material attached on the bill is backflushed. The quantity in the To Move step of the last operation is decreased, if there is a routing. The Quantity Complete on the job or repetitive schedule is increased.

Complete Discrete Jobs and Repetitive Schedules


Completing Jobs
Completion Transaction Process If the quantity completed equals the total quantity for a schedule, and there are other active schedules following it on the assembly/line, the schedules status is changed to CompleteNo Charges. If the schedule is the last active schedule, its status is changed to Complete. Job and repetitive schedule statuses are automatically updated to Complete when the total number of assemblies completed and scrapped on a job or repetitive schedule is greater than or equal to the required quantity.

Complete Discrete Jobs and Repetitive Schedules


Completion Transactions
Complete assemblies from jobs and repetitive schedules into inventory Return completed assemblies from inventory to jobs and repetitive schedules over-complete assemblies

Complete Discrete Jobs and Repetitive Schedules


Completion Transactions
(N) WIP > Material Transactions > Completion Transactions

Assemblies can be over completed to inventory from jobs and schedules per established tolerance limits without changing the job start quantity.

Complete Discrete Jobs and Repetitive Schedules


Work order less completions
Using work order-less completions: Complete assemblies without having to create a job or schedule Do several tasks in one step at completion Substitute components Support lot and serial number control Cost transactions using standard and average costing

Complete Discrete Jobs and Repetitive Schedules


Work order less completions
(N) WIP > Material Transactions > Workorder-less Completion Transactions

Complete Discrete Jobs and Repetitive Schedules


Returning Assemblies from Inventory to WIP
Completed assemblies can be returned to work in process using the Completion Transactions window as well as the Move Transactions window. Reasons to Return Assemblies to WIP User want to perform additional processing. User found a quality problem. User mistakenly completed unfinished assemblies to inventory. User performing a disassembly using a nonstandard job.

Complete Discrete Jobs and Repetitive Schedules


Returning Assemblies from Inventory to WIP
Return Characteristics User can return assemblies from inventory to WIP by selecting Return as the transaction type. User can return as many assemblies as needed. Any assembly pull components that were backflushed upon completion are unbackflushed; that is, they are returned to inventory when you return the assembly to work in process.

Complete Discrete Jobs and Repetitive Schedules


Costing Completion Transactions
Costing Assembly Completion Transactions Completion transactions decrease work in process valuation and increase inventory valuation. The accounting entries for assembly completion transactions are:
Account Subinventory elemental accounts WIP accounting class valuation accounts Debit XX XX Credit

Complete Discrete Jobs and Repetitive Schedules


Costing Completion Transactions
Earning Assembly Material Overhead on Completion Overheads can be assigned based on the total value of an item. These overheads can be earned as assemblies into are completed into inventory. The accounting entries are:
Account Subinventory material overhead account Inventory material overhead absorption account Debit XX XX Credit

Complete Discrete Jobs and Repetitive Schedules


Manufacturing Average Costing
Items can be costed at a weighted average perpetual cost. Completions are valued using the sum of the actual costs of resources and materials issued to a job Partial completions are valued using the appropriate proportional sum of actual resource and materials issued to a job Final completions are valued using the total net value in a job The unit cost of a completion is computed elementally
Material ,Material and overhead ,Resource, Overhead &Outside processing

Complete Discrete Jobs and Repetitive Schedules


Completion Transactions for Repetitive Schedules
Roll forward Rules When all assemblies of a schedule are completed, WIP checks the schedule for any excess components resulting from over issue of material requirements. If the subsequent schedule is released, or if it is unreleased and falls into the auto release time fence, WIP rolls the excess material charges forward to that schedule. If there is no subsequent schedule to auto release, WIP does not roll the excess material charges forward.

