You are on page 1of 544
Project Manual City of High Point Alcoholic Beverage Control Board ABC STORE NO. 7 1583 Skeet Club Road High Point, North Carolina November 20, 2007 * Snes ma “y “ny warren “narchitecture 200-6 South stratford Road, Winston-Salem, NG 27103 Phone! (396) 727-1389" Fax: (996) 727-0850 HIGH POINT ABC TABLE OF CONTENTS CONTRACT INFORMATION Instructions to Bidders - AIA DOCUMENT 4701-1997 00110 - Supplementary Instructions to Bidders 00401 - Bid Form (Sample) 00410 - Bid Bond - AIA DOCUMENT 310-1970 00501 - Standard Form of Agreement between Owner and Contractor - AIA Document A101-1997 00510 - Performance Bond - AIA Document 4312-1984 00520 - Payment Bond - ATA Document 4312-1984 00670 - Affidavit of Contractor (Payment of Debts and Claims) - AIA Document G-706-1994 00680 - Affidavit of Contractor (Release of Liens) - AZA Document G-706-A-1994 00690 - Contractor's General Warranty 00701 - General Conditions of the Contract for Construction ~ AIA Document A201-1997 00801 - Supplementary Conditions of the Contract for Construction (00901 - Soil Investigation Data DIVISION 1 - GENERAL REQUIREMENTS 01100 - Summary 01210 - Allowances 01250 - Contract Modification Procedures 01290 - Payment Procedures 01310 - Project Management and Coordination 01320 - Construetion Progress Documentation 01330 - Submittal Procedures 01400 - Quality Requirements 01420 - References 01500 -'Temporary Facilities and Controls 01600 - Product Requirements 01700 - Execution Requirements 01770 - Closeout Procedures 01781 - Project Record Documents DIVISION 2 - SITE CONSTRUCTION 02115 - Soil Erosion and Sediment Control 02221 - Site Demolition 02300 - Earthwork 02362 - Termite Control 02512 - Site Water Distribution 02516 - Disinfection of Water Distribution 02539 - Sanitary Sewage Systems 02630 - Storm Drainage Systems 02745 - Asphaltic Concrete Paving 02753 - Portland Cement Concrete Pavement 02924 - Seeding and Soil Supplements ‘TABLE OF CONTENTS TOC-1 HIGH POINT ABC DIVISION 3 - CONCRETE 03300 - Cast-in-Place Conerete DIVISION 4 - MASONRY 04810 - Unit Masonry Assemblies DIVISION 5 - METALS 05120 - Structural Steel 05220 - Stee! Joists 05310 - Stee! Deck 05400 - Cold-Formed Metal Framing 05500 - Metal Fabrications 05521 - Pipe and Tube Railings 05700. - Omamental Metal DIVISION 6 - WOOD AND PLASTICS 06105 - Miscellaneous Carpentry 06402 - Interior Architectural Woodwork DIVISION 7 - THERMAL AND MOISTURE PROTECTION 07210 - Building Insulation 07241 - Exterior Insulation and Finish Systems - Class PB 07411 - Metal Roof Panels 07543 - Thermoplastic Polyolefin (TPO) Roofing 07620 - Sheet Metal Flashing and Trim 07720 - Roof Accessories 07920 - Joint Sealants DIVISION 8 - DOORS AND WINDOWS 08110 - Steel Doors and Frames 08211 - Flush Wood Doors 08331 - Overhead Coiling Doors 08411 - Aluminum-Framed Entrances and Storefronts 08461 - Sliding Automatic Entrance Doors 08711 - Door Hardware 08800 - Glazing DIVISION 9 - FINISHES 09260 - Gypsum Board Assemblies 09511 - Acoustical Panel Ceilings 09651 - Resilient Floor Tile (09681 - Carpet 09653 - Resilient Wall Base and Accessories 09751 - Interior Stone Facing ‘TABLE OF CONTENTS TOC-2 HIGH POINT ABC 09912 - Painting DIVISION 10 - SPECIALTIES 10522 - Fire Extinguishers Cabinets 10523 - Fire Extinguishers 10730 - Protective Canopies 10801 - Toilet and Bath Accessories DIVISION 11 - EQUIPMENT 11160 - Loading Dock Equipment DIVISION 12 - FURNISHINGS Not Used DIVISION 13 - SPECIAL CONSTRUCTION Not Used DIVISION 14 - CONVEYING SYSTEMS Not Used DIVISION 15 - PLUMBING, FIRE PROTECTION AND HEATING/AIR CONDITIONING 15010-A - Basic Plumbing Requirements 15140-A - Supports and Anchors 15190-A - Plumbing Identification 15260-A - Piping Insulation 15410-A - Plumbing Piping 15430-A - Plumbing Specialties 15440-A - Plumbing Fixtures 15450-A - Plumbing Equipment 15010-B - Basic Mechanical Requirements 15025-B - Division of Work 15140-B - Supports and Anchors 15190-B - Mechanical Identification 15290-B - Ductwork Insulation 15781-B - Packaged Rooftop Air Conditioning Units 15890-B - Ductwork 15910-B - Ductwork Accessories 15936-B - Air Outlets and Inlets 15990-B - Testing, Adjusting, and Balancing DIVISION 16 ~ ELECTRICAL 16010 - Basic Electrical Requirements 16025 - Division of Work 16035 - Electrical Testing ‘TABLE OF CONTENTS TOC-3 HIGH POINT ABC 16111 - Conduit 16123 - Building Wire and Cable 16130 -Boxes 16141 - Wiring Devices 16170 - Grounding and Bonding 16190 - Supporting Devices 16195. - Electrical Identification 16441 - Enclosed Switches 16470 - Panelboards 16485. - Contactors 16510 -Interior Luminaries 16741 - Telephone Service Entrance ‘TABLE OF CONTENTS TOC-4 BATA Document A701" - 1997 Instructions to Bidders for the following PROJECT: (Name and location or address): EP ABC Store Number 7 (Oak Hollow Shopping Center igh Point, NC ADDITIONS AND DELETIONS: ‘THE OWNER: “The author of this document has (Name and address): ‘added infomation needed oF ts “igh Point Alcoholic Beverage Control Board ‘complation. The author may ao 201 West Fucfield Road tate reed the tothe High Point, NC 27261 ovina AIA standard form, An ‘Adéions and Dslaions Papert THE ARCHITECT: that noes acded inormation a8 (Name and address): ‘wall as revisions to the standard Warten Architecture, PC, ‘erm texts aval trom the 390-C South Stratford Road ‘author and should be reviewed. Winston-Salem, NC 27103 ‘Avert inthe lett mergin of this document Indcatos where the autor has added necessary TABLE OF ARTICLES Infomation and where the eutnor has added oor dleted trom he 1 DEFINITIONS original AIA text, “This document has important legal consequences. Consultation with an attorney Is encouraged with respect to its completion or modtication. 2 _BIDDER'S REPRESENTATIONS. 3 BIDDING DOCUMENTS 4 BIDDING PROCEDURES CONSIDERATION OF BIDS. POST-BID INFORMATION 7 PERFORMANCE BOND AND PAYMENT BOND 8 —_ FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ‘NaDocurent ATOT™ — 1007 Copyright ©1070, 1373, 1078, 1957 ad 197 by The Anatkan he of Achiods. Altighs reserved. WARNING: eA eset preety 8 Copy iy acinermoa rete Una erewaton droion of t AK. Document of any portion of may result in aevere svt and criminal penalties, an wl be prosecuted tthe maxim 2 be nda the i canna rnd Oy AA stare a TOME on AEG ne! rN OGETI8| whch rn on A IDO. nde br ser totes: (1226206071) ARTICLE 1 DEFINITIONS § 1.1 Bidding Documents include the Bidding Requirements and the proposed Contract Documents. The Bidding Requirements consist ofthe Advertisement or Invitation to Bid, Instructions to Bidders, Supplementary Instructions to Bidders, the bid form, and other sample bidding and contract forms, The proposed Contract Documents consist of the form of Agreement between the Owner and Contractor, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications and all Addenda issued prior to execution of the Contract. § 1.2 Detinitions set forth in the General Conditions of the Contract for Construction, ATA Document A201, or in other Contract Documents are applicable to the Bidding Documents, § 1.3 Addenda are written or graphic instruments issued by the Architect prior to the execution of the Contract which ‘modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections, § 4.4 A Bid is «complete and properly executed proposel to do the Work for the sums stipulated therein, submitted Jn accordance with the Bidding Documents §1.5 The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base, to which Work may be added or from which Work may be deleted for sums stated in Alternate Bids, §18 An Altemate Bid (or Altemate) is an amount stated in the Bid to be added to or deducted from the amount of the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted. §47 A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment or services or a portion of the Work as described in the Bidding Documents $118 A Bidder isa person or entity who submits a Bid and who meets the requirements set forth inthe Bidding Documents {§1.9 A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment or labor for a portion of the Work. ARTICLE 2 BIDDER'S REPRESENTATIONS. § 211 The Bidder by making a Bid represents that: § 2.1.1 The Bidder has read and understands the Bidding Documents or Contract Documents, to the extent that such documentation relates to the Work for which the Bid is submitted, and for other portions of the Project, if any, being bid concurrently or presently under construction, § 2.1.2 The Bid is made in compliance with the Bidding Documents. §2.1.3 The Bidder has visited the site, become familiar with local conditions under which the Work is to be performed and has correlated the Bidder's personal observations with the requirements of the proposed Contract Documents. {§2.1.4 The Bid is based upon the materials, equipment and systems required by the Bidding Documents without exception, ARTICLE 3 BIDDING DOCUMENTS §3.1 COPIES § 3.4.1 Bidders may obtain complete sets of the Bidding Documents from the issuing office designated in the ‘Advertisement or Invitation to Bid inthe number and for the deposit sum, if any stated therein. The deposit will be refunded to Bidders who submit a bona fide Bid and retum the Bidding Documents in good condition within ten days after receipt of Bids, The cost of replacement of missing or damaged documents will be deducted from the deposit. A Bidder receiving a Contract award may retain the Bidding Documents and the Bidder’s deposit will be refunded, § 21.2 Bidding Documents will tbe issued directly to Sub-bidders unless specifically offered inthe Advertisement or Invitation to Bid, or in supplementary instructions to bidders, "NA Document ATO1™ ~ 1907. Copyright © 1070, 1074, 1078, 1087 and 1097 by The Amotcan ace of Achill rights reserved. WARNING ‘Tis AI" Documantis protected by U.S. Copyright Law and International Tati, Unauthortnd reproduction or detrbution ft AIA” ‘or any portion oft may resuitin severe cv and oriminal pena, and willbe prosecuted to th maxim eatery pol “This document was produced by lA software a 1842-48 on 11/7/2007 undo Gret No. 1000274268 1 whi eyes on 121/207, andl hat ot Note: (veasaaeer § 3.1.3 Bidders shall use complete sets of Bidding Documents in preparing Bids; neither the Owner nor Architect assumes responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents, §3.14 The Owner and Architect may make copies of the Bidding Documents available on the above terms forthe ‘purpose of obiaining Bids on the Work. No license or grant of use is conferred by issuance of copies of the Bidding. Documents {§3. INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS §3.21 The Bidder shall carefully study and compare the Bidding Documents with each other, and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for which the Bid is submitted, shall examine the site and local conditions, and shall at once report to the Architect errors, inconsistencies or ambiguities discovered. §3.22 Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a ‘written request which shall reach the Architect atleast seven days prior to the date for receipt of Bids, §3.23 Interpretations, corrections and changes of the Bidding Documents will be made by Addendum, Interpretations, corrections and changes of the Bidding Documents made in any other manner will not be binding, and Bidders shall not rely upon them. §23SUBSTITUTIONS §3.3.1 The materials, products and equipment described in the Bidding Documents establish a standard of required function, dimension, appearance and quality to be met by any proposed substitution. {§3.3.2 No substitation will be considered prior to receipt of Bids unless written request for approval has been received by the Architect atleast ten days prior to the date for receipt of Bids. Such requests shall include the name ‘of the material or equipment for which itis to be substituted and a complete description of the proposed substitution including drawings, performance and test data, and other information necessary for an evaluation. A statement setting forth changes in other materials, equipment or other portions of the Work, including changes inthe work of other contracts that incorporation of the proposed substitution would require, shall be included. The burden of proof of the merit of the proposed substitution is upon the proposer. The Architect's decision of approval or disapproval of proposed substitution shall be final, §3.33 If the Architect approves a proposed substitution prior to receipt of Bids, such approval will be set forth in an ‘Addendum, Bidders shall not rely upon approvals made in any other manner, §3.34 No substitutions will be considered after the Contract award unless specifically provided for in the Contract Documents, §3.4 ADDENDA §3.44 Addenda will be transmitted to all who are known by the issuing office to have received a complete set of Bidding Documents. §34.2 Copies of Addenda will be made available for inspection wherever Bidding Documents are on file for that purpose, § 3.43 Addenda will be issued no later than four days prior tothe date for receipt of Bids except an Addendum ‘Withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids. § 3.44 Exch Bidder shall ascertain prior to submitting a Bid thet the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid, ARTICLE 4. BIDDING PROCEDURES §4.1 PREPARATION OF BIDS §4.1.1 Bids shall be submitted on the forms included with the Bidding Documents, TA Document ATOT™— 1957. Copyright © 1970, 107, 1870, 187 and 1807 by Tha Amevcan nate of Aches, Alright reserved, WARRING: ‘This AIR* Document is protcted by US. Copyright Law and ternational Teales Unautharlzed reproduction or alstibuton ote AIA” Document or any portion of may tui in severe cviand criminal pens, and wil be prosecuted to tho maximum sitet possible under the fam. Thi dccumant was prosise By AIA coher Ye248 on 1127200" undet Order No 1b087¢258, 4 whieh empires on 117007, erie Nt er rene (12as20e71) Cron § 4.1.2 All blanks on the bid form shall be legibly executed in anon-erasable medium. § 4.1.3 Sums shall be expressed in both words and figures. In case of discrepancy, the amount written in words shall gover, $4.14 Interlineations, alterations and erasures must be initialed by the signer of the Bid. $4.18 All requested Altemates shall be bid, If no change in the Base Bid is required, enter "No Change.” {$41.6 Where two or more Bids for designated portions of the Work have been requested, the Bidder may, without forfeiture ofthe bid security, state the Bidder’s refusal to accept award of less than the combination of Bids stipulated by the Bidder. The Bidder shall make no additional stipulations on the bid form nor qualify the Bid in any other manner, $4.1, Bach copy of the Bid shall state the legal name of the Bidder and the nature of legal form of the Biddec, The Bidder shall provide evidence of legal authority (o perform within the jurisdiction of the Work, Each copy shall be signed by the person or persons legally authorized to bind the Bidder a contract. A Bid by a corporation shall further give the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached certifying the agent's authority to bind the Bidder, §4.2BID SECURITY § 4.2.1 Each Bid shall be accompanied by a bid security in the form and amount required if so stipulated in the Instructions to Bidders. The Bidder pledges to enter into a Contract. with the Owner on the terms stated in the Bid and will, if required, furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder. Should the Bidder refuse to enter into such Contract or fail to furnish such bonds if required, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty. The amount of the bid security shall not be forfeited to the Owner in the event the Owner fails to comply with Section 6.2, § 4.22 If a surety bond is required, it shall be written on AIA Document A310, Bid Bond, unless otherwise provided in the Bidding Documents, and the attomey-in-fact who executes the bond on behalf of the surety shall affix to the bond a certified and current copy of the power of attomey. §423 The Over will have the right to retain the bid security of Bidders to whom an award is being considered ‘until ether (a) the Contract has been executed and bonds, ifequired, have been fumished, or (b) the specified time has elapsed so that Bids may be withdrawn or (c) all Bids have been rejected, §.43 SUBMISSION OF BIDS § 4.3.1 All copies ofthe Bid, the bid security, if any, and any other documents required to be submitted with the Bid shall be enclosed in a sealed opaque envelope, The envelope shall be addressed to the party receiving the Bids and shall be identified with the Project name, the Bidder’s name and address and, if applicable, the designated portion of the Work for which the Bid is submitted, If the Bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope with the notation "SEALED BID ENCLOSED" on the face thereof. § 4.32 Bids shall be deposited at the designated location prior tothe time and date for receipt of Bids. Bids received after the time and date for receipt of Bids willbe reuumed unopened. §4.33 The Bidder shal assure full responsibilty for ely delivery atthe location designated for receipt of Bids. $4.34 Oral, telephonic, telegraphic, facsimile or other electronically transmitted bids will not be considered. § 44 MODIFICATION OR WITHDRAWAL OF BID §4.4.1 A Bid may not be modified, withdrawn or canceled by the Bidder during the stipulated time period following the time and date designated for the receipt of Bids, and each Bidder so agrees in submitting & Bid, §4.42 Prior to the time and date designated for receipt of Bids, a Bid submitted may be modified or withdrawn by notice tothe party receiving Bids a the place designated for receipt of Bids, Such notice shall be in writing over ihe ‘RIA Document ATOT™ — 1007, Copyright © 1070, 1074, 107, G57 and 1007 by Tw Ameccan ratte of Arohiaca. Allright reserved, WARNING: Ths AIA" Document Is protected by US Copyright Law and Iterational Treats. Unauthorized reproduction or letrbution of AA DDacumans ot any parton of may resuit in severe sul an erminel penal, and wl be prosecuted tothe maximum extent possible undo the “hs document was produced by AA software at 1:42:48 on 1121/2007 undo Odor No-1000274268 1 weih opires on 12/207, andl hat or (122271) signature of the Bidder. Written confirmation over the signature of the Bidder shall be received, and date- and time- stamped by the receiving party on or before the date and time set for receipt of Bids. A change shall be so worded as ‘not to reveal the amount of the original Bid. §4.43 Withdrawn Bids may be resubmitted up to the date and time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders, §4.44 Bid security, if required, shall be in an amount sufficient for the Bid as resubmitted. ARTICLE 5 CONSIDERATION OF BIDS §5-1 OPENING OF BIDS Act the discretion of the Owner, if stipulated in the Advertisement or Invitation to Bid, the properly identified Bids received on time will be publicly opened and will be read aloud, An abstract ofthe Bids may be made available to Bidders, §5.2 REJECTION OF BIDS ‘The Owner shall have the tight to reject any or all Bids. A Bid not accompanied by a required bid security or by other data required by the Bidding Documents, or a Bid which is in any way incomplete or irregular is subject to rejection. § 5.3 ACCEPTANCE OF BID (AWARD) § 5.3.1 is the intent of the Owner to award a Contract to the lowest qualified Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents and docs not exceed the funds available. ‘The Owner shall have the right to waive informalities and irregularities in a Bid received and to accept the Bid which, in the Owner's judgment, is in the Owner's own best interests. §5.32 The Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided inthe Bidding Documents, and to determine the low Bidder on the basi ofthe sum of the Base Bid and ‘Altemates accepted. ARTICLE 6 POST-BID INFORMATION §6.1 CONTRACTOR'S QUALIFICATION STATEMENT Bidders to whom award of a Contract is under consideration shall submit to the Architect, upon request, a properly executed AIA Document A305, Contractor's Qualification Statement, unless such a Statement has been previously required and submitted as a prerequisite to the issuance of Bidding Documents. {§6.2 OWNER'S FINANCIAL CAPABILITY The Owner shall, a the request of the Bidder to whom award of a Contract is under consideration and no later than seven days prior to the expiration of the time for withdrawal of Bids, furnish to the Bidder reasonable evidence that financial arrangements have been made to fulfill the Owner’s obligations under the Contract. Unless such reasonsble cevidence is furnished, the Bidder will not be required to execute the Agreement between the Owner and Contractor, §6.3 SUBMITTALS §6.31 The Bidder shall, as soon as practicable or as stipulated in the Bidding Documents, after notification of selection for the award of a Contract, furnish to the Owner through the Architect in writing: 4 adesignation of the Work to be performed with the Bidder's own forces; 2 names of the manufacturers, products, and the suppliers of principal items or systems of materials and equipment proposed for the Work; and 3 names of persons or entities (including those who are to furnish materials or equipment fabricated to special design) proposed forthe principal portions of the Work. {§6.3.2 The Bidder will be required to establish tothe satisfaction ofthe Architect and Owner the reliability and ‘esponsibility of the persons or entities proposed to furnish and perform the Work described in the Bidding Documents. §8.33 Prior to the execution of the Contract, the Architect will notify the Bidder in writing if either the Owner or Architect, after due investigation, has reasonable objection to a person or entity proposed by the Bidder. Ifthe “HA Document A701™ - 1897. Copyright @ 1870, 1974, 1876, 1967 and 1997 by The Amerean incite of Architects. All rights reserved. WARNING: ‘Tals AIA" Documant le proacted by US. Copytight Law and international Trestle, Unauthorized reproduction or atrbuton of tis AIA” Document, oF any portion of, may result In sovere civ an eriminel ena, and wil be prosacuted to the maximom extent possible unde the tam. Ths document was produced by AIA softwar 16249 on 11/21/2007 unt Ore No.1000274268 1 Weohaypres on ¥2T 12007 nda not or remie, User tots: (12as200071) ‘Owner or Architect hus reasonable objection toa proposed person or entity, the Bidder may, a the Bidder’s option, (1) withdraw the Bid or (2) submit an acceptable substitute person or entity with an adjustment in the Base Bid or Altemate Bid to cover the difference in cost occasioned by such substitution. The Owner may accept the adjusted bid price or disqualify the Bidder. Inthe event of either withdrawal or disqualification, bid security will ot be forfeited. {$6.34 Persons and entities proposed by the Bidder and to whom the Owner and Architect have made no reasonable ‘Objection must be used on the Work for which they were proposed and shall not be changed except with the wen consent ofthe Owner and Architect. ARTICLE 7 PERFORMANCE BOND AND PAYMENT BOND §7-1 BOND REQUIREMENTS §7.1.1 If stipulated in the Bidding Documents, the Bidder shall furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder. Bonds may be secured through the Bidder's usual sources, §7.1.2 Ifthe furnishing of such bonds is stipulated in the Bidding Documents, the cost shall be included in the Bid, If the furnishing of such bonds is required after receipt of bids and before execution of the Contract, the cost of such bbonds shall be added to the Bid in determining the Contract Sum. §7.1.3 Ifthe Owner requires that bonds be secured from other than the Bidder’s usual sources, changes in cost will be adjusted as provided in the Contract Documents. {§7.2 TME OF DELIVERY AND FORM OF BONDS §7.24 The Bidder shall deliver the required bonds to the Owner not later than three days following the date of execution ofthe Contract. Ifthe Work isto be commenced prior thereto in response to a letter of intent, the Bidder shall, prior to commencement of the Work, submit evidence satisfactory to the Owner that such bonds will be fummished and delivered in accordance with this Section 7.2.1. {§7.22 Unless otherwise provided, the bonds shall be written on AIA Document A312, Performance Bond and Payment Bond. Both bonds shall be written inthe amount ofthe Contract Sum, §7.23 The bonds shall be dated on or after the date of the Contract. §7.24 The Bidder shall require the attomey-in-fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of the power of attorney. ARTICLE 8 FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR Unless otherwise required in the Bidding Documents, the Agreement for the Work will be written on AIA. Document A101, Standard Form of Agreement Between Owner and Contractor Where the Basis of Payment Is 8 Stipulated Sum, ‘NA Document ATO1™~ 1087. Copyright ©1070, 1074, 1078, 1087 and 107 by The Ameren ratio of Architects, Allright reserved. WARNING: {This AIK" Documents protectad by US Copyright Law and inernational Treats, Unathortaed aprodiction or astrbuton of ts AIA™ Document, o any portion of may resuit in severe cil and ximinal ponalte, and wl be prosecuted tothe maximum exert possileundor the law, This document was rodutod by AA sofware at 16:42:48 on 1/27/2007 undo Ord’ No, tOUD274268 | whlch oxpos on 12/1/2007. ands net or (1228200071) HIGH POINT ABC ‘SECTION 00110 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS: ‘The “Instruction to Bidders,” AIA Document A701-1997, as published by the American Institute of Ar- chitects, is bound herein, and made a part of this document. Modify and supplement Articles of AIA Document A701 as follows: ARTICLE 2 - BIDDER’S REPRENTATIONS, Subparagraph 2.1.3, Add: “2.1.3.1 Before submitting a bid for his work, each Bidder shall examine the premises and satisfy ‘himself as to the existing conditions that will in any manner affect the work under his contract. No allowances shall be made subsequently, in this connection, in his behalf for any error or negligence on his part." ARTICLE 3 - BIDDING DOCUMENTS Subparagraph 3.4.4; Add: “3.4.4.1 A copy of such Addendum will be mailed or delivered to each Prime Bidder receiving a set of documents from the architect. 3.4.4.2. The Owner will not be responsible for any other explanations or interpretations of such docu- ‘ments which anyone presumes to make on behalf of the Owner before Bid Opening. 