Complete Discrete Jobs and Repetitive Schedules


Completion Transactions for Repetitive Schedules
Autorelease Repetitive production can be streamlined by automatically releasing the next schedule when one schedule is completed. A line can continue running and build repetitive assembly if another schedule is defined for the assembly on that line. If the schedule is defined but unreleased, the completion of the preceding schedule can serve as a signal to automatically release the next unreleased schedule.

Complete Discrete Jobs and Repetitive Schedules


Closing Discrete Jobs
Can the Status of a Closed Job Be Changed? To be able to unclose jobs, the Close Discrete Jobs function security parameter must be set to Y. Only jobs closed in error should be unclosed, it should be done this immediately after the close using the Close Discrete Jobs window. If assembly costs are rolled up between the time a job is closed and unclosed, costs may be incorrect because the unclose process does not revalue the job. A job that is linked to a sales order cannot be unclosed. A job that was closed in an accounting job that is no longer open cannot be unclosed

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface Open Resource Transaction Interface Work Order Interface

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface This interface is used to transfer WIP move transaction information into Oracle Applications. The records can be loaded into the Open Move Transaction Interface from a variety of sources, including external data collection devices such as bar code readers, automated test equipment, cell controllers, and other manufacturing execution systems. The interface validates the records & marks invalid transactions, so that the transactions can be corrected & resubmitted

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface This interface enables users to perform many of the functions possible from the Move Transactions window. Move assemblies between operations and intra-operation steps Scrap assemblies Move assemblies from an operation and complete them into inventory with a single transaction Over-complete a quantity greater than the job or schedule quantity if over-completions are enabled Return assemblies from inventory and move to an operation with a single transaction

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface Ad hoc operations cannot be added through this interface even if the WIP Allow Creation of New Operations parameter is set. The table populated while inserting records into the interface is WIP_MOVE_TXN_INTERFACE Types of move transactions Move transaction Move Completion Move Return

Work In P rocess Interfa ces


Open Move Transaction Interface Columns to be populated:
FM_INTRAOPERATION_STEP_TYPE,FM_OPERATION_SEQ_NUM, LINE_CODE, ORGANIZATION_CODE, PROCESS_PHASE, PROCESS_STATUS, TO_INTRAOPERATION_STEP_TYPE, TO_OPERATION_SEQ_NUM, TRANSACTION_DATE, TRANSACTION_QUANTITY, TRANSACTION_UOM, WIP_ENTITY_NAME FM_INTRAOPERATION_STEP_TYPE,FM_OPERATION_SEQ_NUM

WIP Interfaces

are only required for move transaction/ completion transactions TO_INTRAOPERATION_STEP_TYPE,TO_OPERATION_SEQ_NUM are only required for move transaction & move return transactions

Work In P rocess Interfa ces


WIP Interfaces
Open Resource Transaction Interface This interface is used to charge resources. External data collection devices such as bar code readers, payroll systems, and time card entry forms can be used to collect resource and overhead transaction data, then load the data into the Open Resource Transaction Interface for WIP to process. The interface validates the data and marks any that are invalid so that it can be corrected and resubmitted.

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface This interface enables users to perform many of the functions possible from the Resource Transactions window. Charge labor resources Charge overhead resources Charge outside processing resources Add ad hoc resources Note: Non-person resources cannot be charged at an actual usage rate or amount through the Resource Transactions window. This feature is unique to the Resource Transaction Interface.

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface The table populated while inserting records into the interface is WIP_COST_TXN_INTERFACE Columns to be populated:
OPERATION_SEQ_NUM, ORGANIZATION_CODE, ORGANIZATION_ID, PROCESS_PHASE, PROCESS_STATUS, RESOURCE_SEQ_NUM, TRANSACTION_QUANTITY, TRANSACTION_DATE, TRANSACTION_TYPE, TRANSACTION_UOM, WIP_ENTITY_NAME