3.4.43. Itis the responsibility of each Prime Bidder to verify for himself that he has received all Ad- denda; and that material suppliers are familiar with and included in their price all Addenda issued up to the time for Bid Opening, 3.4.4.4 The Bidder shall state the number of addenda received in the appropriate space on the Bid Form.” ARTICLE 4 - BIDDING PROCEDURES Subparagraph 4.1.1; Add: “4.1.1.1 Bach Bid shall be prepared on the blank Bid Forms provided by the Architect. The sample Bid Form bound with the Project Manual shall not be used, The Bidder shall indicate his correct name, address, and license number in the space provided in the upper right comer of the first page of the bid form.” Subparagraph 4.1.3; Add: “4.1.3.1 ‘The amount of the Base Bid shall be the total charge for the Project, not including any alter- nates. SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 0110-1 HIGH POINT ABC 4.1.3.2. Bidders shall submit unit prices required by the Bid Form. 4.13.3 All applicable taxes, sales, use, etc. shall be included in the lump sum bid submitted. 4.1.3.4 The cost of Building Permit shall be included in the lump sum bid submitted. 4.1.3.5 The Bidder shall state in his Bid the number of calendar days from date of signing Contract in which he will guarantee to complete the work.” Subparagraph 4.1.7; Add: “4.1.7.1 Each bidder shall indicate again his correct name on the last page of the Bid Form above the signature. Bids by individuals must be signed by the person bidding. Bids by construction company with sole owner shall be signed in the name of the company by the owner of the company. Bids by partnership shall show the full name of all partners and shall be signed in the name of the partnership by one of the partners. 4.1.7.2. Bids by corporations shall indicate the legal name of the corporation followed by the name of the State of incorporation; and shall be signed by the president, secretary, or one of the other officers of the corporation. The signature of a person authorized as agent to bid will be acceptable provided the Bid is accompanied by proper power-of-attorney. Bids by corporations shall have the corporate seal affixed adjacent to the signature. 4.1.7.3 All signatures shall be in ink, and the name of the person signing shall be typed also or printed below the signature followed by a title showing the relationship to the bidding organization such as: “Owner” in the case of a partnership; “President”, “Vice-President”, “Secretary”, or “Treas- urer”, in the case of a corporation; or “Agent” in the case of someone acting as agent or attomey-in- fact. A Bid by a person who affixes to his signature the word “President”, “Secretary”, or “Agent”, etc., without disclosing the name of his organization may be held as an individual bidder.” Subparagraph 4.2.1; Add: “4.2.1.1 The Bid Bond required to be submitted with the Bid Proposal shall be in the amount of 5% of the Bid Proposal. Subparagraph 4.3.1; Add: “43.1.1 Bach Bid shall be submitted in a sealed opaque envelope indicating the Bidder’s name, and shall be marked in the lower left-hand corner as follows: “Bid for (name of Project) a Bidder’s Name * a ‘License No, a 43.1.2 Sealed envelope shall be addressed to The City of High Point Alcoholic Beverage Control Board.’ SUPPLEMENTARY INSTRUCTIONS TO BIDDERS oo110-2 HIGH POINT ABC Subparagraph 4.4.2; Add: “4.4.2.1 Bids may also be withdrawn after the public opening if an unintentional, substantial error is ‘made by the contractor and it can be proven that the error was arithmetic or an omission. The request to withdraw a Bid must be made in writing to the Owner within seventy-two (72) hours after the opening of Bids. The Bid guaranty of any Bidder withdrawing his Bid in accordance with the forego- ing conditions will be retumed promptly.” ARTICLE 5 - CONSIDERATION OF BIDS Subparagraph 5.2; Add: “5.2.1 Bids may be rejected if they show any unexplained erasures, omissions, alterations of form, additions not called for, added restricting or qualifying conditions or other irregularities of any kind.” Add: “ARTICLE 9 - SUPPLEMENTARY INSTRUCTIONS. 9.1 LIQUIDATED DAMAGES 9.1.1 The contractor shall pay liquidated damages to the Owner as described SUPPLEMENTARY GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION, ARTICLE 9; Para- graph 9.11 9.2. CONSTRUCTION DOCUMENTS 9.2.1 Ten (10) copies of Drawings and Specifications shall be furnished, free of charge, to the success- ful bidder for General Construction.” 9.3 MINORITY BUSINESS PARTICIPATION GOALS, 9.3.1. Per G.S, 143-128, the state and local goal for Minority Participation in 10%. Good faith efforts ‘must be made by the bidders to attain this goal. Failure of a bidder to comply with the requirements is grounds for rejection of the bid. ‘SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 00110 -3 HIGH POINT ABC SECTION 00401 - BID FORM High Point Alcoholic Beverage Control Board Bidder 201 West Fairfield Road Address - High Point, NC 27263 NC License No, Date Gentlemen: The undersigned, having carefully examined the Bidding Docu, Agreement" Conditions of the Contract, Drawings, and Specifications, all subsequent Addenda ‘as ed, by'the.Arel hitést, Warren Architecture, P.C., visited the site and being familiar with all condition isco ‘of the work, hereby agrees to furnish all labor, materials, equipment and services, ete. i yding all allowances, to ‘complete the construction of: “y ABC STORE NO. 735" gD 1583 SKEET mre “ey ‘ HIGH POINT, All to be in accordance with these documents for i ee? ee BASE BID: Dollars (s ‘TIME OF COMPLETION _ be a ‘The undersigngé:further shies td's sign Gghract for all work in the above amount, if offered within forty-five dys aftérreceipt of Bids & s ‘The uniiérsigned s tha in the case of failure on his part to execute the said contract and bond within ten lendar days after written notice being given of the award of the Contract, the Owner thay, upon discretion, withdraw such notice of award, < ‘The undersignedtfurther‘larces to begin work promptly after a notice to proceed with an adequate force, carry the work forwetd as rapidly as possible and complete the entire project no later than calendar days from the date of the Owner-Contractor Agreement. UNIT PRICE SCHEDULE Should the undersigned be required to perform work over and above that required by the Contract Documents, or should he be ordered to omit work required by the Contract Documents, he will be paid an extra amount or shall credit the Owner, as the ease may be, on the basis of unit prices stated herein, prices quoted being sum total compensation payable or creditable for such items in place. BID FORM 00401 = 1 HIGH POINT ABC Unit prices quoted and accepted shall apply throughout the life of the Contract, except as otherwise specifically noted. Unit prices shall be applied, as appropriate, to compute the total value of changes in the scope or the work all in accordance with the Contract Documents. __ Work TT Rock Excavation .. Rock Excavation (Trench) . Additional Earth Excavation (Bulk) . Additional Earth Excavation (Trench) 5. Additional Fill . Unsuitable Soil Removal Conerete in forms (not reinforced) paveenr ADDENDA, Addenda have been received as follows: Addendum No. Addendum No, ‘Addendum No. ‘Addendum No. CONTRACTOR LICENSE ‘The undersigned further states that he ig duly lice 1 Contact, forthe type of work proposed, in the State of North Carolina, and that all fee rit, ete: Goin to the submission of this proposal have ‘been paid in full, £ Itis distinctly understood that pic ih Point Alcoholic Beverage Control Board reserves the right to rejestdand all bids shOuld they. deem it to be in the best interest of the Owner. ha FE é - oa eu 20, Name of Firm or Crea biting Bid Treense Witness: By: Title: (Owner Pariner(President¥. President Attest: By: BID FORM 00401 -2 ‘HIGH POINT ABC Title: (Affe Corporate Seal Here) (Corp. Secretary or Asis. Secretary Onby) BID FORM 00401 -3 HIGH POINT ABC SHELL COST DETAIL SUMMARY Complete the following cost summary and return with completed bid package. | HARD COSTS. TOTAL COSTS: General Conditions Sitework Landscaping Conerete Structural Steel I 2. 3. 4. 3.__| Masonry 6. 7.__| Miscellaneous Carpentry 8 Millwork and Shelving 9. | Roofing 10. _ | Thermal and Moisture Protection TI, __| Glass and Glazing 12.__| Doors, Frames and Hardware 13.___| Metal Studs and Gypsum Board [4 Ceilings (15. [ Floor Coverings 16.__ | Wall Coverings 17.__| Specialties 18,_| Dock Equipment a 19, _ | Plumbing 20. | HVAC ay 21.__| Electrical 22.__| Overhead and Profit 23.__| Bonds BID FORM 0401-4 HIGH POINT ABC SECTION 00410 - BID BOND ‘The Bid Bond, AIA Document A-310-A, 1970 Edition, shall be the form of Bid Bond, and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices. END OF SECTION BID BOND 0410-1 HIGH POINT ABC SECTION 00501 - FORM OF AGREEMENT The Standard Form of Agreement Between Owner and Contractor where the Basis of Payment is a Stipulated Sum, AIA Document A101, 1997, as modified, shall be the form of Agreement, and is incorporated into the Contract Documents by reference Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices. END OF SECTION FORM OF AGREEMENT 0501-1 HIGH POINT ABC ‘SECTION 00510 - PERFORMANCE BOND The Performance Bond, AIA Document A-312, 1984 Edition, shall be the form of Performance Bond and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices. END OF SECTION PERFORMANCE BOND 0510-1 HIGH POINT ABC SECTION 00520 - PAYMENT BOND ‘The Payment Bond, AIA Document A-312, 1984 Edition, shall be the form of Payment Bond and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices. END OF SECTION PAYMENT BOND 00520- 1 HIGH POINT ABC SECTION 00670 - AFFIDAVIT OF CONTRACTOR ‘The Contractor's Affidavit of Payment of Debts and Claims, AIA Document G-706, 1994 Edition, shall be the form of Affidavit of Contractor, and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices. END OF SECTION AFFIDAVIT OF CONTRACTOR, 0670-1 HIGH POINT ABC SECTION 00680 - AFFIDAVIT OF CONTRACTOR (Release of Liens) ‘The Contractor's Affidavit of Release of Liens, AIA Document G-706-A, 1994 Edition, shall be the form of Affidavit of Contractor, and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC 20006, or from the local AIA offices, END OF SECTION AFFIDAVIT OF CONTRACTOR (Release of Liens) 00680- 1 HIGH POINT ABC ‘SECTION 00690 - CONTRACTOR’S GENERAL WARRANTY CITY OF HIGH POINT ALCOHOLIC BEVERAGE CONTROL BOARD ABC STORE NO. 7 1583 Skeet Club Road, High Point, North Carolina ‘The undersigned Contractor hereby warrants, in accordance with the applicable provisions and terms set forth in the Contract Documents, all materials and workmanship incorporated in the City of High Point Alcoholic Beverage Control Board ABC Store No. 7, 1583 Skeet Club Road, High Point, North Carolina; against any and all defects due to faulty materials or workmanship or negligence for a period of 12 ‘months, or such longer periods as set forth in the Contract Documents, from the effective date of this warranty. This Contractor further warrants all work incorporated in this project to remain leakproof and ‘watertight at all points for a period of 24 months from the effective date of this Warranty. ‘This Warranty shall be binding where defects occur due to normal usage conditions and does not cover willful or malicious damage, damage caused by acts of God or other casualty beyond the control of the Contractor. This Warranty shall be in addition to other warranties and guarantees set forth in the Contract Documents, and shall not act to constitute a waiver of additional protection of the Owner afforded, where applicable, by consumer protection and product liability provisions of law, and theses stipulations shall not constitute waiver of any additional rights or remedies available to the Owner under the law. Signed: ‘Name Tith Date: (Corporate Seal) Subscribed and sworn before me this day of. »20_. (Notary Public) END OF SECTION CONTRACTOR’S GENERAL WARRANTY. 00690- 1 HIGH POINT ABC SECTION 00701 - GENERAL CONDITIONS OF THE CONTRACT ‘The General Conditions of the Contract for Construction, AIA Document A-201, 1997 Edition, shall be the form of General Conditions, and is incorporated into the Contract Documents by reference. Copies of the standard forms cited are available for examination at the office of the Architect. Copies of the standard forms may also be obtained from The American Institute of Architects, 1735 New York Avenue, N.W., Washington, DC. 20006, or from the local AIA offices. END OF SECTION GENERAL CONDITIONS OF THE CONTRACT 00701-1 HIGH POINT ABC SECTION 00801 - SUPPLEMENTARY GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION ‘The “General Conditions of the Contract for Construction,” AIA Document 4201-1997, as published by the American Institute of Architects, is bound herein, and made a part of this document. The Supplementary Conditions contain changes and additions to the “General Conditions of the Contract for Construction”, ATA Document A201-1997. Where any portion of an Article in AIA Document A201 is modified or voided by the Supplementary Conditions, the unaltered provisions shall remain in effect. Modify and supplement Articles of AIA Document A201 as follows: ARTICLE 1 - GENERAL PROVISIONS. 1.1 BASIC DEFINITIONS Subparagraph 1.1.1; Add: “1.1.1.1 The Contract Documents shall also include AIA Document A312 - Performance Bond, AIA Document A312 - Payment Bond and Insurance Certificates.” ARTICLE 2— OWNER, 2.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER, Subparagraph 2.2.3; Add “All other grade lines shall be established and maintained by the Contractor.” Subparagraph 2.2.5; delete and substitute: “2.2.5 The Contractor will be furnished, free of charge, ten (10) copies of Drawings and Project Manuals for execution of the Work.” ARTICLE 3- CONTRACTOR 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR Subparagraph 3.2.1; Add: “The Contractor shall request and receive from the Architect, in writing, clarification of such error, omission or inconsistency before proceeding with the Work.” ‘Add the following subparagraphs: SUPPLEMENTARY CONDITIONS: 00801 -1 HIGH POINT ABC “3.2.4 Should the Contractor discover a conflict between the Specifications and Drawings, he shall request and receive clarification from the Architect, in writing, before proceeding with any work re- Jated to the conflicting documents. 3.2.5 Should the Specifications fal to particularly describe the material or kind of goods to be used in any part of the Work, the Contractor shall request additional information of the Architect before performing the Work, The material that would normally be used in such part of the Work to produce first quality finished work shall generally be considered the intended standard. 3.2.6 The Contractor shall examine all Drawings and Specifications for all portions of the Work. All Work for which a particular trade is responsible is not necessarily shown on the section of the Draw- ings and Specifications primarily applying to that trade. No allowance shall be made for the Contrac- tor’s failure to familiarize himself with the complete documents and to adequately apply his forces.” 3.5 WARRANTY Add the following subparagraph: “3.5.2. All warranties and guarantees shall be executed by the manufacturer or Contractor as applica- ble and addressed to the Owner. All warranties and guarantees shall be submitted to the Owner, in writing, upon completion of the Work and prior to the Final Certificate of Payment.” ARTICLE 4~ ADMINISTRATION OF THE CONTRACT 4.2. ARCHITECT'S ADMINISTRATION OF THE CONTRACT Subparagraph 4.2.4; Add: “4.2.4.1 Any instructions that the Architect may issue to the Contractor shall be for the purpose of in- terpreting the Contract Documents and not an act of supervision. ‘The Architect assumes no responsi- bility, either direct or implied, to direct and supervise the means and methods of executing the Work.” “4.2.42. Any direct communications between the Owner and the Contractor which affect the per- formance or administration of the Contract, or which modify the Contract requirements, shall be ‘made or confirmed in writing, with copies made to the Architect.” ARTICLE 5 - AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK 5.3 SUBCONTRACTURAL RELATIONS Subparagraph 5.3.1; Add: “5.3.1.1 The Owner or Architect will not undertake to settle any differences or disputes between the Contractor and his Subcontractors, nor between Subcontractors.” ARTICLE 9 - PAYMENTS AND COMPLETION SUPPLEMENTARY CONDITIONS 00801 -2 HIGH POINT ABC 9.3 APPLICATIONS FOR PAYMENT. Subparagraph 9.3.1; Add “9.3.1.3 Until final payment is made the Owner will pay 90 percent of the amount due on account of ‘monthly payments. The remaining 10 percent will be retained until the work is determined to be sub- stantially complete as specified under 9.8.” ‘Add the following Paragraph: “9.11 LIQUIDATED DAMAGES 9.11.1 As actual damages for any delay in completion are impossible to determine, the Contractor and his sureties shall be liable for/and pay to the Owner the sum of one thousand dollars ($1,000.00) per calendar day, for each calendar day of delay until the contract work is completed and accepted.” ARTICLE 11 = INSURANCE 11,1 CONTRACTOR'S LIABILITY INSURANCE Subparagraph 11.1.1; Add: “9 claims for damages sustained by any class of employee engaged in hazardous work on the Project under this Agreement, and not covered under Workmen’s Compensation.” “10 claims for damages to property arising from blasting, explosion, or collapse due to excavation, moving, shoring, and the like, and damage to facilities resulting from underground work.” Subparagraph 11.1.2; Add: “11.1.2.1 Without limiting any of the other obligations or liabilities of the Contractor, the Contractor shall purchase and maintain insurance coverage as follows or greater if required by law: 1. Workman's Compensation: a. State: Statutory b. Applicable Federal: Statutory ©. Employer's Liability: $100,000, 2. Comprehensive or Commercial General Liability (including Premises-Operations; Independ- ent Contractor's Protective; Products and Completed Operations; Broad Form Property Dam- age): a. Bodily Injury and Property Damage: $10,000,000 Combined Single Limit b, Product and Completed Operations to be maintained for two years after final payment, ¢. Property Damage Liability Insurance shall provide X,C and U Coverage. 3. Contractual Liability: a. Bodily Injury and Property Damage: $10,000,000 Combined Single Limit 4, Personal Injury: a. With Employment Exclusion deleted: — $10,000,000 Each Person Aggregate SUPPLEMENTARY CONDITIONS 00801 - 3 HIGH POINT ABC 5. Business Automobile Liability (including owned, non-owned, and hired vehicles) a. Bodily injury and Property Damage: $10,000,000 Combined Single Limit 6. Umbrella Excess Liability: Provide as acceptable to meet above limits 11,1,2.2 The Contractor shall include a Hold Harmless Clause in their insurance policy, indemnify- ing the Owner as required under Paragraph 3.18.” Subparagraph 11.1.3; A “11.1.3.1 Approval of the Insurance by the Owner shall not relieve or decrease the liability of the Contractor hereunder.” 1.1.3.2 The Contractor shall furnish one copy of each Certificate of Insurance herein required at- tached to each copy of the Agreement. The Contractor shall furnish to the Owner copies of any en- dorsements that are subsequently issued amending coverage or limits. Certificates of each Subcon- tractor’s coverage shall be on file in the Contractor’s general office.” 11.5 PERFORMANCE BOND AND PAYMENT BOND Subparagraph 11.5.1; delete and add: “115.1 Prior to signing the Contract, the Contractor shall furnish bonds covering the faithful per- formance of the Contract and the payment of all obligations arising thereunder. Cost of bond shall be paid by the Contractor. 11,5.1.1 The Contractor shall deliver the bonds to the Owner not later than the date of execution of the Contract; or if the Work is commenced prior thereto in response to notice to proceed, the Contrac- tor shall, prior to commencement of the Work, submit evidence satisfactory to the Owmer that such bonds will be issued. 11.5.1. Bonds shall be executed on the forms illustrated, Performance Bond and Payment Bond, with amount shown on each part equal to 100% of the total amount payable by terms of the Contract. Surety shall be a company licensed to do business in the State of North Carolina and shall be accept- able to the Owner, Title “Licensed Resident Agent” shall appear after signature. 115.13 Bonds shall be dated the same as or subsequent to the Contract, and shall be accompanied by a current certified Power-of-Attorney. Bond shall be furnished in sufficient number of copies 50 that one copy can be bound with each copy of the Agreement. 11.5.1.4 Seal of the bonding company shall be impressed on each copy of bond. 11,5.1.5 The Contractor's signature(s) on performance bond shall correspond to that of the Contract, and such person(s) signing the agreement involved as described under laws of the State of North, Carolina.” ARTICLE 13 - MISCELLANEOUS PROVISIONS ‘Add the following Paragraph: SUPPLEMENTARY CONDITIONS 00801 -4 HIGH POINT ABC “13.8 EQUAL OPPORTUNITY 13.8.1 The Contractor and all Subcontractors shall not discriminate against any employee or appli- cant for employment because of physical or mental handicap, race, religion, color, sex, na~ tional origin or age. The contractor shall take affirmative action to insure that applicants are employed, and that employees are treated during employment, without regard to their to their physical or mental handicap, race, religion, color, sex, national origin or age. Such actions shall include, but shall not be limited to, the following: employment, upgrading, demotion or transfer, recruitment or recruitment advertising, layoff or termination, rates of pay or other forms of compensation, and selection for training including apprenticeship. The Contractor agrees to post in conspicuous places, available to all employees and applicants for employ- ment, notices setting forth the policies of non-discrimination. 13.8.2 The Contractor and all Subcontractors shall, in all solicitations or advertisement for employees placed by them or on their behalf, state that all applicants will receive considera- tion for employment without regard to race, religion, color, sex, national origin or age.” SUPPLEMENTARY CONDITIONS 00801 -5 HIGH POINT ABC SECTION 00901 ~ SOIL INVESTIGATION DATA PART 1-GENERAL. 1.1 SOIL INVESTIGATION DATA A.A report of soil borings and subsurface investigations performed by Engineering Consulting Services, LTD and dated July 6, 2006 is attached hereto, This report is not a part of Contract, Documents and Contractor shall be responsible for any conclusions to be drawn from this information. If Contractor prefers not to assume such risk, he may employ his own experts to analyze available information and he shall assume responsibility for any consequences of acting, ‘on conclusions obtained. Owner does not guarantee continuity of conditions indicated at boring locations. END OF SECTION 00220 SOIL INVESTIGATION DATA. 00901 -1 CAROLINAS REPORT OF SUBSURFACE EXPLORATION AND GEOTECHNICAL ENGINEERING ANALYSIS OAK HOLLOW SHOPPING CENTER - ABC STORE HIGH POINT, NORTH CAROLINA ECS CAROLINAS, LLP PROJECT NUMBER G-12656 PREPARED FOR HIGH POINT ABC BOARD HIGH POINT, NORTH CAROLINA JULY 6, 2006 ECS CAROLINAS, LLP Geotechnical * Construction Materials * Environmental July 6, 2006 Ms. Rosalind R. Stewart High Point ABC Board 201 West Fairfield Road High Point, North Carolina 27263 ECS Project No. G-12656 Report of Subsurface Exploration and Geotechnical Engineering Analysis, ‘Oak Hollow Shopping Center - ABC Store High Point, North Carolina Dear Ms. Stewart: ECS Carolinas, LLP (ECS) has completed a subsurface exploration for the subject site as authorized by acceptance of our Proposal No. 9008-P, dated November 15, 2005. The purposes of this exploration were to explore the soil, rock, and groundwater conditions at the site and to develop geotechnical recommendations to guide design and construction of the project. This report presents ur evaluations and recommendations, the results of our exploration, our scope of work, and our understanding of the project information. ECS appreciates the opportunity to provide our professional services during this phase of your project. Please do not hesitate to contact us if you have any questions concerning the following report. Respectfully, Woe oR Oa, Ne CRESS * O Ops ic ECS CAROLINAS, LLP Todd J. Roberson Reviewed by: “David M. Cui Senior Project Manager Attachments cc: Mr. Mark Sohmer, AIA ~ Warren Architecture “481 Koger Boulevard + Greensboro, NC 27407 + (336) 856-7150 + Fax (336) 856-7160 => (Oak Hollow Shopping Center ~ ABC Store High Point, North Carolina ECS Project No 12656 ‘July 6, 2006 REPORT SUMMARY ‘We request you read the entire contents of this report. Recommendations and clarifications are contained in the body that are not in the report summary. Project Planning Existing fill appears generally suitable for support of foundations and grade slabs. We expect some sporadic undercutting across the site due to surficial soft soils. Depending on where the arn etaing footprint will be located, some borings indicated marginally soft sols ‘that may Tequire limited deeper undercutting of the footings. Earthwork and foundation construction red be scheduled during the drier months ofthe year whenever possible to reduce the effect of aoe tee project, Site sols ean be used as controlled fil without need for drying. We do not Expect rock excavation within typical planned excavations, Temporary ‘and permanent groundwater control measures do not appear to be necessary Design We recommend an average sttipping depth of 3 inches across area tobe cut or file. Site soils wre etal for use as controlled fill, We recommend a shrinkage factor of 15 to 20 percuit when arfcalating earthwork quantities using on-site soils for fill. We recommend a s'ope of 2:1 (FV) for permanent cut slopes. We recommend a slope of 2.5:1 for permanent fill slopes constructed using controlled fil ‘We recommend the structures be supported on shallow foundations designed for an allowable net bearing pressure of 3,000 pounds per square foot. We expect such shallow foundations will taporienee less than I inch of total settlement and on the order of 1/3 to 1/2 inch of differential settlement. We recommend the floor slab be supported on a soil subgrade, We recommend a modus of MMberade reaction of 150 pounds per cubic inch for structural design of ch sab, "The slab should Subgrade tr tony building foundations unless the connection is designed to accommodate the anticipated foundation settlements. We recommend Tight duty asphalt pavements consist of 2 inches of asphalt over 6 incies of agpregate base course stone. We recommend heavy duty asphalt pavements consist of 3 inches of asphalt over 8 inches of aggregate base course stone, Permanent groundwater control does not appear to be needed for this site Construction Limited undercutting (less than 5 feet) may be required in isolated areas of the footings. Paved reas may require limited undercutting or subgrade stabilization depending on prevailing weather conditions. Site soils can be used as controlled fill without need for drying. ak Hollow Shopping Center — ABC Store High Point, North Carolina ECS Project No 12656 July 6, 2006 Excavations for general site grading, foundations, and underground utilities can be made with a low potential for ripping, jackhammering, or blasting. The site soils are OSHA Type B and C soils for the purpose of temporary excavation support. Groundwater is not expected within planned shallow excavation depths, so temporary groundwater control is not anticipated, Oak Hollow Shopping Center — ABC Store High Point, North Carolina ‘ECS Project No 12656 uly 6, 2006 DESIGN RECOMMENDATIONS Site Grading and Earthwork Controlled fill should be compacted to at least 95 percent of the maximum dry density obtained in, accordance with ASTM Specification D-698, Standard Proctor Method. Controlled fill placed within 1 foot below pavement subgrades should be compacted to 98 percent of the standard Proctor maximum dry density. Aggregate base course (ABC) stone should be compacted to 100 percent of standard Proctor maximum dry density. ‘We recommend an average stripping depth of 3 inches across areas to be cut or filled. Site soils are suitable for use as controlled fill. We recommend a shrinkage factor of 15 to 20 percent when. calculating earthwork quantities using on-site soils for fill. Permanent Site Slopes We recommend that permanent cut slopes less than 10 feet tall through undisturbed residual soils be constructed at 2:1 (horizontal: vertical) or flatter. Permanent fill slopes less than 20 feet tall may be constructed using controlled fill ata slope of 2.5:1 or flatter. A slope of 3:1 or flatter may be desirable to permit establishment of vegetation, safe mowing, and maintenance. The surface of all cut and fill slopes should be adequately compacted, All permanent slopes should be protected using vegetation or other means to prevent erosion. ‘The outside face of building foundations and the edges of pavements placed near slopes should be located an appropriate distance from the slope. The North Carolina Building Code lists the following requirements: ‘+ Buildings or pavements placed at the top of fill slopes should be placed at distance equal to at least 1/3 of the height of the slope behind the crest of the slope, but that distance need not be more than 40 feet. ‘+ Buildings or pavements near the bottom of a slope should be located at least % of the height of the slope from the toe of the slope, but the distance need not be more than 15 feet. Slopes with structures located closer than these limits or slopes taller than the height limits indicated, should be specifically evaluated by the geotechnical engineer and may require approval from the building code official. Building Foundations We recommend the proposed building be supported on shallow foundations bearing on approved existing fill, undisturbed residual soils and new compacted controlled fil, Isolated zones of lower consistency fill were encountered and may require limited undercutting (less than 5 feet). Shallow foundations should be designed for an allowable net bearing pressure of 3,000 pounds per square foot. The allowable net soil bearing pressure refers to that pressure which may be transmitted to the foundation bearing soils in excess of the surrounding overburden pressure, We anticipate total settlements of shallow foundations for the structure should be less than about 1 inch. Differential settlements are expected to be on the order of 1/3 to 1/2 of the total (Oak Hollow Shopping Center ~ ABC Store High Point, North Carolina ECS Project No 12656 July 6, 2006 settlements. Settlements of foundations are expected to be primarily the result of elastic compression of the bearing soils and therefore settlements should occur relatively soon after the loads are applied. Settlements of heavily loaded foundations or settlement sensitive equipment should be evaluated on a case-by-case basis In order to reduce the possibility of foundation bearing failure and excessive settlement due to local shear or "punching" action, the 2002 North Carolina Building Code requires that footings have a minimum width of 16 inches. Footings should be embedded deep enough below exterior grades to reduce potential movements from frost action or excessive drying shrinkage. For this region, we recommend footings be placed at least 1.5 feet below finished grade. Floor Slab Design Approved existing fill, residual soils and controlled fill are suitable for support of a concrete slab on grade floor. We recommend a modulus of subgrade reaction (k) of 150 pounds per cubic inch for structural design of the floor slab. This value is representative of a 1-ft square loaded area and may need to be adjusted depending the size and shape of the loaded area depending on the method of structural analysis. ‘We recommend that the floor slab be isolated from building foundations unless the connection is designed to accommodate anticipated foundation settlement. Lateral Earth Pressures/Retaining Walls According to the 2002 North Carolina Building Code, retaining systems which provide a total vertical grade change of 5 feet over a horizontal distance of 50 feet or less must be designed and constructed under the responsible charge of a licensed professional engineer. ‘This includes retaining walls less than 5 feet tal that may have slopes above or below the walls. We recommend the following parameters for design of retaining wall Soil Type Unit | Active. | AtRest | Passive | Friction | Friction Weight, | Coefficient | Coefficient | Coefficient |. “Angle, | Factor Pet K, kK, Ky degrees Undisturbed 15 033 0.50 3.00 30 035 Residual Soils Controlied Fill 5 036 035) 27 | 28 035 ‘The parameters given above are for walls without appreciable backslopes. Sloping backfill behind the wall will significantly increase the lateral pressure applied to the wall, which will require ‘modification of the earth pressure coefficients recommended above. ‘The Active Coefficient should be used where the wall is allowed to rotate. Rotation at the top of the wall on the order of 0.5% to 1% of the wall height is normally required to develop the full Active Earth Pressure condition. If rotation of the top of the wall is not an acceptable condition or if the rotation will be restrained by bracing or by supported floors, then the At Rest Earth Pressure Coefficient should be used to design the wall. ak Hollow Shopping Center ~ ABC Store High Point. Norih Carolina ECS Project No 12656 uly 6, 2005 Resistance to lateral sliding of the wall will be derived from friction between the wall foundation and ‘the supporting soil and from passive earth pressure against the outside face of the embedded wall and foundation. We recommend the resistance derived from both sources be considered to act simultaneously. However, we recommend a factor of safety of 2.0 be used to compute the allowable resistance from passive pressure since considerable lateral displacement is typically required to fully ‘mobilize the passive resistance. Additionally, passive earth pressure should be neglected in the top 1.5 feet of embedment to account for seasonal drainage, shrinkage, softening, or erosion Retaining wall design should account for any surcharge loads within a 45-degree slope from the base of the wall. Below grade walls that may retain water behind them should be designed to resist hydrostatic pressures in addition to earth pressures unless an adequate wall drainage zone is provided. The surface of the backfill should slope slightly to promote positive surface water flow away from the retaining wall to prevent ponding of water behind the wall, If segmental block retaining walls will be utilized in cut areas of the site, the wall face should be located far enough away from adjacent property lines, structures, or other site constraints to permit construction of the segmental block wall. We recommend the face of the wall be located away from the site constraint by at least 2 times the total change in elevation that the retaining wall, including any slopes above or below the wall, will provide, This separation should provide approximately one ‘wall height behind the wall face to accommodate the geogrid reinforcing sheets while still allowing enough space to make a temporary excavation for construction of the segmental wall Seismic Conditions We recommend a Seismic Site Classification D in accordance with the 2002 North Carolina Building Code based on the encountered conditions. If this causes the design of the structure to be controlled by seismic loads, then additional field exploration and in-situ testing including measurement of the shear wave velocity profile of the site should be performed. Please contact us to discuss additional exploration if seismic loads control design of the structure. Pavements Pavements for the project are expected to consist of light duty parking areas and heavy duty pavements in driveway areas. Asphalt Pavements Pavement Type “Asphalt Surface ‘Aggregate Base Course, in. Course, in. NCDOT SF9.5A NCDOT ABC Stone. Heavy Duty 3 8 Tight Duty 2 6 Concrete Pavements ‘Pavement Type Concrete ‘Aggregate Base (4,000 psi @28°* | Course, in. days) NCDOT ABC Stone_} Heavy Duly 6 4 J Oak Hollow Shopping Center ~ ABC Store High Point North Carolina ECS Project No 12656 Sil 6, 2006 ‘The materials should be in accordance with NCDOT Standard Specifications for Roads and Structures. ‘An important consideration with the design and construction of pavements is surface and subsurface drainage, Where standing water develops, either on the pavement surface or within the base course layer, softening of the subgrade and other problems related to the deterioration of the pavement can be expected. Furthermore, good drainage should minimize the possibility of the subgrade materials becoming saturated over a long period of time. Large, front-loading trash dumpsters frequently impose concentrated front-wheel loads on pavements during loading. This type of loading typically results in rutting of the pavement and ultimately pavement failures. We recommend that the pavement in trash pickup areas consist of an 8-inch thick concrete slab. The slab should be sized to accommodate both the dumpster and the entire truck. Permanent Groundwater Control Based on the site conditions, we do not expect the need for permanent groundwater control at the site. CONSTRUCTION RECOMMENDATIONS ‘Subgrade Preparation and Earthwork Operations Site preparation should begin with stripping all vegetation, root-zone, and all other soft or unsuitable material from the proposed building and pavement areas. We expect a stripping depth of 3 inches based on the borings. Stripping depths will vary depending on the time of the year. During the wet seasons stripping may be deeper due to saturated soils on the surface. Following stripping and rough excavation, but prior to placing controlled fill, the exposed subgrades should be proofrolled. Unstable areas identified by proofrolling should be undercut to firm materials. If firm soils are not encountered within 3 feet below subgrade elevation in grade slab and pavement areas, the deeper unstable materials should be evaluated by the project geotechnical engineer to determine if these materials may remain in place, Any undercut areas should be backfilled with controlled fil, ‘We do not anticipate soft surficial soils unless grading operations are performed after extended wet weather. Some deeper lower consistency soils may be detected during prooffolling or when footings are excavated. If earthwork is performed during winter or after appreciable rainfall then subgrades may be unstable due to wet soil conditions, which could increase the amount of undercutting required. We anticipate that most site soils can be adequately compacted without need for special drying, measures, Drying of wet soils, if encountered, may be accomplished by spreading and discing or by other mechanical or chemical means. The ability to dry wet soils, and therefore the ability to use them for fill, will be reduced if earthwork is performed during late winter or spring. We recommend a shrinkage factor of 15 to 20 percent for calculating earthwork balances using site soils as fill. Oak Hollow Shopping Center— ABC Store High Poin, North Carolina ECS Project No 12656 Jy 6, 2006 When dry, the majority of the site soil should provide adequate subgrade support for fill placement and construction operations. When wet, the soil may degrade quickly with disturbance from construction traffic. Good site drainage should be maintained during earthwork operations to prevent ponding water on exposed subgrades, Excavation Conditions We expect excavations can be made with a low potential for ripping, jackhammering or blasting. Partially weathered rock was encountered deep in one boring, Auger refusal materials were not encountered at the borings. We do not expect hard soils and partially weathered rock that will be difficult to excavate to be encountered with typical excavation depths. ‘The site soils are OSHA Type B and C soils for the purpose of excavation support. Partially weathered rock and hard rock may be Type A materials in some cases. Excavations should be constructed in compliance with current OSHA standards for excavation and trenching safety. Excavations should be observed by a “competent person”, as defined by OSHA, who should evaluate the specific soil type and other conditions, which may control the excavation side slopes, or the need for shoring or bracing, Foundation Construction Foundation excavations should be tested to confirm adequate bearing prior to installation of reinforcing steel or placement of concrete. Unsuitable soils should be undercut to firm soils and the undercut excavations should be backfilled with compacted controlled fill or washed stone, Limited undercutting of footings may be required to obtain the design bearing pressure. Due to the depth of fill at the site we recommend foundations in fill be observed and inspected by the geotechnical engineer for approval. Exposure to the environment may weaken the soils at the footing bearing level if the foundation excavations remain open for too long a time; therefore, foundation concrete should be placed the same day that foundations are excavated. If the bearing soils are softened by surface water intrusion or exposure, the softened soils must be removed from the foundation excavation bottom immediately prior to placement of concrete. If the excavation must remain open overnight, or if rainfall becomes imminent while the bearing soils are exposed, a 1- to 3-inch thick "mud mat” of "ean" concrete may be placed on the bearing surface to protect the bearing soils, The mud mat should not be placed until the bearing soils have been tested for adequate bearing capacity. ‘Temporary Groundwater Control Deep fill sometimes has trapped water between compacted layers. Should trapped water or groundwater be encountered during excavations then temporary groundwater control measures such as gravity ditches or pumping from gravel lined and cased sumps should be sufficient to provide temporary groundwater control where necessary. ak Hollow Shopping Center ABC Store High Point, North Carolina ECS Project No 12656 July 6, 2006 ‘SPECIFICATION RECOMMENDATIONS Proofrolling Exposed subgrades shall be proofrolled using appropriate equipment to identify areas of unstable subgrade. Appropriate equipment shall be a dump truck having a single rear axle with axle weight of at least 10 tons, or a dump truck having a tandem rear axle with axle weight of at least 20 tons. Alternate equipment, such as a fully loaded pan scraper, may be utilized with approval ‘of the geotechnical engineer responsible for evaluating the subgrade during construction. Proofrolling shall consist of driving the appropriate equipment over the subgrade at a walking pace. The prooftolling equipment shall make overlapping passes across the subgrade in the same direction, with the overlap not exceeding %4 the width of the equipment. A second set of overlapping passes shall then be made in a direction perpendicular to the first set of passes. Controlled Fill Controlled fill should be placed in lifts and then compacted to at least 95 percent of the maximum dry density obtained in accordance with ASTM Specification D-698, Standard Proctor Method. Controlled fill placed within 1 foot below pavement subgrades should be compacted to 98 percent of the standard Proctor maximum dry density. Aggregate base course (ABC) stone should be compacted to 100 percent of standard Proctor maximum dry density. jum loose lift thickness depends upon the type of compaction equipment used: ‘Small, Self-Propelled or Remote Controlled (Rammax, ete.) Hand Operated (Plate Tamps, Jumping Jacks, Wacker-Packers) The moisture content at the time of compaction should be within 5 percent of the optimum moisture content determined by ASTM D698, Some soils will require a moisture content closer to optimum to facilitate compaction, while other soils can be adequately compacted at moisture contents even more than 5 percent away from optimum. For this reason, the moisture content of the fill should not be the sole reason for failing a field density test. If the density test indicates the fill is adequately compacted but the moisture content is more than 5 percent away from the optimum moisture content, the density results should be reviewed by the geotechnical engineer ‘who should then recommend whether the fill should be accepted or rejected. Controlled fill should be soil that has less than 5% fibrous organic content and a liquid limit and plasticity index less than 50 and 20, respectively. Soils with Unified Soil Classification System group symbols of SP, SW, SM, SC, and ML are suitable for use as controlled fill. Soils wit USCS group symbol of CL which meet the restrictions for liquid limit and plasticity index are also suitable for use as controlled fill. ak Hollow Shopping Center ~ ABC Store High Point, North Carolina BCS Project No 12656 uly 6, 2006 Compaction Testing We recommend that all fill operations be observed and tested by an engineering technician to determine if compaction requirements are being met. The testing agency should perform a sufficient number of tests to confirm that compaction is being achieved. For mass grading operations we recommend a minimum of one density per 300 cubic yards of fill placed or per 1 foot of fill thickness, whichever results in more tests. We recommend at least one test per 1 foot thickness of fill for every 100 linear feet of utility trench backfill. Density tests in the field shall be performed using the Drive Tube Method (ASTM D2937), the Sand Cone Method (ASTM D1556), or the Nuclear Method (ASTM D2922). If the Nuclear Method is used, the moisture content determined by the nuclear density equipment shall be verified by performing one moisture content test per ASTM D2216 for every five nuclear density tests. Foundation Testing We recommend testing all shallow foundations to confirm the presence of foundation materials similar to those assumed in the design. We recommend the testing consist of hand auger borings ‘with Dynamic Cone Penetrometer testing performed by an engineer or engineering technician, ak Hollow Shopping Center ~ ABC Store High Point, North Carolina ECS Project No 12656 uly 6, 2006 APPENDICES Appendix A— Exploration Results Appendix B ~ Exploration Procedures ‘Appendix C~ Project Description Appendix D ~ Report Qualifications Appendix E — Illustrations Site Location Map Boring Location Plan Generalized Subsurface Profile Legend Sheet and Unified Soil Classification System Soil Test Boring Logs (Ook Hollow Shopping Center ABC Store High Poins, North Carolina ECS Project No 12656 uly 6, 2006 APPENDIX A -EXPLORATION RESULTS Conditions ‘The site is a 0.96 acre tract located in the Oak Hollow Shopping Center in High Point, North Carolina. The site is currently a relatively level grass outparcel that gradually slopes down toward the west, The site is bounded by Skeet Club Road and service roads that supply Oak Hollow Shopping Center, We did not observe indications of groundwater springs or rock outcrops during our site visit. Regional Geology The site is located in the Piedmont Physiographic province of North Carolina. The Piedmont extends generally from Alabama to southern Pennsylvania and extends from the Valley and Ridge province in the west to the Coastal Plain province to the east. The soils in the Piedmont were formed by in-place weathering of parent rock and are termed residual soils (or saprolite). The typical residual profile consists of a clayey near surface horizon, where weathering is most severe, transitioning to silts and sands with increasing depth. ‘The materials transition to partially weathered rock (PWR), which is designated for geotechnical engineering purposes as residual ‘material with a Standard Penetration Test resistance in excess of 100 blows per foot. The degree of weathering typically decreases with depth until solid bedrock is encountered. Due to differential weathering along seams and less resistant materials, it is not uncommon to encounter seams and layers of harder materials within partially weathered rock. A review of the Geologic Map of North Carolina (1985) indicates the site is underlain by metamorphosed granitic rock of the Carolina Slate Belt. It is important to note that the natural geology within portions of the site may have been modified in the past by the placement of fill materials. The quality of man-made fills can vary significantly, and it is often difficult to assess the engineering properties of existing fills. Furthermore, there is no specific correlation between N-values from the standard penetration test and the degree of compaction of existing ill sols; however, a qualitative assessment of existing fills ean sometimes be made based on the N-values obtained and observations of the materials sampled in the test borings. The borings typically encountered fill and undisturbed residual soils derived from the in-place weathering of parent rock. Partially weathered rock was encountered deep in boring B-3. Hard, uunweathered rock was not encountered by the borings. The encountered conditions are summarized on the Generalized Subsurface Profile in Appendix E. Additional information is provided on the soil boring logs in Appendix E. Fill soils consisting of medium stiff to very stiff fine sandy silt with clay and rock fragments were encountered in borings B-1 through B-7 to depths of 3 to 12 feet. Standard Penetration Test values within the fill ranged from 5 to 20 blows per foot. With the exception of isolated zones of lower consisteney material in borings B-2 and B-4, the fill appeared to be well compacted. We did not find evidence of debris, rash, or excessive fibrous organic materials within the fill. ok Hollow Shopping Center — ABC Store High Point, North Carolina ECS Project No 12656 ‘July 6, 2006 The undisturbed residual soils generally consisted of medium stiff to very hard fine sandy silt and medium dense silty fine to medium sand. The residual soils typically had SPT resistance values ranging from 6 to 66 blows per foot. Partially weathered rock was encountered in boring B-3 at depths of 21 and 32 feet. Auger refusal materials were not encountered by the borings. Groundwater Conditions Groundwater was not encountered above the cave-in depths of the borings at the completion of drilling, ‘The borings caved-in at depths of 11 to 22 feet below existing grades. In this geology, the cave-in depth of a boring is often an indication of the stabilized water level although the water level may be a few feet below the cave-in depth and therefore cannot be directly observed, In general, shallow unconfined groundwater movement within the soils overlying bedrock is controlled largely by topographic gradients. Movement in this water table is generally from higher to lower elevations. Recharge occurs primarily by infiltration along higher elevations and typically discharges into streams or other surface water bodies. ‘The elevation of the shallow water table is ‘transient and can vary greatly with seasonal fluctuations in precipitation, surface water runoff, and other factors. Normally, the highest groundwater levels occur in the late winter and spring and the lowest groundwater levels occur in the late summer and fall ok Hollow Shopping Center ~ ABC Store High Point, North Carolina ECS Project No 12656 “July 6, 2006, APPENDIX B - EXPLORATION PROCEDURES Soil Test Borings Seven soil test borings, denoted B-1 through B-7, were performed on June 15, 2006 at the approximate locations shown on the Boring Location Plan in Appendix E. The boring locations were selected by ECS and were staked in the field by measuring from existing site features. Boring elevations were not available at the time of this report. Drilling was performed by a Diedrich D-50 truck mounted drilling machine using continuous- flight hollow stem augers. Soil samples were obtained by means of the split-barrel sampling procedures in accordance with ASTM Specification D-1586. In the split-barrel sampling procedure, a 2-inch O.D., split-barrel sampler is driven into the soil a distance of 18 inches by means of a 140-pound hammer falling 30 inches. The number of blows required to drive the sampler through a 12-inch interval is termed the Standard Penetration Test (SPT) value and is indicated for each sample on the boring logs. This value can be used to provide a qualitative indication of the in-place relative density of cohesionless soils. In a less reliable way, it also indicates the consistency of cohesive soils. This indication is qualitative, since many factors can significantly affect the SPT value and prevent a direct correlation between drill erews, drill rigs, drilling procedures, and hammer-rod-sampler assemblies. Representative portions of cach SPT sample were sealed in airtight containers and returned to our laboratory for classification, testing, and storage. The soil samples were visually classified in general accordance with the Unified Soil Classification System (USCS). The basic elements of the USCS are described on a legend sheet attached in Appendix E and in ASTM D2487. Additional information from each soil boring is provided on the individual soil test boring logs in Appendix E. Laboratory Testing Program Selected SPT samples from borings B-1, B-3, B-4, B-6, and B-7 were tested for natural moisture content in accordance with ASTM D2216. Results are indicated on the individual boring logs in Appendix E. u Oak Hollow Shopping Center - ABC Store High Point, North Carolina ECS Projact No 12656 uly 6, 2006 APPENDIX C - PROJECT DESCRIPTION “The project site is being evaluated for development with an ABC Store. The building will eonsist of a single story structure surrounded by asphalt pavements and landscaping, Specific structural loading for foundation information was not provided at the time of this report. We anticipate that minor cuts and fill depths relative to existing grade are planned. Project information was obtained from Mr. John Warren and Mr. Mark Sohmer of Warren “Architecture. We have received copies of a site plan that illustrates the existing development and lots ‘and a property drawing indicating the roadways and site features. 