Work In P rocess Interfa ces


WIP Interfaces
Open Move Transaction Interface PROCESS_PHASE describes the current processing phase of the transaction. The Cost Worker processes each transaction row through the following two phases Values: 1 Resource Validation ,2 Resource Processing PROCESS_STATUS contains the state of the transaction. Values: 1 Pending , 2 Running ,3 Error TRANSACTION_TYPE should be set to: Values: 1 for normal resource transactions,2 for overhead transactions & 3 for outside processing transactions

Work In P rocess Interfa ces


WIP Interfaces
Work order Interface The Work Order Interface enables users to import Discrete job and Repetitive schedule header information, and Discrete job operations, material, resource, and scheduling information from any source, using a single process. Options available: Planned orders for new Discrete jobs, Discrete job operations, components, resources, resource usage, and scheduling details, Update and reschedule recommendations for existing Discrete jobs, and suggested Repetitive schedules

Work In P rocess Interfa ces


WIP Interfaces
Work order Interface The Work Order Interface consists of two tables: the WIP_JOB_SCHEDULE_INTERFACE table (Open Job and Schedule Interface table), and the WIP_JOB_DTLS_INTERFACE table (WIP Job Details Interface table). Header information is loaded into the WIP_JOB_SCHEDULE_INTERFACE table, and operations, components, resources, and scheduling information into the WIP_JOB_DTLS_INTERFACE table.

Work In P rocess Interfa ces


WIP Interfaces
Work order Interface The Work Order Interface consists of two tables: the WIP_JOB_SCHEDULE_INTERFACE table (Open Job and Schedule Interface table), and the WIP_JOB_DTLS_INTERFACE table (WIP Job Details Interface table). Header information is loaded into the WIP_JOB_SCHEDULE_INTERFACE table, and operations, components, resources, and scheduling information into the WIP_JOB_DTLS_INTERFACE table.

Picki ng for Man ufacturi ng


Picking for Manufacturing
Introduced in 11.5.7 Family pack for manufacturing Combines the functionality of Manufacturing & Warehouse management system to provide rule based component picking.. Operation or assembly pull material can be excluded from the tasks. Migration to the new Picking for Manufacturing is optional for WIP users.

Picki ng for Man ufacturi ng


Picking for Manufacturing
Move orders will be created for all component requirements. Picking supports discrete/lot based jobs, as well as flow & repetitive schedules. The use of move orders will allow users to use the standard inventory picking rules, as well as to track and transact the component requirements.

Picki ng for Man ufacturi ng


Picking for Manufacturing
Supply type push - Material issued directly to job - Transacting the move order / task decrements inventory Supply type assembly / operation pull - Material moved to supply subinventory - Material pulled at operation move or assembly completion - Optionally excluded from process

Picki ng for Man ufacturi ng


Picking for Manufacturing
Pick release selected jobs -Use Inventory Rules to allocate material -Allocated material cannot be used for other transactions -Create move orders for the required material -Missing material is backordered and available for rerelease Optionally print move order pick slip report Move order transacted on desktop -Query on specific jobs or schedules -Update allocations if necessary

Picki ng for Man ufacturi ng


Picking for Manufacturing
Current Functionality in Release 11.5.9 User can specify upto which operation the material needs to be pick released for a single or set of jobs. Various picking methodologies (like cluster pick, bulk pick, zone pick etc.) supported by Order management also can be used. However this feature is limited to Discrete jobs only. All the material requirements for a job is released under a single move order irrespective of the supply types. User will have the option on printing of the pick slips at the time of pick release. .

Picki ng for Man ufacturi ng


Picking for Manufacturing
Current Functionality in Release 11.5.9 User can choose whether to plan tasks by default or not for each pick release. This option can also be set at organization level and can be overridden by user while pick releasing. . After the pick release, if allocation was partial, user can check the leftover requirements for a job by clicking on a particular job node. User can see the backordered quantity for each component. .

Picki ng for Man ufacturi ng


Picking for Manufacturing
(N) WIP> Discrete> Component Pick Release
.