12 Oak Hollow Shopping Center ~ ABC Store High Poins, North Carolina ECS Project No 12656 July 6, 2006 APPENDIX D - REPORT QUALIFICATIONS, This report has been prepared in order to aid in the evaluation of this site and to assist the Owner and Engineer in the feasibility study of the project. The report scope is limited to the specific project and location described, and the project description represents our understanding of the significant aspects relevant to soil and foundation characteristics. The recommendations in this report have been developed using generalized subsurface conditions based on the soil test borings performed. Subsurface conditions can vary laterally and with depth, and significantly different conditions may exist at locations between the borings. Conditions different from those encountered by the borings and described in this report may require modifications to the geotechnical recommendations for the project. We recommend that the construction activities be monitored by a qualified geotechnical engineering firm to provide the necessary overview and to check the suitability of the subgrade soils for support of slabs, pavements, and footings. We would be pleased to provide these services. B ak Hollow Shopping Center ~ ABC Store High Point, North Carolina ECS Project No 12656 July 6, 2006 LLUSTRATIONS APPENDIX ‘SCALE (IN FEET) 1000 * 2000 REFERENCE: USGS TOPOGRAPHIC MAP HIGH POINT EAST, NC QUADRANGLE DATED 1951, PHOTOREVISED 1994 ———— CAROLINAS FIGURE 1 SITE LOCATION MAP OAK HOLLOW SHOPPING CENTER — ABC BUILDING HIGH POINT, NORTH CAROLINA ECS PROJECT G-12656 9921-9 ‘90-02 -9/aae serv meme swan! SYNITOUVO 0 09 warowo gusow aoa sont | ay oon | NVId NOLLVOOT DNINO& ee @ guano ——ss . Set [ear pa ao > = ® 7 ese C= [eS smuay gree, MOSReTN anion 3 2 non 7 | QS—N9 G3NOZ z INgnasv3 $95d Sl Bd ae) — ee aamuin (4.101 30 Lave A%Ua"eO) 3 STUOV £28°0 : 2S~N9 G3NOZ Gres 99d Sel Bd & ooaren 9 q Ga ce a _ rege sem VEL Ec ; 3,ch.2R00NS ~~ {88 aesengg oa atte Yad 07 ~os9zi-9 o- 92-97 RN peenrrnrs [aaa moro & eee suv ceo S| SYNITONVO ; 2 VNIIONVO HINON ‘LNIOd HOI SS eacenson fl ome come vo ONIGTING OAV NALNSO ONIddOHS so aneana on - oY we a = 2 BR MOTIOH NVO — avou ano Laays oan come soe - aMd0dd wr Ae GoVaaNSANsS CaAZIIVaANAD ons ane — reff] sau rw 2 wow/sna) ru = vu] © ganold OST WOOO VOS (1 = «1 38 S3ONVLSIC WOUAIA sivos Gl iON S55NvIsIG WINOZOH % (99510 nuis¥) L003 ¥3d SMOG Ni JONVISISR 1531 NOUWUINIE GUVGNVIS INISBUEY SONRIOG OL DGN SUBENNN “1 's310N Ov- Ov- CD Bee @ G03 AS an W oe- oe- swf] 9? C F wu aA RY 9705 CAND) cao, oO > ~ 02 8 03.002 8 €03 a = 02e- 0e-= e ID cna CD aad fe oy 6 [ a OST 8 03 0S a G02 0ST a A039 0ST 8 aOF WwW 7 ie wff]z wfffee ws fife will se 4, ||feto- 5, ||] erm ay ~o- on i oI- aaa} | “> Ww 2 oI- at Will or a wile ” st 3 m4] |g " a 9 tHa| [or oe " nu “ sus} [2 aaa} | § wy] |4 ae) a i Be a or 6 © on 6 ot 0 0 \ | | | | | 1 L-8 9-8 sa o-€ e-€ 2-4 1-8 ak Hollow Shopping Cener~ ABC Store High Point, North Carolina BCS Project No 12656 July 6, 2006 REFERENCE NOTES FOR BORING LOGS I. Drilling and Sampling Symbols: ‘SS Split Spoon Sampler RB Rock BitDrilling ST Shelby Tube Sampler BS Bulk Sample of Cuttings RC Rock Core: NX, BX, AX PA Power Auger (no sample) PM __ Pressuremeter HSA Hollow Stem Auger DC — Dutch Cone Penetrometer WS Wash Sample ‘Standard Penetration Test Blow Count (Blows/Ft) refers to the blows per foot of a 140 1b. hammer falling 30 inches on 2 2 inch O.D. split spoon sampler, as specified in ASTM D-1586. The blow count is commonly referred to as the N-value. IL. Correlation of Penetration Resistance to Soil Consistency: Sands Cohesive Soils - Silts and Clays ser Consistency SPT Consistency Unconfined Nvalue Novalue Compressive ‘Sength, Op, tsf 0-3 Very Loose 0-2 Very Soft 0-025 4-9 ‘Loose 3-4 Soft 0.25 -05 10-29 Medium Dense 5-8 Medium Stift 05-10 30-49 ‘Dense 9-16 Stiff 1.0-2.0 50 - 100 Very Dense 17-29 Very Stiff 20-40 100+ Partially Weathered Rock 30-50 Hard 40-80 50 - 100 Very Hard >80 100+ Partially Weathered Rock IIL. Unified Soil Classification Symbols: GP Poorly Graded Gravel ML Low Plasticity Silt GW Well Graded Gravel MH is GM Silty Gravel cL Low Plasticity Clay GC Clayey Gravel CH High Plasticity Clay SP Poorly Graded Sand OL ——_Low Plasticity Organics SW Well Graded Sand OH High Plasticity Organics SM Silty Sand CL-ML Dual Classification SC Clayey Sand (typical) IV. Water Level Measurement Symbols: WL Water Level AB After Boring WS While Sampling AC After Coring WD While Drilling ‘The water levels are those water levels actually measured in the borehole at the times indicated by the symbol. The measurements are relatively reliable when augering, without adding fluids, in a granular sol. In clays and plastic silts the accurate determination of water levels may require several days for the water level to stabilize. In such cases, additional methods of measurement are generally applied. Unified Soil Classification System (ASTM Designation D-2487) a ion Group Symbol Tapia Nese losfcaron Chere j ow ‘Well-graded gravels and gravel sg Cx=Dyp/Dyo Greater than + Au snd minus ie ono fins Fla tW¥f0eDyp Berven and 3 2 oP Poorly graded gravels and gravel Ed Nor menting both epiers for GW al Enlmiuesliticornoine = 3S 3S 3| 5 erie 2,6 GM Sip yaveln grovebsandats ——-B GA.E Aree limbs pot belay A" line or g rire BSS F plasticity index ass chan + 32 Leake Be cc Clayey gravels gravelsand-clsy -Anorberg limits plot above "A" ine 3 misnures, ioe and plasticity index greater chan 7 a ee el) ee ee a| 38 sands; linle or no fines B gE g Con DyPDyrDe) Bewesn | ands B| 3s cere - 3) 33 Ge owiy godedsandsand purely gB2 _Notmenng both aor SW 28a sands, litle orno fines ge g| age bE 2 SM Silty sands, sand intr ee ee bant ; 22 Atria inks plrsbove 7 g ML __Inorganie sits, very fine sands, ‘See Ccrapeeoeeig woe fi arb 2 rookie iyo elayey Be ar 5 = LLEEIT= 1 Z Cl trarginiecin oflowiemediem { i pas. povelly in ney 3 clays, silty clays, lean clays: a zg ee 8 ol ‘Organic sls and organic sity 5 : hays of ow plasty Q 5 Mair Tnorgenie sis, miesceous oF . . Fatomoczou ine Fads Fi, g clas ae bar peach i Saciays ou ae OH Oigasiocoys of medium high ‘Piha fr he laa of fae plaseity "Tents made on Faso Hiner han No 4D seve Highly erganie soils mt ‘em, muck and other highly organic soils ‘Fibrous organie mater, will char, bur, or plow UNIFIED SOLL CLASSIFICATION SYSTEM CLIENT HIGH POINT ABC BOARD 708 # ‘BORING # G-12656| B-1 ‘SHEET Lor 4 PROJECT NAME SAGE CUB ND - OM ROL SPRING CONTR 18 BLE “ARCHITECT-ENGINEER SITE LOCATION HIGH POINT, NORTH CAROLINA pee ~O- calms, prengourren se gum ini 3 E ere OF BIG OTS TE) cx que sat & acret E g E B |g |porrow oF casmic BB} toss oF circurarion [r50R> | 4 E we —00—| Bg 5 i i SURFACE ELEVATION EG] @ smogp papmanon ote som 50 40 ote 5 Topsoil Depth 3” ]1|ss|1e|15] “FILLY Brown, Fine Sandy SILT, 0®@ @ With Cloy cnd Rock Fragments, 172 Wet, Stiff, (FILL) 2 |ss]38 17] “RESIDUAL: Ton, Brown, Fine ay 5 Sandy Clayey SILT, Moist, Stiff, (ML) +} |ss|18| 16 4 q Tan, Brown, Fine Sandy SILT Moist, Stiff to Very Stiff, 4 =] (ML) 4 |ss| 18] 16 ie 18 [15 13 1615 19 4 END OF BORING @ 20.0' 25 THE STRATIFICATION LINES REPRESENT WE WPPRONDNATE BOUNDARY LINES SETVEDN SOR TYRES D-STTU THE TRANSITION WAY Be GRADUAL ym. DRY ¥5 of @| Bonne stereo 06-16-06 Ymuscy DRY mace) BORING COMPLETED 6-16-06 CAVE IN DEPTH © 14,0" um WAR (08-28-06) MAR (07-00-06) mc D5Q__Forsua’ WINGO DRILING METHOD HSA se en 6) caer Toa BORING # a __HIGH POINT ABC_BOARD _G-12656| 8-2 tor Ec FECT WE TT ECE EUs... ‘SHEET CUB ROAD ONK HOLLOW SHOPFNG CMTE AB BULEING \SAROUINAS. SITE LOCATION =O Saar, reer HIGH POINT, NORTH CAROLINA 1 ee [ riasnic area aqui thor cowrgr x nar - | Sees E E) _ [PESCRPTION oF nara ENGL TRS TE] ace quam ons w Recover | 2) E| 8) g [oom or ame Batson cnomanon BD BEL RO og eo —| 5 i 8) E | |suurnce mzvaros E 8] @ swogp znemnos } a| a8 BL to mp ao so 808 4 Topsoll Depth 2” E 1 Jss|18/15] “Fills Grown, Fine Sandy SILT, 9 With Clay, Rock Fragmenis, a Trace Roots, Wet, Stiff to Jessfiefis| Medium sift, (FILL) E A 5 E | —{ RESIDUAL: Tan, Green, Fine “fs |ss|ie [ie] Sandy Silt, With Cloy, Moist, = 20 4 Very Stiff to Stiff, (ML) ss| 1815 16 ss[ie|i4 7 12 ss[16| 16 10 END OF BORING @ 20.0’ THE SYRSTOPIEATION LINES REPRESENT THE APPROWGNATE: BOUNDARY UES RETVEDN SOIL TWPES -SITU THE VARMETION WAY BE GRADUAL ym DRY ys or @| pone sure 6-16-06 Emvoon DRY Yeucs) Bom COMPETED —_QG—16—O6 [AEN DEPTH 13.57 em Re DSO FOREUN WINGO [PRILING MEMIOD HSA CLIENT HIGH POINT ABC BOARD 308 G-12656 BORING # B-3 —— — ascear2| PROIECT NAME KETC RMD ~ OK HOON SHOPPS CENTER ABUL “ARCHITECT-ENGINEER ECs... ‘SITE LOCATION =o msrp Ree HIGH POINT, NORTH CAROLINA 1 z 3 4 Se yume wan uo oe hr 7 me ogee ae Fg [RO oF EE OT TE sae gare ae «we |B} a] S leorow or cisme toss or oncusmon FEB] SG | Bor on dine i00e 8] §/ 3] | ene mo i a| a) ale oS ooo Depth 3” 7 |ss|ie}i6| “FILL Brown, Fine Sondy SILT, Wik, Clay’ and. Rock Fragments, 4 Motat, Very sii fo Shite We |ss{is) 0 (FILL) 5 3 [ss|ie| 0 —_Q6—16—-06 [CNT I DUPTH @ 11.5) | ye meD50 FeRRAN WINGO | DRELING MaTHOD Hs cuieNT ‘PROJECT NAME 708 BORING = | HIGH POINT ABC BOARD |_G-12656| 8-6 ced Ec : Tcaecr- eos EGS... MEET CUB ROAD - CHK HOLLOW SHOPPING CENTER AC BUG _ \SAROUINAS ‘SITE LOCATION “O- cnisirg eesernourreR HIGH POINT, NORTH CAROLINA t 2 3 5+ = oo. = Pecceeeeeeee ee ests eee ; Bea SR SAR GE acc ote z 2] E) Bg lnorow or caswc Mp toss or excmanos HR] H Z| ROO Hwee ——— | 2 O/B) E)E) fsmace nox BE] sung rpemcon oF Topsoil Depth 2” Fr fss[ie [is] FLL Brown, Fi Senay SUT ae Moist, Stiff, (FILL) 2 ss} 18 | 16 5 RESIDUAL: Tan, Brown, Fine —]3|ss|18]14] Sandy Clayey SILT, Moist, Stiff, (ML) oan 18 }15, 10 4 Moist, Hard, (ML) 15- END OF BORING @ 15.0’ [HE STRATIFICATION LINES REPRESENT TE APPROWDATE BOUNDARY LINES BETWEEN SOIL TPES VST Tee TRANSITION BAY BE GABOR mm DRY ws on @|sonnc sure 6-16-08 Gruscm DRY _Yeuacey Bonne COMPLETED Q6—16—06 [cave w DEM © 11.5" Em mG D50 FORRAN WINGO. DRILUNG METHOD HSA i cueNT 708 BORING a ——— HIGH POINT ABC_BOARD G-12656] 8-7 tor Ec eer hae “ciara ~SS... SKEET CLUB ROAD - QAK HOLLOW SHOPPING CENTER ABC BLING |Sanounas SITE LOCATION “> CA perTen HIGH POINT, NORTH CAROLINA pe gs Pusnc wane ‘ago uur cows dag =| x oe El lJ g [PRSCRFTON oF waremin. exes Uns [a ET a a EB | 2/5] 8] g foray or casts toss oF crecuanoy Gsm | f Bo oa ao coe | Elalelalé BE noe raecaren i 5) 8] g [orice samrros EA] © swoup pram ; 10 a0 NE 40 sor +} Topsoil Depth 2” {1 [ss]:8|13] FILE Brown, Fine Sondy SLT, e@Q7 With Clay and Rock Fragments, 11.9 q Moist, Very SIiff to tif, Ae lss}ie}u] (FILL) 13 5 + FILL: Brown, Fine Sandy Clayey {3 |[ss}1e]14] SILT, With Rock Frogments, Moist, Medium tiff, (FILL) 4 FILL: Brown, Fine Sandy Clayey =| 4 | SS/ 18} 16 SILT, With Rock Fragments, 18 105 Moist, Very Stiff, (FILL) 4 RESIDUAL: Tan, Brown, Fine q |_| Sandy SILT, Moist, Very Sift, =]s|ss}1efic] (MY 22 15- END OF BORING @ 15,0" -LLJ |" “Fe Feneniornes eR ne ERE BOUNDARY LINES BETWEEN SOIL TYPES DCSITU THE TRANSITION DAY BE GRADUAL gm DRY 5 on @| norine staxren 06-16-06 [gmoom DRY Ywuiacr) BORNO COMPLETED Q6—16—O06 | cave mt DEPTH @ 41,9" Im Re D50 Foran WINGO DRELING METHOD HSA HIGH POINT ABC SECTION 01100 - SUMMARY PART 1 -GENERAL Ll 12 13 14 A ¢, WORK COVERED BY CONTRACT DOCUMENTS, Project Identification: Project consists of 5,670 square foot ABC retail store. 1. Project Location: 1583 Skeet Club Road, High Point, NC. 2. Owner: City of High Point Alcoholic Beverage Control Board, Architect Identification: The Contract Documents, dated November 20, 2007 were prepared for Project by Warren Architecture, P. C., 390-C South Stratford Road, Winston-Salem, NC. ‘The Work consists of construction of a one story, 5,670 square foot retail store. The building envelope consists of brick veneer and EIFS on metal stud walls, single-ply and metal roofing, and concrete slab. The structural system consists of steel columns with bar joists and steel trusses. The HAC system consists of roof-top package units, Project will be constructed under a general construction contract. USE OF PREMISES General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Owner's right to perform work or to retain other contractors on portions of Project. FUTURE WORK Future Contract: Owner has awarded a separate contract for additional work to be performed at the site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract. The Contract for future work includes the following: 1, Security: A separate contract has been awarded to Century Watch for furnishing and installation of the security system. 2, Retail Fixtures: A. separate contract has been awarded to Display Options, Inc. for furnishing and installation of free standing retail shelving fixtures, SPECIFICATION FORMATS AND CONVENTIONS Specification Format: ‘The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "MasterFormat" numbering system. SUMMARY 01100 -1 HIGH POINT ABC B, Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations, ‘These conventions are as follows: 1, Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates. 2, Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted. a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01100 SUMMARY 01100 -2 HIGH POINT ABC SECTION 01210 - ALLOWANCES PART 1 -GENERAL 1 12 13 14 A SUMMARY This Section includes administrative and procedural requirements governing the following: 1. Unit cost allowances. See Division 1 Section "Unit Prices" for procedures for using unit prices with quantity allowances. SELECTION AND PURCHASE At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work. Purchase products and systems selected by Architect from the designated supplier. SUBMITTALS Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance. UNIT COST ALLOWANCES ‘Unit cost allowances include cost of materials onty. Contractor's overhead, profit, and related costs for labor, related products and equipment are not included in the allowance and are part of the Base Bid. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs, PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION ALLOWANCES o1210-1 HIGH POINT ABC ‘A. Examine products covered by an allowance promptly on delivery for damage or defects. Retum damaged or defective products to manufacturer for replacement. 3.2 PREPARATION A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that cach allowance item is completely integrated and interfaced with related work. END OF SECTION 01210 ALLOWANCES 01210-2 HIGH POINT ABC SECTION 01250 - CONTRACT MODIFICATION PROCEDURES PART 1 GENERAL Ll 12 13 A B. SUMMARY This Section specifies administrative and procedural requirements for handling and processing Contract modifications. Sce Division 1 Section "Allowances" for procedural requirements for handling and processing allowances, See Division 1 Section "Unit Prices" for administrative requirements for using unit prices ‘MINOR CHANGES IN THE WORK Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA. Document G710, "Architect's Supplemental Instructions." PROPOSAL REQUESTS Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications, 1, Proposal Requests issued by Architect are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change. 2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change, a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. ©. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change. 1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time. CONTRACT MODIFICATION PROCEDURES 01250-1 HIGH POINT ABC 1s 16 2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. 3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. 4, Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. 5. Comply with requirements in Division 1 Section "Product Requirements" if the proposed change requires substitution of one product or system for product o system specified, Proposal Request Form: Use AIA Document G709. ALLOWANCES Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances, ‘mixing wastes, normal product imperfections, and similar margins. 1, Include installation costs in purchase amount only where indicated as part of the allowance. 2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed. 3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances. 4, Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the Purchase Order amount or Contractor's handling, labor, installation, overhead, and profit. Submit claims within 21 days of receipt of the Change Order or Construction Change Directive authorizing work to proceed. Owner will reject claims submitted later than 21 days after such authorization. 1, Do not include Contractor's or subcontractor’s indirect expense in the Change Order cost amount unless itis clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents. 2. No change to Contractor's indirect expense is permitted for selection of higher- or lower- priced materials or systems of the same scope and nature as originally indicated. CHANGE ORDER PROCEDURES On Owner's approval of a Proposal Request, Architect will issue a Change Order for signatures, of Owner and Contractor on AIA Document G701. CONSTRUCTION CHANGE DIRECTIVE, CONTRACT MODIFICATION PROCEDURES 01250 -2 HIGH POINT ABC A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA. Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. 1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time. B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract, PART 2- PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01250 CONTRACT MODIFICATION PROCEDURES, 01250-3 HIGH POINT ABC SECTION 01290 - PAYMENT PROCEDURES, PART 1 -GENERAL, 11 SUMMARY A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment. 12 SCHEDULE OF VALUES A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule. 1, Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Submittals Schedule and Application for Payment forms with Continuation Sheets. 2, Submit the Schedule of Values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment. B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section. 1, Identification: Include the following Project identification on the Schedule of Values: Project name and location. Name of Architect, Architect's project number. Contractor's name and address. Date of submittal. gaoge 2, Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed: Related Specification Section or Division. Description of the Work. ‘Name of subcontractor. ‘Name of manufacturer or fabricator. ‘Name of supplier. Change Orders (numbers) that affect value, Dollar value. mmpaoge 1) Percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. 3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project, PAYMENT PROCEDURES 01290-1 HIGH POINT ABC 13 Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate, 4, Round amounts to nearest whole dollar; total shall equal the Contract Sum. 5. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. 6. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work. 7. Allowances: Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by ‘measured quantity. Use information indicated in the Contract Documents to determine quantities. 8. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. 9. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum. APPLICATIONS FOR PAYMENT Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner. L Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement. Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment, Application Preparation: Complete every entry on form, Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action. 1, Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made. 2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application. ‘Transmittal: Submit 4 signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required. 1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application. PAYMENT PROCEDURES 01290-2 HIGH POINT ABC F, Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment. 1, Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item. ‘When an application shows completion of an item, submit final or full waivers. ‘Owner reserves the right to designate which entities involved in the Work must submit waivers. 4, Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien, 2. 5 G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following: List of subcontractors. Schedule of Values. Contractor's Construction Schedule (preliminary if not final). Submittals Schedule (preliminary if not final). List of Contractors staff assignments. Copies of building permits Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. 8. Certificates of insurance and insurance policies. 9. Performance and payment bonds. 10. Data needed to acquire Owner's insurance. H. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. 1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum. 2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupaney of designated portions of the Work. I. Final Payment Application: Submit final Application for Payment with releases and supporting. documentation not previously submitted and accepted, including, but not limited, to the following: 1. Evidence of completion of Project closeout requirements. 2, Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. Updated final statement, accounting for final changes to the Contract Sum, AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims." AIA Document G706A, "Contractor's Affidavit of Release of Liens.” AIA Document G707, "Consent of Surety to Final Payment." Evidence that claims have been settled. noyae PAYMENT PROCEDURES, 01290 -3 HIGH POINT ABC 8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01290 PAYMENT PROCEDURES 01290-4 HIGH POINT ABC SECTION 01310 - PROJECT MANAGEMENT AND COORDINATION PART 1 -GENERAL Ll 12 A SUMMARY This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: 1, General Project coordination procedures. 2. Project meetings. See Division 1 Section "Execution Requirements’ for procedures for coordinating general installation and field-engincering services, including establishment of benchmarks and control points. COORDINATION Coordination: Coordinate construction operations included in various Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation. 1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation. 2. Coordinate installation of different components with other contractors to ensure ‘maximum accessibility for required maintenance, service, and repair. 3. Make adequate provisions to accommodate items scheduled for later installation, If necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following: Preparation of Contractor's Construction Schedule, Preparation of the Schedule of Values. Installation and removal of temporary facilities and controls. Delivery and processing of submittals. Progress meetings. reinstallation conferences. Project closeout activities. PROJECT MANAGEMENT AND COORDINATION 01310-1 HIGH POINT ABC 13 PROJECT MEETINGS ‘A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated, 1, Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times. 2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. 3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concemed, including Owner and Architect, within 3 days of the meeting. B. Progress Meetings: Conduct progress meetings at bi-weekly intervals. Coordinate dates of ‘meetings with preparation of payment requests. 1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concemed with current progress or involved in planning, coordination, or performance of future activities shall be represented at these ‘meetings. All participants at the conference shall be familiar with Project and authorized to conchide matters relating to the Work. 2. . Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time, b. Review present and future needs of each entity present, including the following: 1) Interface requirements. 2) Sequence of operations. 3) Status of submittals. 4) Deliveries 5) Off-site fabrication. 6) Access. 7) Site utilization, 8) Temporary facilities and controls. 9) Work hours. 10) Hazards and risks. 11) Progress cleaning. 12) Quality and work standards. 13) Change Orders. 14) Documentation of information for payment requests. 3. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report. PROJECT MANAGEMENT AND COORDINATION 01310-2 HIGH POINT ABC a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made ot recognized. Issue revised schedule concurrently with the report of each meeting. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01310 PROJECT MANAGEMENT AND COORDINATION 01310-3 HIGH POINT ABC SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1-GENERAL La A 12 13 SUMMARY This Seotion includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following: Contractor's Construction Schedule. Submittals Schedule Weekly construction reports. Field condition reports. BeRe See Division 1 Section "Payment Procedures" for submitting the Schedule of Values, DEFINITIONS Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float. Float: The measure of leeway in starting and completing an activity. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for areater detail ‘Major Area: A significant construction element. SUBMITTALS Submittals Schedule: Submit three copies of schedule. Arrange the following information in a tabular format: 1, Scheduled date for first submittal. 2. Specification Section number and title 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. 6. Scheduled date for Architect's final release or approval. Contractor's Construction Schedule: Submit two printed copies of initial schedule, one a reproducible print and one a blue- or black-line print, large enough to show entire schedule for entire construction period, Weekly Construction Reports: Submit two copies at weekly intervals. Field Condi mn Reports: Submit two copies at time of discovery of differing conditions. CONSTRUCTION PROGRESS DOCUMENTATION 01320-1 HIGH POINT ABC 14 COORDINATION A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors. B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports. L 2. Secure time commitments for performing critical elements of the Work from parties involved, Coordinate cach construction activity in the network with other activities and schedule them in proper sequence. PART 2- PRODUCTS 2.1 SUBMITTALS SCHEDULE ‘A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, ‘manufacturing, fabrication, and delivery when establishing dates, 1 2 Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule. Submit concurrently with the first complete submittal of Contractor's Construction Schedule. 2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL, Time Frame: Extend schedule from date established for commencement of the Work to date of Substantial Completion. 1 Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order. Activities: Treat each separate area as a separate numbered activity for each principal element of the Work. Comply with the following: Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section “Submittal Procedures” in schedule, Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule. CONSTRUCTION PROGRESS DOCUMENTATION 01320-2 23 24 T ABC 4, Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion, Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule. CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART) Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 15 days of date established for the Notice of Award. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line 1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar. REPORTS. ‘Weekly Construction Reports: Prepare a weekly construction report recording events at Project site, including the following: List of subcontractors. Daily weather conditions. ‘Accidents, Stoppages, delays, shortages, and losses. ‘Meter readings and similar recordings. Orders and requests of authorities having jurisdiction. Services connected and disconnected. Equipment or system tests and startups. Senay hee Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a request for information on CSI Form 13.2A. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents PART 3 - EXECUTION Ba CONTRACTOR'S CONSTRUCTION SCHEDULE, CONSTRUCTION PROGRESS DOCUMENTATION 01320-3 HIGH POINT ABC ‘A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule 2 days before each regularly scheduled progress meeting. 1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting. 2, Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations. 3. As the Work progresses, indicate Actual Completion percentage for each activity. B. Distribution: Distribute copies of approved schedule to Architect, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. 1. Post copies in Project meeting rooms and temporary field offices. 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities. END OF SECTION 01320 CONSTRUCTION PROGRESS DOCUMENTATION 01320-4 HIGH POINT ABC SECTION 01330 - SUBMITTAL PROCEDURES, PART | - GENERAL Ll 12 13 SUMMARY This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Division 1 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule and the Submittals Schedule, See Division 1 Section "Quality Requirements" for submitting test and inspection reports and Delegated-Design Submittals and for erecting mockups. See Division 1 Section "Closeout Procedures" for submitting warranties Project Record Documents and operation and maintenance manuals, DEFINITIONS Action Submittals: Written and graphic information that requires Architect's responsive action. Informational Submittals: Written information that does not require Architect's approval. Submittals may be rejected for not complying with requirements, SUBMITTAL PROCEDURES Coordination: Coordinate preparation and processing of submittals with performance of construction activities. 1, Coordinate each submittal with fabrication, purchasing, testing, delivery, other submnittals, and related activities that require sequential activity. 2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination, a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. Submittals Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. SUBMITTAL PROCEDURES 01330-1 HIGH POINT ABC 1, Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. Architect will advise Contractor when a submittal being processed must be delayed for coordination. 2. intermediate submittal is necessary, process it in same manner as initial submittal. 3. Allow 15 days for processing each resubmittal. 4, No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, D. Identification: Place a permanent label or title block on each submittal for identification. 1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 4 by 5 inches on label or beside title block to record Contractor's review and approval markings and action taken by Architect. 3. Include the following information on label for processing and recording action taken: Project name. Date, ‘Name and address of Architect. ‘Name and address of Contractor. ‘Name and address of subcontractor. ‘Name and address of supplier. ‘Name of manufacturer. Unique identifier, including revision number. Number and title of appropriate Specification Section. Drawing number and detail references, as appropriate. ‘Other necessary identification. RvrEe peas se E, Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals. Additional Copies: Unless additional copies are required for final submittal, and unless “Architect observes noncompliance with provisions of the Contract Documents, initial submittal ‘may serve as final submittal. 1, Additional copies submitted for maintenance manuals will not be marked with action taken and will be returned. ‘Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmitial form. Architect will discard submittals received from sources other than Contractor. 1, Include Contractor's certification stating that information submitted complies with requirements of the Contract Documents. 2. Transmittal Form: Use AIA Document G810, H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. SUBMITTAL PROCEDURES 01330 -2 HIGH POINT ABC L ‘Use for Construction: Use only final submittals with mark indicating action taken by Architect in connection with construction. PART 2-PRODUCTS 21 A cl ACTION SUBMITTALS General: Prepare and submit Action Submittals required by individual Specification Sections. ih ‘Number of Copies: Submit four copies of each submittal, unless otherwise indicated. Architect will return two copies. Mark up and retain one returned copy as a Project, Record Document, Product Data: Collect information into 2 single submittal for each element of construction and type of product or equipment. 1. 2. 3. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data. Mark each copy of each submittal to show which products and options are applicable. Include the following information, as applicable: Manufacturer's written recommendations Manufacturer's product specifications. Manufacturer's installation instructions. Manufacturer's catalog cuts. Wiring diagrams showing factory-installed wiring. Printed performance curves. Operational range diagrams. Compliance with recognized trade association standards, Compliance with recognized testing agency standards Pre me pe oe Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, 1 Preparation: Include the following information, as applicable: Dimensions. Identification of products. Fabrication and installation drawings. Roughing-in and setting diagrams. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring, ‘Shopwork manufacturing instructions. ‘Templates and patterns. Schedules. Notation of coordination requirements, j. Notation of dimensions established by field measurement. paoge PEE SUBMITTAL PROCEDURES 0130-3 HIGH POINT ABC 2, Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring, 3. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 24 by 36 inches. D, Coordination Drawings: Comply with requirements in Division 1 Section "Project Management and Coordination." E, Samples: Prepare physical units of materials or products, including the following: 1, Comply with requirements in Division 1 Section "Quality Requirements" for mockups. 2, Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available, a, Submit 3 full scts of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will retum submittal with options selected. 3. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from the same material to be used for the Work, cured and finished in manner specified, and physically identical with the product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection. a. Submit three sets of Samples, Architect will retain two Sample sets; remainder will be retumed. 4, Preparation: Mount, display, or package Samples in manner specified to facilitate review of qualities indicated. 3. Submit Samples for review of kind, color, pattern, and texture for a final check of these characteristics with other elements and for a comparison of these characteristics between final submittal and actual component as delivered and installed. 6. Disposition: Maintain sets of approved Samples at Project site, available for quality- control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. F. Product Schedule or List: Prepare a written summary indicating types of products required for the Work and their intended location. G, Delegated-Design Submittal: Comply with requirements in Division 1 Section "Quality Requirements." Submittals Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation." 1. Application for Payment: Comply with requirements in Division 1 Section "Payment Procedures." J. Schedule of Values: Comply with requirements in Division 1 Section "Payment Procedures." SUBMITTAL PROCEDURES 0130-4 HIGH POINT ABC K, 22 Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. INFORMATIONAL SUBMITTALS General: Prepare and submit Informational Submittals required by other Specification Sections. 1, Number of Copies: Submit two copies of each submittal, unless otherwise indicated. Architect will not return copies. 2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. 3. Test and Inspection Reports: Comply with requirements in Division 1 Section "Quality Requirements." Contracto’s Construction Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation.” Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements, Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified, Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements and, where required, is authorized for this specific Project. ‘Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements. Include evidence of manufacturing experience where required. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements, Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion. SUBMITTAL PROCEDURES 0130-5 HIGH POINT ABC K. L M. N. oO. R. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product ot after product is installed in its final location, for compliance with requirements, Product Test Reports: Prepare written reports indicating current product produced by ‘manufacturer complies with requirements, Base reports on evaluation of tests performed by ‘manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency, Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect. for Project. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements in Division 1 Section "Closeout Procedures.” Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations Include list of assumptions and other performance and design criteria and a summary of loads Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers. Manufacturer's Instructions: Prepare written or published information that documents ‘manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of ‘manufacturer. ‘Manufacturer's Field Reports: Prepare written information documenting factory-authotized service representative's tests and inspections. Insurance Certificates and Bonds: Prepare written information indicating current status of insurance or bonding coverage, Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage. Construction Photographs: Comply with requirements in Division 1 Section "Construction Progress Documentation." PART 3 - EXECUTION Ba A B, CONTRACTOR'S REVIEW Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect. Approval Stamp: Stamp each submittal with a uniform, approval stamp, Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date SUBMITTAL PROCEDURES 01330-6 HIGH POINT ABC of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents, 3.2 ARCHITECT'S ACTION ‘A. General: Architect will not review submittals that do not bear Contractor's approval stamp and will return them without action, B. Action Submittals: Architect will review each submittal, make marks to indicate corrections or ‘modifications required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken C. Informational Submittals: Architect will review each submittal and will not retum it, or will reject and retum it if it does not comply with requirements. Architect will forward each submittal to appropriate party. D. Submittals not required by the Contract Documents will not be reviewed and may be discarded. END OF SECTION 01330 SUBMITTAL PROCEDURES 01330-7 HIGH POINT ABC SECTION 01400 - QUALITY REQUIREMENTS PART 1 -GENERAL, ii 12 13 A SUMMARY This Section includes administrative and procedural requirements for quality assurance and quality control. ‘Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. 1. Specified tests, inspections, and related actions do not limit Contractor's quality-control procedures that facilitate compliance with the Contract Document requirements. 2, Requirements for Contractor to provide quality-control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section. See Divisions 2 through 16 Sections for specific test and inspection requirements. DEFINITIONS Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements. Services do not include contract enforcement activities performed by Architect. Mockups: Full-size, physical example assemblies to illustrate finishes and materials. Mockups are used to verify selections made under Sample submittals, to demonstrate aesthetic effects and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples. Mockups establish the standard by which the Work will be judged. Testing Agency: An entity engaged to perform specific tests, inspections, ot both. Testing laboratory shall mean the same as testing agency. DELEGATED DESIGN Performance and Design Criteria; Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. 1. Ifcriteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect. QUALITY REQUIREMENTS 01400 - 1 HIGH POINT ABC 14 1s SUBMITTALS Qualification Data: For testing agencies specified in “Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated, Include list of codes, loads, and other factors used in performing these services, Reports: Prepare and submit certified written reports that include the following: Date of issue. Project ttle and number. Name, address, and telephone number of testing agency. Dates and locations of samples and tests or inspections. ‘Names of individuals making tests and inspections. Description of the Work and test and inspection method. Identification of product and Specification Section. ‘Complete test or inspection data. ‘Test and inspection results and an interpretation of test results. 10. Ambient conditions at time of sample taking and testing and inspecting. 1, Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements. 12, Name and signature of laboratory inspector. 13, Recommendations on retesting and reinspecting. BeRe Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work. QUALITY ASSURANCE Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of ‘manufacturer's products that are similar in material, design, and extent to those indicated for this Project. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance. QUALITY REQUIREMENTS 01400-2 HIGH POINT ABC D. 16 Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated. 1, Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using ‘materials indicated for the completed Work: 1, Build mockups in location and of size indicated or, if not indicated, as directed by Architect 3. Demonstrate the proposed range of aesthetic effects and workmanship. 4, Obtain Architect's approval of mockups before starting work, fabrication, or construction. 5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work. 6. Demolish and remove mockups when directed, unless otherwise indicated, QUALITY CONTROL Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services. 1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of the types of testing and inspecting they are engaged to perform, 2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted by Change Order. Contractor Responsibilities: Unless otherwise indicated, provide quality-control services specified and required by authorities having jurisdiction. QUALITY REQUIREMENTS 01400 - 3, HIGH POINT ABC 1 Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services. Contractor shall not employ the same entity engaged by Owner, unless agreed to in writing by Owner. 2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed. 3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service. 4, Testing and inspecting requested by Contractor and not required by the Contract ‘Documents are Contractor's responsibility. 5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct. C. Special Tests and Inspections: Owner will engage a testing agency to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner. 1, Testing agency will notify Architect and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services. 2, Testing agency will submit a certified written report of each test, inspection, and similar quality-control service to Architect with copy to Contractor and to authorities having jurisdiction, 3, Testing agency will submit a final report of special tests and inspections at Substantial Completion, which inctudes a list of unresolved deficiencies. 4, Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents. 5. Testing agency will retest and reinspect corrected work. D. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components’ and equipment installation, including service connections. Report results in writing. E, _ Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that revised or replaced Work that failed to comply with requirements established by the Contract Documents. F, Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties, Provide qualified personnel to perform required tests and inspections. 1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services. 2, Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements. 3, Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor. 4, Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work. 5. Donot perform any duties of Contractor. QUALITY REQUIREMENTS 0140-4 HIGH POINT ABC G. H, Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel, Provide the following: 1. Access to the Work. 2, Incidental labor and facilities necessary to facilitate tests and inspections. 3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples. 4, Facilities for storage and field-curing of test samples. 5. Delivery of samples to testing agencies, 6. Preliminary design mix proposed for use for material mixes that require control by testing agency. 7. Security and protection for samples and for testing and inspecting equipment at Project site. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting, 1. Schedule times for tests, inspections, obtaining samples, and similar PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 A B. c REPAIR AND PROTECTION General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes. 1. Provide materials and comply with installation requirements specified in other Sections of these Specifications. Restore patched areas and extend restoration into adjoining areas in a manner that eliminates evidence of patching. 2. Comply with the Contract Document requirements for Division 1 Section "Cutting and Patching." Protect construction exposed by or for quality-control service activities. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services. END OF SECTION 01400 QUALITY REQUIREMENTS 01400 - 5 HIGH POINT ABC SECTION 01420 - REFERENCES PART 1 -GENERAL, Ll DEFINITIONS General: Basic Contract definitions are included in the Conditions of the Contract, "Approved"; When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract. "Directed": A command or instruction by Architect. Other terms including "requested," “authorized,” "selected," "approved," "required," and "permitted" have the same meaning as “directed.” "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," “noted,” "scheduled," and "specified" have the same meaning as "indicated." "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations. "Provide": Furnish and install, complete and ready for the intended use. "Installer": Contractor or another entity engaged by Contractor as an employee, Subcontractor, ‘or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations. 1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generie name. "Experienced": When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction. REFERENCES 01420-1 HIGH POINT ABC 12 K, "Project Site": Space available for performing construction activities. ‘The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built. INDUSTRY STANDARDS Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if ‘bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference, Publication Dates: Comply with standards in effect as of date of the Contract Documents, unless otherwise indicated. Conflicting Requirements: If compliance with two or more standards is specified and the standards establish different ot conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Architect for a decision before proceeding. 1. Minimum Quantity or Quality Levels: ‘The quantity or quality level shown or specified shall be the minimum provided or performed. ‘The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum ot maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding, Copies of Standards: Each entity engaged in construction on Project must be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. 1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source and make them available on request. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list. ADAAG Americans with Disabilities Act (ADA) CER cRD pop Code of Federal Regulations ‘Handbook for Concrete and Cement Department of Defense Specifications and Standards FED-STD Federal Standard (See FS) FS Federal Specification FIMS Federal Test Method Standard (See FS) REFERENCES, 01420 -2 HIGH POINT ABC MILSPEC ‘UFAS Military Specification and Standards Uniform Federal Accessibility Standards 13. ABBREVIATIONS AND ACRONYMS A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Gale Research's "Encyclopedia of Associations" or in Columbia Books’ "National Trade & Professional Associations of the U.S." B, Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. AAADM AABC AAMA AAN AASHTO. AATCC. ABMA ACI ACPA, ABIC AEPA AF&PA AGA AGC AHAM REFERENCES Aluminum Association, Inc. (The) American Association of Automatic Door Manufacturers Associated Air Balance Council American Architectural Manufacturers Association American Association of Nurserymen (See ANLA) American Association of State Highway and Transportation Officials American Association of Textile Chemists and Cotorists (The) American Bearing Manufacturers Association American Concrete Institute/ACI International American Conerete Pipe Association Association of Edison Illuminating Companies, Inc. (The) American Forest & Paper Association (See AF&PA) American Forest & Paper Association American Gas Association Associated General Contractors of America (The) American Hardboard Association Association of Home Appliance Manufacturers 01420- 3, HIGH POINT ABC AL ANSI AOSA ASCA, ASCE ASHRAE ASME ASSE ASTM AWCI AWCMA AWI ‘REFERENCES Asphalt Institute American Institute of Architects (The) American Institute of Steel Construction ‘American Iron and Stee! Institute ‘American Institute of Timber Construction Associated Landscape Contractors of America American Lumber Standard Committee Air Movement and Control Association Intemational, Inc. American Nursery & Landscape Association (Formerly: AAN - American Association of Nurserymen) American National Standards Institute Association of Official Seed Analysts APA - The Engineered Wood Association Architectural Precast Association American Petroleum Institute Ait-Conditioning & Refrigeration Institute Architectural Spray Coaters Association American Society of Civil Engineers American Society of Heating, Refrigerating and Air-Conditioning Engineers ASME International (The American Society of Mechanical Engineers Intemational) American Society of Sanitary Engineering ASTM Intemational (American Society for Testing and Materials Intemational) AWC International (Association of the Wall and Ceiling Industries International) American Window Covering Manufacturers Association (See WCMA) Architectural Woodwork Institute 01420-4 HIGH POINT ABC AWPA AWS AWWA, BHMA BIA BIFMA cece CESS CEA, CREA, CGA CGSB CIMA CISCA CISPI CLEMI PPA, csr cssB cm REFERENCES American Wood-Preservers' Association American Welding Society American Water Works Association Builders Hardware Manufacturers Association Brick Industry Association (The) BIFMA Intemational (Business and Institutional Furniture Manufacturer's Association International) Carpet Cushion Council Center for Cold-Formed Steel Structures Copper Development Association Inc. Canadian Electricity Association Chemical Fabrics & Film Association, Inc. Compressed Gas Association Canadian General Standards Board Cellulose Insulation Manufacturers Association Ceilings & Interior Systems Construction Association Cast Iron Soil Pipe Institute Chain Link Fence Manufacturers Institute Corrugated Polyethylene Pipe Association Carpet & Rug Institute (The) Concrete Reinforcing Steet Institute CSA International (Formerly: IAS - International Approval Services) Construction Specifications Institute (The) Cedar Shake & Shingle Bureau Cooling Technology Institute (Formerly: Cooling Tower Institute) 01420 -5 HIGH POINT ABC DEI EIA EIMA EJMA FCI FGMA FM EMG FSC GA GANA GRI GTA HL HL HMMA HPVA ICEA ICRI IEC IEEE IESNA REFERENCES Door and Hardware Institute Electronic Industries Alliance EIFS Industry Members Association Expansion Joint Manufacturers Association, Tne. Fluid Controls Institute Flat Glass Marketing Association (See GANA) Factory Mutual System (See FMG) FM Global (Formerly: FM - Factory Mutual System) Forest Stewardship Council Gypsum Association Glass Association of North America (Formerly: FGMA - Flat Glass Marketing Association) Geosynthetic Research Institute Glass Tempering Division of Glass Association of North America (See GANA) Hydraulic Institute Hydronics Institute Hollow Metal Manufacturers Association (See NAAMM) Hardwood Plywood & Veneer Association HP. White Laboratory, Inc. Intemational Approval Services (See CSA) Insulated Cable Engineers Association, Inc. International Concrete Repair Institute, Inc. Intemational Electrotechnical Commission Institute of Electrical and Electronics Engineers, Inc. (The) Illuminating Engineering Society of North America 01420-6 HIGH POINT ABC icc IGMA ISSFA, BA Irs Iws KCMA LMA LPL SGA MBMA, MFMA. MFMA. MBIA MIA MLISFA MSS NAAMM NAAMM NACE NAIMA REFERENCES Insulating Glass Certification Council Insulating Glass Manufacturers Alliance (The) Indiana Limestone Institute of America, Inc, International Solid Surface Fabricators Association International Imaging Industry Association (Formerly; PIMA - Photographic & Imaging Manufacturers Association) Intertek Testing Services Insect Screening Weavers Association (Now defunct) Kitchen Cabinet Manufacturers Association Laminating Materials Association (Formerly: ALA - American Laminators Association) Lightning Protection Institute Laminated Safety Glass Association (See GANA) Metal Building Manufacturers Association Maple Flooring Manufacturers Association ‘Metal Framing Manufacturers Association Material Handling Industry of America Marble Institute of America Metal Lath/Steel Framing Association (See SMA) ‘Master Painters Institute ‘Manufacturers Standardization Society of The Valve and Fittings Industry Inc, ‘National Association of Architectural Metal Manufacturers ‘North American Association of Mirror Manufacturers (See GANA) ‘NACE Intemational (National Association of Corrosion Engineers International) ‘North American Insulation Manufacturers Association (The) 01420-7 HIGH POINT ABC NAMI NBGQA NCMA NCPI NCTA NEBB NECA NeLMA, ‘NEMA NETA NFPA NERC NGA NHLA NLGA NOFMA NRCA NRMCA NSA NSF NSSGA NIMA NWWDA PCL PDCA REFERENCES ‘National Accreditation and Management Institute, Inc. National Building Granite Quarries Association, Inc. ‘National Concrete Masonry Association National Clay Pipe Institute National Cable & Telecommunications Association National Environmental Balancing Bureau ‘National Electrical Contractors Association Northeastern Lumber Manufacturers’ Association National Electrical Manufacturers Association InterNational Electrical Testing Association National Fire Protection Association National Fenestration Rating Couneil National Glass Association National Hardwood Lumber Association ‘National Lumber Grades Authority National Oak Flooring Manufacturers Association ‘National Roofing Contractors Association National Ready Mixed Concrete Association National Stone Association (See NSSGA) NSF International (National Sanitation Foundation Intemational) ‘National Stone, Sand & Gravel Association (Formerly: NSA - National Stone Association) ‘National Terrazzo and Mosaic Association, Inc. National Wood Window and Door Association (See WDMA) PrecastPrestressed Concrete Institute Painting and Decorating Contractors of America 1420-8 HIGH POINT ABC PDI PGI RCSC RFCI RIS, SAE SDI SDI SEFA sGoc SIGMA, sit SMA SMACNA, SPFA SPIB ‘SPV/SPFD SPRI SSINA SSMA SSPC stl SWI REFERENCES Plumbing & Drainage Institute Pvc jeomembrane Institute Research Council on Structural Connections Resilient Floor Covering Institute Redwood Inspection Service SAE International Steel Deck Institute Steel Door Institute Scientific Equipment and Furniture Association Safety Glazing Certification Council Sealed Insulating Glass Manufacturers Association (See IGMA) Steel Joist Institute Screen Manufacturers Association Sheet Metal and Air Conditioning Contractors! National Association Spray Polyurethane Foam Alliance (Formerly: SPI/SPED - The Society of the Plastics Industry, Inc. Spray Polyurethane Foam Division) Southern Pine Inspection Bureau (The) Society of the Plastics Industry (The) Spray Polyurethane Foam Division (See SPEA) SPRI (Single Ply Roofing Institute) Specialty Steel Industry of North America Steel Stud Manufacturers Association (Formerly: ML/SFA - Metal Lath/Steel Framing Association) SSPC: The Society for Protective Coatings Steel Tank Institute Steel Window Institute 01420-9 HIGH POINT ABC SWRI Sealant, Waterproofing, and Restoration Institute TCA Tile Council of America, Inc, TIAEIA _Telecommunications Industry Association/Blectronic Industries Alliance TPL Truss Plate Institute TPL ‘Turfgrass Producers International UL Underwriters Laboratories Inc. UNI Uni-Bell PVC Pipe Association USITT —_United States Institute for Theatre Technology, Inc, WASTEC Waste Equipment Technology Association WCLIB West Coast Lumber Inspection Bureau WCMA Window Covering Manufacturers Association (See WCSC) wesc Window Covering Safety Council (Formerly: WCMA - Window Covering Manufacturers Association) WDMA —_ Window & Door Manufacturers Association (Formerly: NWWDA - National Wood Window and Door Association) wic Woodwork Institute of California WMMPA — Wood Moulding & Millwork Producers Association WWPA Western Wood Products Association C. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. BOCA BOCA International, Inc. CABO Council of American Building Officials (See ICC) TAPMO —_International Association of Plumbing and Mechanical Officials (The) ICBO International Conference of Buildirig Officials icc International Code Council, Ine. (Formerly: CABO - Council of American Building Officials) SBCCI Southern Building Code Congress International, Ine. REFERENCES 01420 - 10 HIGH POINT ABC D. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. cE Army Corps of Engineers psc ‘Consumer Product Safety Commission Doc Department of Commerce EPA Environmental Protection Agency FAA Federal Aviation Administration FDA Food and Drug Administration GsA General Services Administration HUD Department of Housing and Urban Development LBL Lawrence Berkeley Laboratory (See LBNL) LBNL Lawrence Berkeley National Laboratory NCHRP —_ National Cooperative Highway Research Program (See TRB) NIST National Institute of Standards and Technology OSHA Occupational Safety & Health Administration PBS Public Building Service (See GSA) RUS Rural Utilities Service (See USDA) TRB Transportation Research Board USDA Department of Agriculture USPS Postal Service E, State Govemment Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list NCDOIL —_North Carolina Department of Insurance REFERENCES, 01420- 11 HIGH POINT ABC PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01420 REFERENCES 01420 - 12 HIGH POINT ABC SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS PART 1 -GENERAL. Ll 13 14 15 16 A SUMMARY This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, and security and protection facilities. See Division 1 Section "Execution Requirements" for progress cleaning requirements. DEFINITIONS Permanent Enclosure: As determined by Architect, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures. USE CHARGES General: Cost or use charges for temporary facilities are not chargeable to Owner or Architect and shall be included in the Contract Sum, SUBMITTALS ‘Temporary Utility Reports: Submit reports of tests, inspections, meter readings, and similar procedures performed on temporary utilities. QUALITY ASSURANCE Standards: Comply with ANSIA10.6, NECA's "Temporary Electrical Facilities," and ‘NEPA 241. 1, Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits. PROJECT CONDITIONS ‘Temporary Utilities: At earliest feasible time, when acceplable to Owner, change over from use of temporary service to use of permanent service. ‘TEMPORARY FACILITIES AND CONTROLS 0150-1 HIGH POINT ABC 1, Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities. Conditions of Use: The following conditions apply to use of temporary services and facilities by all parties engaged in the Work: 1. Keep temporary services and facilities clean and neat. 2. Relocate temporary services and facilities as required by progress of the Work. PART 2- PRODUCTS 24 22 2 MATERIALS General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if approved by Architect, Provide materials suitable for use intended, Pavement: Comply with Division 2 Section 02511 “Hot-Mix Asphalt Paving and Section 02751 “Cement Conerete Pavement.” Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD comer and pull posts, with 1-5/8-inch- OD top rails. Portable Chain-Link Fencing: Minimum 2-inch 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; mininmum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails Provide galvanized steel bases for supporting posts. Wood Enclosure Fence: Plywood, 6 feet high, framed with four 2-by-4-inch rails, with preservative-treated wood posts spaced not more than 8 feet apart, Lumber and Plywood: Comply with requirements in Division 6 Section Miscellaneous Carpentry." Gypsum Board: ASTM C36, minimum 1/2 inch thick by 48 inches wide by maximum available lengths; regular-type panels with tapered edges. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or tock wool; with maximum flame-spread and smoke-developed indices of 25 and 50, respectively. ‘Tarpaulins: Fire-resistive labeled with flame-spread rating of 15 or less. ‘Water: Potable, EQUIPMENT TEMPORARY FACILITIES AND CONTROLS, 0150-2 HIGH POINT ABC A Field Offices: Mobile units with lockable entrances, operable windows, and serviceable finishes; heated and air conditioned; on foundations adequate for normal loading. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent as indicated or a combination of extinguishers of NFPA-recommended classes for exposures. 1. Comply with NEPA 10 and NEPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure. Self-Contained Toilet Units: Single-occupant units of chemical, aerated recirculation, or combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material, Drinking-Water Fixtures: Containerized, tap-dispenser, bottied-water, including paper cup supply. 1. Where power is accessible, provide electric water coolers to maintain dispensed water temperature at 45 to 55 deg F. Heating Equipment: Unless Owner authorizes use of permanent heating system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control, 1, Use of kerosene or gasoline-buming space heaters, open-flame heaters, or salamander- type heating units is prohibited, 2, Heating Units: Listed and labeled, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use for type of fuel being consumed, Electrical Outlets: Properly configured, NEMA-polarized outlets to prevent insertion of 110- to 120-V plugs into higher-voltage outlets; equipped with ground-fault circuit interrupters, reset button, and pilot light. Power Distribution System Circuits: Where permitted and overhead and exposed for surveillance, wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits may be nonmetallic sheathed cable. PART 3 - EXECUTION 34 A 32 INSTALLATION, GENERAL Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required, Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities. ‘TEMPORARY UTILITY INSTALLATION ‘TEMPORARY FACILITIES AND CONTROLS. 0150-3 ‘HIGH POINT ABC A General: Engage appropriate local utility company to install temporary service or connect to existing service. Where utility company provides only part of the service, provide the remainder with matching, compatible materials and equipment. Comply with utility company recommendations. 1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. 2. Provide adequate capacity at each stage of construction. Before temporary utility is available, provide trucked-in services. 3. Obtain easements to bring temporary utilities to Project site where Owner's easements cannot be used for that purpose. Sewers and Drainage: If sewers are available, provide temporary connections to remove effluent that can be discharged lawfully. If sewers are not available or cannot be used, provide Grainage ditches, dry wells, stabilization ponds, and similar facilites. If neither sewers nor rainage facilities can be lawfully used for discharge of effluent, provide containers to remove and dispose of effluent off-site in a lawful manner. 1. Filter out excessive soil, construction debris, chemicals, oils, and similar contaminants that might clog sewers or pollute waterways before discharge. 2. Connect temporary sewers to municipal system as directed by sewer department officials 3, Maintain temporary sewers and drainage facilities in a clean, sanitary condition. After heavy use, restore normal conditions promptly. 4, Provide temporary filter beds, settlement tanks, separators, and similar devices to purify effluent to levels acceptable to authorities having jurisdiction. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction until permanent water service is in use. Sterilize temporary water piping before Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fixtures. Comply with regulations and health codes for type, number, location, operation, and maintenance of fixtures and facilities. 1. Disposable Supplies: Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Maintain adequate supply. Provide covered waste containers for disposal of used material 2. Toilets: Install self-contained toilet units. Shield toilets to ensure privacy. 3. Wash Facilities: Install wash facilities supplied with potable water at convenient locations for personnel who handle materials that require wash up. Dispose of drainage properly. Supply cleaning compounds appropriate for each type of material handled, 4, Drinking-Water Facilities: Provide bottled-water, drinking-water units or where power is accessible; provide electric water coolers to maintain dispensed water temperature at 45, 10 55 deg F. (7.2 to 12.7 deg C). Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment from that specified that will not have a harmful effect on completed installations or elements being installed. ‘TEMPORARY FACILITIES AND CONTROLS 01500 -4 HIGH POINT ABC 1, Maintain a minimum temperature of $0 deg F in permanently enclosed portions of building for normal construction activities, and 65 deg F for finishing activities and areas, where finished Work has been installed. F, Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment from that specified that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption. G. Electric Power Service: Provide weatherproof, grounded electric power service and distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload-protected disconnecting means, automatic ground-fault interrupters, and main distribution switchgear. 1, Install power distribution wiring overhead and rise vertically where least exposed to damage. H, Electric Distribution: Provide receptacle outlets adequate for connection of power tools and equipment. 1. Provide waterproof connectors to connect separate lengths of electrical power cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio. 1. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations and traffic conditions 1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system. 2. Provide one 100-W incandescent lamp per 500 sq. ft, uniformly distributed, for general lighting, or equivalent illumination. 3. Provide one 100-W incandescent lamp every 50 feet in traffic areas. 4, Install exterior-yard site lighting that will provide adequate illumination for construction operations, traffic conditions, and signage visibility when the Work is being performed, J. Telephone Service: Provide temporary telephone service throughout construction period for field office and first-aid station. 1, Provide additional telephone lines for the following: a, Provide a dedicated telephone line for each facsimile machine and computer with modem in each field office. 2, At each telephone, post a list of important telephone numbers, including potice and fire departments ambulance service Contractor's home office Architect's office Engineers’ offices Owner's office and principal subcontractors’ field and home offices. 3. Provide voice-mail service on superintendents telephone. 4, Provide a portable cellular telephone for superintendent's use in making and receiving telephone calls when away from field office. TEMPORARY FACILITIES AND CONTROLS 0150-5 HIGH POINT ABC 33 A. SUPPORT FACILITIES INSTALLATION General: Comply with the following: 1. Locate field office, storage sheds, sanitary facilities, and other temporary construction and support facilities for easy access, 2. Provide incombustible construction for offices, shops, and sheds located within construction area or within 30 feet of building lines. Comply with NFPA 241 3. Maintain support facilities until near Substantial Completion. Remove before Substantial ‘Completion, Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner. ‘Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate to support loads and to withstand exposure to traffic during construction period. Locate temporary roads and paved areas in same location as permanent roads and paved areas. Extend temporary roads and paved areas, within construction limits indicated, as necessary for construction operations 1. Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas. 2. Prepare subgrade and install subbase and base for temporary roads and paved areas according to Division 2 Section "Earthwork." 3. Recondition base after temporary use, including removing contaminated material, regrading, prooffolling, compacting, and testing, 4, Delay installation of final course of permanent hot-mix asphalt pavement until immediately before Substantial Completion. Repair hot-mix asphalt base-course pavement before installation of final course according to Division 2 Section "Hot-Mix Asphalt Paving ." Dewatering Facilities and Drains: Comply with requirements in applicable Division 2 Sections for temporary drainage and dewatering facilities and operations not directly associated with construction activities included in individual Sections. Where feasible, use same facilities. Maintain Project site, excavations, and construction free of water. Project Identification and Temporary Signs: Prepare Project identification sign in sizes indicated. Install sign where indicated to inform public and persons seeking entrance to Project. Do not permit installation of unauthorized sign. 1, Engage an experienced sign painter to apply graphics for Project identification sign. Comply with details indicated. 2. Prepare temporary signs to provide directional information to construction personnel. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste ftom construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Comply with Division I Section "Execution Requirements " for progress cleaning requirements. 1, If required by authorities having jurisdiction, provide separate containers, clearly labeled, for each type of waste material to be deposited. ‘TEMPORARY FACILITIES AND CONTROLS 0150-6 HIGH POINT ABC 34 Field Office: Provide an insulated, weathertight, heated and air-conditioned field office for use by superintendent; of sufficient size to accommodate required office personnel and meetings of 10 persons at Project site. Keep office clean and orderly. SECURITY AND PROTECTION FACILITIES INSTALLATION Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects, Avoid using tools and equipment that produce harmful noise, Restrict use of noisemaking tools and equipment to hours that will minimize complaints from persons or firms near Project site. Stormwater Control: Provide earthen embankments and similar barriers in and around ‘excavations and subgrade construction, sufficient to prevent flooding by runoff of stormwater from heavy rains. Pest Control: Before deep foundation work has been completed, retain a local exterminator or pest-control company to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests. Engage this pest-control service to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Obtain extended warranty for Owner. Perform control operations lawfully, using environmentally safe materials. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning, signs to inform personnel and public of possible hazard, Where appropriate and needed, provide lighting, including flashing red or amber lights. ‘Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities, Provide temporary weathertight enclosure for building exterior. 1, Where heating or cooling is needed and permanent enclosure is not complete, provide insulated temporary enclosures. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects. 2. Vertical Openings: Close openings of 25 sq. ft. or less with plywood or similar materials 3. Horizontal Openings: Close openings in floor or roof decks and horizontal surfaces with load-bearing, wood-framed construction. 4, Install tarpaulins securely using fire-retardant-treated wood framing and other materials. ‘Temporary Fire Protection: Until fire-protection needs are supplied by permanent facilites, install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241 TEMPORARY FACILITIES AND CONTROLS 01500 -7 HIGH POINT ABC 35 1. Provide fire extinguishers, installed on walls on mounting brackets, visible and accessible from space being served, with sign mounted above. a. Locate fire extinguishers where convenient and effective for their intended purpose; provide not tess than one extinguisher on each floor at or near each usable stairwell. Store combustible materials in containers in fire-safe locations. 3. Maintain unobstructed access to fire extinguishers, fire hydrants, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas 4, Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition. 5. Develop and supervise an overall fire-prevention and first-aid fire-protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures, Post wamings and information. OPERATION, TERMINATION, AND REMOVAL Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage caused by freezing temperatures and similar elements. 1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage. 2, Prevent water-filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations. ‘Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of @ permanent facility, or no later than ‘Substantial Completion, Complete permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired. 1. Materials and facilities that constitute temporary facilities are the property of Contractor. ‘Owner reserves right to take possession of Project identification signs 2, At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements in Division 1 Section "Closeout Procedures." END OF SECTION 01500 ‘TEMPORARY FACILITIES AND CONTROLS 01500-8 HIGH POINT ABC ‘TEMPORARY FACILITIES AND CONTROLS, 01500-9 HIGH POINT ABC TYPICAL FONT STYLE “AVANT GUARDE" : a aie CITY OF HIGH POINT. B45 Alcoholic Beverage : & Control Board__1_| # 5 | Ee s O3 lk yee t STORE NUMBER 7. I ma i L | _ % 5 g 4 WAmauen lt ygantercerss —] | WrfonsclomNe 27103 ‘ eee sia ale Bt gig ; a 3 8 |g i ele s : ii lye ~ AW ‘LIL 7 _ 1) 4 1 I ‘ “Saveerarne 4 OO 4nd TREATED ————————}— ferene zy TEMPORARY FACILITIES AND CONTROLS. 01500 - 10 HIGH POINT ABC SECTION 01600 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1d A 12 SUMMARY This Section includes administrative and procedural requirements for selecting products for use in Project; product delivery, storage, and handling; manufacturers’ standard warranties on products; special warranties; product substitutions; and comparable products. See Division 1 Section "Closeout Procedures" for submitting warranties for contract closeout. See Divisions 2 through 16 Sections for specific requirements for warranties on products and installations specified to be warranted. DEFINITIONS Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," “equipment,” "system," and terms of similar intent 1. Named Products: Items identified by manufacturer's product name, including make or ‘model number or other designation, shown or listed in manufacturer's published product, literature, that is current as of date of the Contract Documents. 2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products. 3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product. Substitutions: Changes in products, materials, equipment, and methods of construction ftom those required by the Contract Documents and proposed by Contractor. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design,” including make or model number or other designation, to establish the significant qualities related to type, fimction, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers, Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for 4 particular product and specifically endorsed by manufacturer to Owner. Special Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Owner. PRODUCT REQUIREMENTS 016001 HIGH POINT ABC 13 A SUBMITTALS Product List: Submit a list, in tabular from, showing specified products. Include generic names of products required. Include manufacturer's name and proprietary product names for each product. 1. Coordinate product list with Contractor's Construction Schedule and the Submittals Schedule. 2. Completed List: Within 60 days after date of commencement of the Work, submit 3 copies of completed product list. Include a written explanation for omissions of data and for variations from Contract requirements, 3. Architect's Action: Architect will respond in writing to Contractor within 15 days of receipt of completed product list. Architect's response will include a list of unacceptable product selections and a brief explanation of reasons for this action. Architect's response, or lack of response, does not constitute a waiver of requirement that products comply with the Contract Documents. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. ik 2. Substitution Request Form: Use CSI Form 13.1. Documentation: Show compliance with requirements for substitutions and the following, 1s applicable: a, Statement indicating why specified material or product cannot be provided. >. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution. ©. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated. 4. Product Data, including drawings and descriptions of products and fabrication and tallation procedures. Samples, where applicable or requested. ‘Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated. Research/evaluation reports evidencing compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction. hh, Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall e f Contract Time. i, Cost information, including a proposal of change, if any, in the Contract Sum, j. Contractor's certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated, k, Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated PRODUCT REQUIREMENTS 01600 -2 HIGH POINT ABC 1s 16 3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within one week of receipt of a request for substitution, Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later. a. Formof Acceptance: Change Order. b. Use product specified if Architect cannot make a decision on use of a proposed substitution within time allocated. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1 Section "Submittal Procedures." Show compliance with requirements. QUALITY ASSURANCE, Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options. PRODUCT DELIVERY, STORAGE, AND HANDLING Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft, Comply with manufacturer's written instructions. 1, Schedule delivery to minimize long-term storage at Project site and to prevent ‘overcrowding of construction spaces. 2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses. 3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. 4, Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected. Store materials in a manner that will not endanger Project structure, Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation. 7. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage. 8. Protect stored products from damage. PRODUCT WARRANTIES ‘Warranties specified in other Sections shall be in addition to, and run concurrent with, other ‘warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. PRODUCT REQUIREMENTS. 01600-3 HIGH POINT ABC B. Special Warranties: Prepare a written document that contains appropriate terms and ‘identification, ready for execution, Submit a draft for approval before final execution. 1 2. 3 Manufacturer's Standard Form: Modified to include Project-specific information and properly executed. Specified Form: Forms are included with the Specifications. Prepare a written document using appropriate form properly executed. Refer to Divisions 2 through 16 Sections for specific content requirements and particular requirements for submitting special warranties. C. Submittal Time: Comply with requirements in Division 1 Section "Closeout Procedures." PART 2 -PRODUCTS 2.1 PRODUCT OPTIONS General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, that are new at time of installation. 1 2, Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents. Where products are accompanied by the term “as selected," Architect will make selection, Where products are accompanied by the term "match sample," sample to be matched is Architect's. Descriptive, performance, and reference standard requirements in the Specifications establish "salient characteristics" of products, B. Product Selection Procedures: Procedures for product selection include the following: 1 Product: Where Specification paragraphs or subparagraphs titled "Product" name a single product and manufacturer, provide the product named. a. Substitutions may be considered, unless otherwise indicated. Manufacturet/Source: Where Specification paragraphs or subparagraphs titled "Manufacturer" or "Source" name single manufacturers or sources, provide a product by the manufacturer or from the source named that complies with requirements. a. Substitutions may be considered, unless otherwise indicated. Products: Where Specification paragraphs or subparagraphs titled "Products" introduce a list of names of both products and manufacturers, provide one of the products listed that complies with requirements. PRODUCT REQUIREMENTS 01600 -4 HIGH POINT ABC a, Substitutions may be considered, unless otherwise indicated. 4, Manufacturers: Where Specification paragraphs or subparagraphs titled "Manufacturers" introduce a list of manufacturers’ names, provide a product by one of the manufacturers listed that complies with requirements. a, Substitutions may be considered, unless otherwise indicated, 5. Available Products: Where Specification paragraphs or subparagraphs titled "Available Products" introduce a list of names of both products and manufacturers, provide one of the products listed or another product that complies with requirements. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product. 6. Available Manufacturers: Where Specification paragraphs or subparagraphs titled "Available Manufacturers” introduce a list of manufacturers’ names, provide a product by one of the manufacturers listed or another manufacturer that complies with requirements. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product. 7. Basis-of-Design Products: Where Specification paragraphs or subparagraphs titled "Basis-of-Design Product" are included and also introduce or refer to a list of manufacturers’ names, provide either the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product. a, Substitutions may be considered, unless otherwise indicated. 8. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, pattems, textures" or a similar phrase, select a product (and manufacturer) that complies with other specified requirements, a, Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Architect will select color, pattern, or texture from manufacturer's product line that does not include premium items, >. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Architect will select color, pattern, or texture from manufacturer's product line that includes both standard and premium items. 2.2 PRODUCT SUBSTITUTIONS A. Timing: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect. B. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: PRODUCT REQUIREMENTS. 01600 - 5 HIGH POINT ABC Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations. Requested substitution does not require extensive revisions to the Contract Documents, Requested substitution is consistent with the Contract Documents and will produce indicated results ‘Substitution request is fully documented and properly submitted. Requested substitution will not adversely affect Contractor's Construction Schedule, Requested substitution has received necessary approvals of authorities having jurisdiction. Requested substitution is compatible with other portions of the Work. Requested substitution has been coordinated with other portions of the Work. Requested substitution provides specified warranty. 2.3 COMPARABLE PRODUCTS A. Where products or manufacturers are specified by name, submit the following, in addition to other required submittals, to obtain approval of an unnamed product: 1 Evidence that the proposed product does not require extensive revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated. Evidence that proposed product provides specified warranty. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested. Samples, if requested. PART 3 - EXECUTION (Not Used) END OF SECTION 01600 PRODUCT REQUIREMENTS 0160-6 HIGH POINT ABC ‘SECTION 01700 - EXECUTION REQUIREMENTS PART | - GENERAL, Ll A 12 13 SUMMARY This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following: Construction layout. Field engineering and surveying. General installation of products Progress cleaning. Starting and adjusting. Protection of installed construction. Correction of the Work. Nava eEe See Division 1 Section "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, and final cleaning, SUBMITTALS Cortificates: Submit certificate signed by land surveyor certifying that location and elevation of improvements comply with requirements. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal. Certified Surveys: Submit two copies signed by land surveyor. Final Property Survey: Submit 10 copies showing the Work performed and record survey data. QUALITY ASSURANCE Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated, PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 31 EXAMINATION EXECUTION REQUIREMENTS 0170-1 HIGH POINT ABC A 32 Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work. 1, Before construction, verify the location and points of connection of utility services. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work. 1, Fumish location data for work related to Project that must be performed by public utilities serving Project site. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations, 1, Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers. 2, Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation. 3. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions. PREPARATION Existing Utility Information: Furnish information to local utility that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction, Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1, Donot proceed with utility interruptions without written permission. Field Measurements: Take field measurements as required to fit the Work properly. Recheck ‘measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to Architect. Include EXECUTION REQUIREMENTS 01700 -2 HIGH POINT ABC 33 34 1 detailed description of problem encountered, together with recommendations for changing the Contract Documents, CONSTRUCTION LAYOUT Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect promptly. General: Engage a land surveyor to lay out the Work using accepted surveying practices. 1, Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project. 2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions. Inform installers of lines and levels to which they must comply. Check the location, level and plumb, of every major element as the Work progresses. Notify Architect when deviations from required lines and levels exceed allowable tolerances. 6. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction. vay Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work, Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels, Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect. FIELD ENGINEERING Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark. 1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents, EXECUTION REQUIREMENTS 01700-3 HIGH POINT ABC 3.5 36 Certified Survey: On completion of foundation walls, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework. Final Property Survey: Prepare a final property survey showing significant features (ceal property) for Project. Include on the survey a certification, signed by land surveyor, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey. 1, Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey." INSTALLATION General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated. 1, Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated. Comply with manufacturer's written instructions and recommendations for installing produets in applications indicated. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work, 1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect. 2. Allow for building movement, including thermal expansion and contraction. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous. PROGRESS CLEANING General: Clean Project site and work areas daily, including common areas, Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully, EXECUTION REQUIREMENTS 0170-4 HIGH POINT ABC 37 38 1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris. 2. Do not hold materials more than 7 days during normal weather or 3 days if the ‘temperature is expected to rise above 80 deg F. 3. Containerize hazardous and unsanitary waste materials separately from other waste. ‘Mark containers appropriately and dispose of legally, according to regulations. Site: Maintain Project site free of waste materials and debris, Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work. 1, Remove liquid spills promptly. 2, Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate, Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning ‘materials that are not hazardous to health or property and that will not damage exposed surfaces. Concealed Spaces: Remove debris from concealed spaces before enclosing the space. Waste Disposal: Burying or buming waste materials on-site will not be permitted. Washing ‘waste materials down sewers or into waterways will not be permitted. During handling and installation, clean and protect construction in progress and adjoining ‘materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. STARTING AND ADJUSTING Start equipment and operating components to confirm proper operation. Remove ‘malfunctioning units, replace with new units, and retest. Adjust operating components for proper operation without binding. Adjust equipment for proper operation. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. PROTECTION OF INSTALLED CONSTRUCTION EXECUTION REQUIREMENTS 0170-5 HIGH POINT ABC 39 A Provide final protection and maintain conditions that ensure installed Work is without damage ‘or deterioration at time of Substantial Completion Comply with manufacturer's written instructions for temperature and relative humidity, CORRECTION OF THE WORK Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements in Division 1 Section "Cutting and Patching.” 1, Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Restore permanent facilities used during construction to their specified condition, Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired. Remove and replace chipped, scratched, and broken glass or reflective surfaces, END OF SECTION 01700 EXECUTION REQUIREMENTS 01700 -6 HIGH POINT ABC SECTION 01770 - CLOSEOUT PROCEDURES, PART 1 -GENERAL, Ll A 12 SUMMARY This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following: Inspection procedures. Project Record Documents. Operation and maintenance manuals. Warranties. Instruction of Owner's personnel, Final cleaning, ausene See Division 1 Section "Payment Procedures" for requirements for Applications for Payment for Substantial and Final Completion. See Division 1 Section "Construction Progress Documentation" for submitting Final ‘Completion construction photographs and negatives, See Divisions 2 through 16 Sections for specific closeout and special cleaning requirements for products of those Sections. SUBSTANTIAL COMPLETION Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request. 1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete. 2. Advise Owner of pending insurance changeover requirements. 3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents. 4, Obtain and submit releases permitting Owner unrestricted use of the Work and access to services and utilities, Include occupancy permits, operating certificates, and similar releases. 5. Prepare and submit Project Record Documents, operation and maintenance manuals, damage or settlement surveys, property surveys, and similar final record information. 6. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable. 7, Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions. Complete startup testing of systems. 9. Submit test/adjust/balance records. ‘CLOSEOUT PROCEDURES 0170-1 HIGH POINT ABC 12) 14 10, Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements. 11. Advise Owner of changeover in heat and other utilities, 12, Submit changeover information related to Owner's occupancy, use, operation, and ‘maintenance. 13, Complete final cleaning requirements, including touchup painting. 14, Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects, Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare the Certificate of Substantial Completion after inspection, or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued, 1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected. 2. Results of completed inspection will form the basis of requirements for Final Completion. FINAL COMPLETION Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following: 1. Submit final Application for Payment according to Division 1 Section "Payment Procedures." 2. Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. ‘The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance. 3. Submit evidence of final, continuing insurance coverage complying with insurance requirements. 4, Submit pest-control final inspection report and warranty, 5. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection ot will notify Contractor of construction that must be completed or corrected before certificate will be issued. 1, Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected. LIST OF INCOMPLETE ITEMS (PUNCH LIST) CLOSEOUT PROCEDURES 01770-2 HIGH POINT ABC 13 A Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. 1. Organize list of spaces in sequential order, starting with exterior areas first proceeding from main entry to rear entry. 2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems PROJECT RECORD DOCUMENTS, General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for Architect's reference during normal working hours. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings. 1, Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints. 4, Give particular attention to information on concealed elements that cannot be readily identified and recorded later. b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations. 2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location. 3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable. 4, Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets; bind each set with durable paper cover sheets. Include identification on cover sheets. Record Specifications: Submit one copy of Project's Specifications, including addenda and ‘contract modifications. Mark copy to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications. 1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. 2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected. 3. Note related Change Orders and Record Drawings, where applicable, Miscellaneous Record Submittals: Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference. CLOSEOUT PROCEDURES 0170-3 HIGH POINT ABC 16 A. 17 PART 2- 24 OPERATION AND MAINTENANCE MANUALS, Assemble a complete set of operation and maintenance data indicating the operation and maintenance of each system, subsystem, and piece of equipment not part of a system. Include operation and maintenance data required in individual Specification Sections and as follows: 1. Operation Data: Include emergency instructions and procedures, system and equipment descriptions, operating procedures, and sequence of operations, 2. Maintenance Data: Include manufacturer's information, list of spare parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and copies of warranties and bonds, Organize operation and maintenance manuals into suitable sets of manageable size. Bind and index data in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, with pocket inside the covers to receive folded oversized sheets. Téentify each binder on front and spine with the printed title "OPERATION AND MAINTENANCE MANUAL," Project name, and subject matter of contents. WARRANTIES, ‘Submittal Time: Submit written warranties on request of Architect for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual. 1, Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper. 2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product o installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer. 3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor. Provide additional copies of each warranty to include in operation and maintenance manuals, PRODUCTS MATERIALS, Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces. PART 3 - EXECUTION CLOSEO UT PROCEDURES: 01770-4 HIGH POINT ABC 34 32 A DEMONSTRATION AND TRAINING Instruction: Instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system, 1. Provide instructors experienced in operation and maintenance procedures. 2. Provide instruction at mutually agreed-on times. For equipment that requires seasonal operation, provide similar instruction at the start of each season. 3. Schedule training with Owner, through Architect, with at least seven days' advance notice. 4, Coordinate instructors, including providing notification of dates, times, length of instruction, and course content. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of @ system, as required by individual Specification Sections. For cach training module, develop a learning objective and teaching outline. : Include instruction for system design and operational philosophy, review of documentation, operations, adjustments, troubleshooting, maintenance, and repai. FINAL CLEANING General: Provide final cleaning, Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipoliution regulations. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturers written instructions. 1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project: a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances, b. Sweep paved areas broom clean, Remove petrochemical spills, stains, and other foreign deposits. ¢. Rake grounds that are neither planted nor paved to @ smooth, even-textured surface. 4. Remove tools, construction equipment, machinery, and surplus material from Project site, €. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces, Restore reflective surfaces to their original condition. £ Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts trenches, equipment vaults, manholes, attics, and similar spaces. 8 Sweep concrete floors broom-clean in unoccupied spaces, CLOSEOUT PROCEDURES 0170-5 HIGH POINT ABC P. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision-obscuring materials Replace chipped or broken glass and other damaged transparent materials, Polish mirrors and glass, taking care not to scratch surfaces. Remove labels that are not permanent. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair of restoration. 1) Do not paint over "UL" and similar labels, including mechanical and electrical nameplates. Wipe surfaces of mechanical and electrical equipment, and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances. Replace parts subject to unusual operating conditions. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures. Leave Project clean and ready for occupancy. . Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid Project of rodents, insects, and other pests. Prepare a report. D. Comply with safety standards for cleaning. Do not bum waste materials. Do not bury debris or excess materials on Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully. END OF SECTION 01770 CLOSEOUT PROCEDURES 0170-6 HIGH POINT ABC SECTION 01781 - PROJECT RECORD DOCUMENTS. PART 1- GENERAL, Ll A 12 c SUMMARY This Section includes administrative and procedural requirements for Project Record Documents, including the following: 1, Record Drawings. 2. Record Specifications. 3. Record Product Data. See Division 1 Section "Closeout Procedures" for operation and maintenance manual requirements. See Divisions 2 through 16 Sections for specific requirements for Project Record Documents of products in those Sections. SUBMITTALS Record Drawings: Comply with the following: 1. Number of Copies: Submit one set of marked-up Record Prints, 2. Number of Copies: Submit copies of Record Drawings as follows: a, Initial Submittal: Submit one set of marked-up Record Prints, and the following: Record Specifications: Submit one copy of Project's Specifications, including addenda and contract modifications, Record Product Data: Submit one copy of each Product Data submittal. PART 2-PRODUCTS 24 A RECORD DRAWINGS Record Prints: Maintain one set of blue- or black-line white prints of the Contract Drawings and Shop Drawings. 1. Preparation: Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare ‘marked-up Record Prints. PROJECT RECORD DOCUMENTS 01781 -1 HIGH POINT ABC a, Give particular attention to information on concealed elements that would be difficult to identify or measure and record later. b. Record data as soon as possible after obtaining it, Record and check the markup before enclosing concealed installations, Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location. Note Construction Change Directive numbers, altemate numbers, Change Order numbers, and similar identification, where applicable. B. Format; Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. 1 Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable scts, Bind each set with durable paper cover sheets. Include identification on cover sheets. Identification: As follows: Project name. Date. Designation "PROJECT RECORD DRAWINGS." Name of Architect. Name of Contractor. 2.2 RECORD SPECIFICATIONS A. Preparation: ‘Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications. 1 2. 3 4, Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. ‘Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected, Record name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made. Note related Change Orders, Record Drawings, and Product Data where applicable. 2.3. RECORD PRODUCT DATA ‘A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal. L 2 Give particular attention to information on concealed products and installations that ‘cannot be readily identified and recorded later. Include significant changes in the product delivered to Project site and changes in ‘manufacturer's written instructions for installation PROJECT RECORD DOCUMENTS 01781 -2 HIGH POINT ABC 24 3. Note related Change Orders, Record Drawings, and Product Data where applicable. MISCELLANEOUS RECORD SUBMITTALS Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work, Bind or file miscellaneous records and identify each, ready for continued use and reference. PART 3 - EXECUTION BA A RECORDING AND MAINTENANCE Recording: Maintain one copy of each submittal during construction period for Project Record Document purposes. Post changes and modifications to Project Record Documents as they occur; do not wait until end of Project. ‘Maintenance of Record Documents and Samples: Store Record Documents and Samples in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for Architect's reference during normal working hours. END OF SECTION 01781 PROJECT RECORD DOCUMENTS 1781-3 HIGH POINT ABC. SECTION 02115 SOIL EROSION AND SEDIMENT CONTROL PART I - GENERAL: 11 SUMMARY: A. This Section includes the following: 1, Erosion control during construction, 2. Temporary seeding and mulching, B, Related Sections include the following: 1, Section 02300- Earthwork 12 SYSTEM DESCRIPTION: A. The extent of soil erosion and sediment control is shown on the drawings and specified herein and generally includes the installation of erosion control devices as shown, maintenance of erosion control devices during construction, and removal at completion. Temporary seeding of disturbed areas is also included in this Section, B. Intent and Procedures: 1. General: Contractor shall do all that is possible to minimize soil erosion and siltation caused by construction operations. The North Carolina Sedimentation Control Commission's Erosion and Sediment Control Planning and Design Manual Practice Standards and Specifications are minimum requirements. Conaply with all applicable regulations relating to the control of soil erosion and prevention of sedimentation pollution. The Contractor shall be fully informed regarding all regulations w conduct of the work, and shall comply with such regulations at all times. affect the 2. Prior to the beginning of soil surface disturbing activities, temporary sol erosion control ‘measures and devices shall be placed as indicated at the areas affected by the land-disturbing activities. Contractor will lay out devices by staking and schedule a site ‘meeting with authorities having jurisdiction to approve erosion control measures prior to installation, 3. Surface water run-off originating upgrade from exposed areas should be controlled to reduce erosion in sediment loss during the period of exposure. ll land-disturbing, activites are to be planned and conducted so as to minimize off-site sedimentation damage. The Contractor shall conduct is activities in a manner which will prevent sediment from teaching streams flowing off site and will prevent increased velocities and peak rates of storm water runoff from resulting in erosion along receiving streams. 4, During the land-disturbing activities, all actions shall be planned and conducted to SOIL EROSION AND SEDIMENT CONTROL. 2115-1 HIGH POINT ABC 10, ‘minimize the size of any area to be exposed at any one time and to limit exposure to the shortest feasible time. All disturbed areas shall be temporarily seeded for erosion protection within twenty-one (21) calendar days on any portion upon which active construction is no longer being undertaken. Every effort possible shall be made to bring each segment of the site to a stable state as quickly as possible, thus minimizing erosion potential Additional erosion control measures may be required by the authorities having jurisdiction that are not shown on the plan. Itis the contractors responsibility to maintain erosion onsite, regardless of the measures required. Any change in the erosion control measures andlor grading shall be called to the attention of the engineer and the authorities having jurisdiction, Weather forecast shall be monitored. The contractor shall prepare for rain events by re- ‘examining all erosion control measues prior to statt of precipitation, Any re-enforcement ‘or corrections should be performed and documented. If fill materials are to be brought onto this project or waste materials are to be taken from this project, this information shall be disclosed and shown on the erosion control and grading plan. Borrow areas and dump sites are considered to be part ofthis project and the property owner of the borrow or dump site is responsible for stabilization and erosion control measures at these sites. The Contractor shall provide the following: a, Written documentation of all deviations from the erosion control plan shall be noted on the approved plans. b, Written documentation of an emergency situation where sediment has been discharged off ste shall be recorded. Also, contractor's actions to repair and return area to prestorm condition shall be recorded. «©. The Contractor shall inspect all erosion and sedimentation control facilites every seven days and within 24 hours of a 0.5 inch or greater of rain. Findings shall be recorded and presented upon request ofthe authorities having jurisdiction. 4. The contractor shall provide rain-recording device and record each rainfall . Any failures that cause visible sedimentation to leave the approved disturbed limits shall be corrected immediately and documented. The authorities having jurisdiction can requie, in addition to any other civil or criminal penalty ot injunctive relief, that any petson(s) who is engaged in a land-disturbing activity and fails to retain sediment generated by the land-isturbing activity, to restore the waters and land affected by the failure so as to minimize the detrimental effects of the resulting pollution. The Contractor may be held liable for any costs, fines or penalties incurred due to any “Notice of Violation” issued by the authorities having jurisdiction ifthe violation is a result of not following the plan, not making repairs ot correction as directed within the specified timeframe, for failure to maintain the devices, or for any other deficiency noted SOIL EROSION AND SEDIMENT CONTROL 2115-2 HIGH POINT ABC in the Notice of Violation that is a result ofthe contractor's actions. The Contractor will not be held liable for any costs, fines or penalties incurred due to any “Notice of ‘Violation” issued by the authorities having jurisdiction ifthe violation isa result of circumstances beyond the control of the Contractor. PART 2- PRODUCTS: 21 22 23 24 SILT FENCE: A, Silt fence fabric shall be, industrial propylene fabric and reinforcement netting stitched together, or other suitable material as approved by the soil erosion control agency ‘maintaining jurisdiction over this site, B. Silt fence reinforcing wire shall be agricultural quality annealed steel #14 W & W ga. wire ‘with open web pattern of 4" x 5" spacing maximum. Place wire support behind fabric. Silt fence supports shall be solid, steel "T-shaped posts. ‘TEMPORARY SEEDING: A. Temporary seeding including fertilizer, limestone and mulch is required to temporarily anchor all disturbed earth and erosion ditches during construction, Seeding schedule is as follows: B, _ Temporary Seeding Schedule: See plans for temporary seeding schedule ‘SOIL AMENDMENTS: ‘A. Limestone: Agricultural ground limestone shall be dolomitic type NCDOT Section 960-2. B. Fertilizer: NCDOT Section 960-1. Fertilizer composition shall be approved by the ‘Architect prior to spreading and shall be dry and free flowing, and shall be delivered to the site in the guaranteed analysis. Any fertilizer which becomes caked ot otherwise damaged ‘making it unsuitable for use, will not be accepted. Fertilizer shall not have been exposed to ‘weather prior to delivery until used, it shall be completely protected at all times. It shall not be stored in direct contact with the ground. C. Mulch: A protective cover shall be placed overall newly seeded areas. It shall consist of cither hay, straw, wood cellulose fiber and tacked with non-toxic asphaltic emulsion, All mulch shall be free of noxious weeds, mold, or other objectionable material. Straw and hay shall be in an ait-dry condition and suitable for placing with mulch blowet equipment D. Asphalt Emulsion Tackifier: Asphalt emulsion, ASTM D 977, Grade SS-1, nontoxic end free of plant growth- or germination-inhibitors. EROSION CONTROL MATERIALS: A. Blankets: Biodegradable wood excelsior, straw, or coconut-fiber mat enclosed in a photodegradable plastic mesh, Excelsior matting shall have mesh on both sides of blanket SOIL EROSION AND SEDIMENT CONTROL 021153 HIGH POINT ABC and shall have a minimum sheat strength of 2 psf, Include manufacturer's recommended steel wire staples, 6 inches long, 2.5 MISCELLANEOUS: A. Concrete Unit Masonry (CMU) units shall be used for catch basin protection as detailed. B. Stone for construction entrance(s) shall be as detailed on the drawings. PART 3- EXECUTION: 3.1 CONSTRUCTION OF TEMPORARY DEVIC! ‘A. Stone construction entrance(s) shall be constructed as shown on the drawings. Maintain stone construction entrance(s) throughout the construction period to prevent mud from being tracked onto the adjoining roads. B. Silt fences shall be constructed of length and configuration necessary to protect against contamination and erosion. Maintain until the work under this Contract is complete. Silt fence shall be installed with the bottom 6” of the fabric placed in a 6" deep trench and backfilled with washed stone to prevent undermining of the silt fence. The silt fabric, fence and posts shall be maintained in good working order throughout the period of the Contract. Apply silt fabric on uphill side of posts with enough wire clips to prevent slippage or sagging under full load, C. Catch basin protection shall be constructed so that CMU anchors stone in place and both ‘work together to filter sediment from runoff. Maintain protection until stand of grass has covered soil. 3.2 SEEDING AND MULCHING: ‘A. Fertilizer shall be distributed evenly by mechanical spreader, worked into the top 4" of topsoil ‘not more than one week prior to seeding operations, Spread at the rate indicated on the plans. Broadcast l/2 of fertilizer in one direction and the remaining 1/2 in a direction at right angles to the first direction, B. Limestone shall be spread at a rate indicated on the plans, unless recommended otherwise by soil analysis. C. Temporary seeding shall be placed with mechanical seeders. Rake or scarify ground areas prior to the start of the seeding operation, Sow equal quantities in two directions at right angles to each other to assure an even distribution over the entire area, D. Mulch shall be spread uniformly over seeded areas atthe rate indicated on the plans, The ‘mulch shall be anchored with the mulch tiller, or ifthe area is not acceptable, asphalt emulsion may be used as tiedown or adhesive, Type $S-1 or approved equal shall be applied either simultaneously with the straw or hay or in a separate operation. The Contractor shall SOIL EROSION AND SEDIMENT CONTROL 021154 HIGH POINT ABC take precautionary measures to provent asphalt adhesive materials from marking or defecing structures, pavements, utilities or plants. 3.3 REMOVAL OF TEMPORARY DEVICES ‘A. Silt Fences and Other Temporary Devices: After completion of site work under this Contract, ‘and a satisfactory stand of grass has been approved the Contractor is to remove sit fences, catch basin protection and other erosion control devices and legally dispose of same off the site END OF SECTION 02115 SOIL EROSION AND SEDIMENT CONTROL o21is-5 HIGH POINT ABC ‘SECTION 02221 - SITE DEMOLITION PART 1 - GENERAL: Ll 12 13 14 1s 16 SUMMARY: ‘A. Section includes demolition of designated structures; demolition of foundations and slabs-on-grade; and disconnecting and demolition of identified utilities; removing demolished materials from the site; protection of items to remain as indicated. B. _ Related Sections: 1. Section 02230 ~ Site Clearing 2. Section 02300 - Earthwork SUBMITTALS: A. Shop Drawings: Indicate demolition and removal sequence and location of salvageable items; location and construction of barricades, fences and temporary work. CLOSEOUT SUBMITTALS: A. Project Record Docuiments: Accurately record actual locations of capped utilities and subsurface obstructions, QUALIFICATIONS: A. Demolition Firm: Company specializing in performing the Work of this section with ‘minimum five years documented experience. REGULATORY REQUIREMENTS: ‘A. Conform to applicable code for demolition of structure, safety of adjacent structures, and dust control. B. Obtain required permits from authorities. C. Notify affected utility companies before starting work and comply with their requirements. D. _Donot close or obstruct roadways, sidewalks and hydrants without permits. E, Conform to applicable regulatory procedures when discovering hazardous or contaminated materials, SCHEDULING: ‘A. Schedule Work to precede site excavation work, B. Describe demolition removal procedures and schedule SITE DEMOLITION 0221-1 HIGH POINT ABC PART 2- PRODUCTS: 21 FILL MATERIALS: A. Fill Material: Soil fil, specified in Section 02300. PART3- EXECUTION: 3.1 PREPARATION: ‘A. Provide, erect, and maintain temporary barriers and security devices, including waming signs and lights, and similar measures, for protection of the public, Owner, Contractor's employees and existing improvements to remain. B. Protect existing landscaping materials, trees, appurtenances, and structures which are not to ‘be demolished, C. Prevent movement or settlement of adjacent structures. Provide bracing and shoring. D. Mark location of utilities. 3.2 DEMOLITION REQUIREMENTS: ‘A. Conduct demolition to minimize interference with adjacent structures and occupancies. B. Cease operations immediately if adjacent structures appear to be in danger. Notify Architect, Do not resume operations until directed. C. Conduct operations with minimum interference to public or private accesses. Maintain protected egress and access from adjacent structures at all times. D. Obtain written permission from adjacent property owners when demolition equipment will traverse, infringe upon or limit access to their property. Sprinkle Work with water to minimize dust. Provide hoses and water connections for this, Purpose. 33 DEMOLITION: A. Disconnect, remove, and identify designated utilities within demolition areas. B. Remove foundation walls and footings to a minimum of two feet below finished grade beyond area of new construction and completely remove all foundation walls and footings within area of new construction, C. Remove concrete slabs on grade, SITE DEMOLITION 2221-2 HIGH POINT ABC D. _ Backiill open pits and holes caused as a result of demolition, in accordance with Section 02300. E. Rough grade and compact areas affected by demolition to maintain site grades and contours. F. Continuous clean-up and remove demolished materials from site. Do not allow materials to accumulate in the building or on the site. G. Donot burn or bury materials on site, Leave site in clean condition. END OF SECTION 02221 SITE DEMOLITION 022213 HIGH POINT ABC SECTION 02300 - EARTHWORK PART | ~GENERAL: 1.1 SUMMARY: A. This Section includes the following: 1. 2. 3. 4 B Rel 1 2. 3. 4 Preparing subgrades, pavements, lawns, and plantings. Excavating and backfilling trenches’ for buried utilities and buried utility structures. Unit price for rock, trench rock and unsuitable soil excavation. Provide dewatering required to protect subgrade. ated Sections include the following: Section 02115 “Soil Erosion and Sediment Control”. Section 02230 “Site Clearing” Section 02630 “Storm Drainage Systems”. Section 02924 “Seeding and Soil Supplements”. 1.2 UNITPRICES: Ae oi ick and Trench Rock Measurement: Volume of rock actually removed, measured in original position, but not to exceed the following: Pepe 24 inches outside of concrete forms other than at footings. 12 inches outside of concrete forms at footings. 6 inches outside of minimum required dimensions of concrete cast against grade, Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments, 6 inches beneath bottom of concrete slabs on grade. 6 inches beneath pipe in trenches, and 24 inches wider than pipe. B. Unit prices for rock and trench rock excavation include replacement with approved materials. 13. DEFINITION! iS: A. Backfill: Soil materials used to fill an excavation, cE 2. Initial Backfill: Backfill placed beside and over pipe in a trench, including hhaunches to support sides of pipe. Final Backfill: Backfill placed over initial backfill to fill a trench. B. Bedding Course: Layer placed over the excavated subgrade in a trench before laying pipe. C. Borrow: Satisfactory sol imported from offsite for use as fll or backfill. EARTHWORK, 0230-1 HIGH POINT ABC D. Drainage Course: Layer supporting slab-on-grade used to minimize capillary flow of pore water. Excavation: Removal of material encountered above subgrade elevations, 1, Additional Excavation: Excavation below subgrade elevations as directed by Architect. Additional excavation and replacement material will be paid for according to Contraet provisions for changes in the Work. 2. Bulk Excavation: Exeavations more than 10 feet in width and pits more than 30 feet in either length or width. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated dimensions without direction by Architect. Unauthorized excavation, as well as remedial work directed by Architect, shall be without additional ‘compensation. Fill: Soil materials used to raise existing grades. Rock: Rock material in beds, ledges, unstratified masses, and conglomerate deposits and boulders of rock material exceeding 1 cu. yd. for bulk excavation or 3/4 cu. yd. for footing, trench, and pit excavation that cannot be removed by rock excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, ripping, or blasting, when permitted: 1. Excavation of Footings, Trenches, and Pits: Late-mmodel, track-mounted hydraulic excavator; equipped with # 42-inch- wide, short-tip-radius rock bucket; rated at not less than 120-hp flywheel power with bucket-curling force of not less than 25,000 Ibf and stick-crowd force of not less than 18,700 Ibf; measured according to SAE J-1179. Bulk Excavation: Late-model, track-mounted loader; rated at not less than 210- hp flywheel power and developing a minimum of 45,000-Ibf breakout force; ‘measured according to SAE J-732. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface. ‘Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill or backfill immediately below base, drainage fill, or topsoil materials. Utilities include on-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings. 14 SUBMITTALS: A Material Test Reports: From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated: 1. Classification according to ASTMD 2487 of each on-site or borrow soil ‘material proposed for fill and backfill. 2. Laboratory compaction curve according to ASTM D 698 for each on-site or borrow soil material proposed for fill and backfill. EARTHWORK 0230-2 HIGH POINT ABC 1.5 PROJECT CONDITIONS: A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted in writing by Architect and then only after arranging to provide temporary utility services according to requirements indicated: 1. Notify Architect not Jess than two days in advance of proposed utility interruptions, 2. Do not proceed with utility interruptions without Architect's written permission, 3. Contact utility-locator service for area where Project is located before excavating. Demolish and completely remove from site existing underground utilities indicated to be removed, Coordinate with Owner to shut off services if lines are active. Refer to the geotechnical report prepared by ECS Carolinas, LLP, for the High Point ABC Board dated July 6, 2006. PART 2- PRODUCTS: 2.1. SOIL MATERIALS: A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations, Satisfactory Soils: ASTM D 2487 soil classification groups CL, ML, GC, SC, GW, GP, GM, SW, SP, and SM, ot a combination of these group symbols; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter. Unsatisfactory Soils: ASTM D 2487 soil classification groups, MH, CH, OL, OH, and PT, or a combination ofthese group symbols. 1. Unsatisfactory soils also include satisfactory soils not maintained within 5 percent of optimum moisture content at time of compaction. Backdill and Fill: Satisfactory soil materials. Backfill and fill in structural areas shall not contain more than 5 percent by weight organic material, shal not have plasticity index (PP greater than 25, or have a maximum dry density less than 90 pounds per cubie foot. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve. PART 3 EXECUTION: EARTHWORK 2300-3, HIGH POINT ABC 3.1 PREPARATION: A Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards cteated by earthwork operations, Protect subgrades and foundation soils against freezing temperatures or frost. Provide protective insulating materials as necessary. Provide erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airbome dust to adjacent properties and walkways. 3.2 DEWATERING: A Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area, Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation. 1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches. 2, Install a dewatering system to keep subgrades dry and convey ground water away from excavations. Maintain until dewatering is no longer required. Dewatering systems shall discharge into an on-site erosion control measure until contributing drainage areas are stabilized, 3.3. EXPLOSIVES: A Explosives: The use of explosives is prohibited 3.4 EXCAVATION, GENERAL: A EARTHWORK Classified Excavation: The following classifications of excavation will be made when rock excavation is encountered in work: 1. Barth Excavation: Barth excavation includes excavation of earth and other materials encountered that are not classified as rock, trench rock, unsuitable or unauthorized excavation 2. Trench Rock Exca Includes removal, disposal of materials and obstructions encountered which cannot be excavated with equipment specified. Payment for trench rock excavation shall be on the basis of the unit price stated con_the bid form. Field measurements shall be determined by the Owner's soil testing service and verified by the Architect. Payment of trench rock shall include replacement with satisfactory soil materials. 3. Rock Excavation: Includes removal and disposal of materials and obstructions encountered which cannot be disloged and excavated with equipment specified. 0230-4 HIGH POINT ABC Rock materials include boulders % cubic yard or more in volume, solid rock, rock in ledges, and rock hard cementitious aggregate deposits. Intermittent drilling, blasting or ripping performed to increase production and not necessary to permit excavation shall be classified as earth excavation. Payment for rock excavation will be on the basis of the unit price stated on the bid form. Payment of rock excavation shall include replacement with satisfactory soil materials. Field measurements shall be determined by the Owner’s soil testing service and verified by the Architect. 3.5. EXCAVATION FOR WALKS AND PAVEMENTS: A Excavate surfaces under walks and pavements to indicated cross sections, elevations, and grades. 3.6 EXCAVATION FOR UTILITY TRENCHES: A Excavate trenches to indicated gradients, lines, depths, and elevations. 1. Beyond building perimeter, excavate trenches to allow installation of top of pipe below frost line. Excavate trenches to uniform widths to provide a working clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches higher than top of pipe or conduit, unless otherwise indicated. 1, Clearance: 12 inches on each side of pipe or conduit. ‘Trench Bottoms: Excavate and shape trench bottoms to provide uniform bearing and support of pipes and conduit. Shape subgrade to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. Remove projecting stones and sharp objects along trench subgrade. 1. For pipes and conduit less than 6 inches in notninal diameter and flat-bottomed, multiple-duct conduit units, hand-excavate trench bottoms and support pipe and conduit on an undisturbed subgrade. 2. For pipes and conduit 6 inches or larger in nominal diameter, shape bottom of trench to support bottom 90 degrees of pipe circumference. Fill depressions with tamped sand backfill, 3. __Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course. 3.7 APPROVAL OF SUBGRADE AND UNSATISFACTORY MATERIAL: A B c EARTHWORK Notify Architect when excavations have reached required subgrade, If Architect determines that unsatisfactory soil is present, continue excavation and replace with compacted backtill or fill material as directed. Excavation of unsatisfactory soi | materials and replacement material will be paid fo 0230-5 HIGH POINT ABC by adjusting the Contract Sum according to ‘Documents, t_prices included in the Contract Proof roll subgrade with pneumatic-tired equipment with a minimum loaded weight of 20, tons to identify soft pockets and areas of excess yielding. Do not proof roll wet or saturated subgrades, Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Architect. 3.8 UNAUTHORIZED EXCAVATION: A ‘Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without the specific direction of the Architect. Fill ‘unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation, Lean concrete fill may be used when approved by Architect. Unauthorized excavations will be filled at no additional cost to the Owner. 1. Fill. unauthorized excavations under other construction or utility pipe as directed by Architect at no additional cost to the Owner. 3.9 STORAGE OF SOIL MATERIALS: A. Stockpile borrow materials and satisfactory excavated soil matetials. Stockpile soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees. 3.10 BACKFILL: A. Place and compact backfill in excavations promptly, but not before completing the following: 1. Construction below finish grade including, where applicable, dampproofing, ‘waterproofing, and perimeter insulation Surveying locations of underground utilities for record documents, Inspecting and testing underground utilities. Removing concrete formwork. ‘Removing trash and debris. Removing temporary shoring and bracing, and sheeting Installing permanent or temporary horizontal bracing on horizontally supported walls. SABAYN 3.11 UTILITY TRENCH BACKFILL: EARTHWORK, 0230-6 HIGH POINT ABC. 3.12 FILL: Backfill trenches excavated under footings and within 18 inches of bottom of footings; fill with concrete to elevation of bottom of footings. Coordinate backfilling with utilities testing Fill voids with approved backfill materials while shoring and bracing, and as sheating is removed. Place and compact final backfill of satisfactory soil material to final grade. Preparation: Remove vegetation, topsoil, debris, unsatisfactory soil materials, obstructions, and deleterious materials from ground surface before placing fills. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material Place and compact fill material in ayers to required elevations as indicated. 3.13 MOISTURE CONTROL: A Uniformly moisten or aerate subgrade and each subsequent fill or backfill layer before compaction to within 5 percent of optimum moisture content. 1. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain frost or ice 2. Remove and replace, or scarify and air-dry, otherwise satisfactory soil material that exceeds optimum moisture content by 5 percent and is too wet to compact to specified dry unit weight. 3.14 COMPACTION OF BACKFILLS AND FILLS: A EARTHWORK Place backfill and fill materials in layers not more than 8 inches in loose depth for ‘material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers. Place backfill and fill materials evenly on all sides of structures to required elevations, and uniformly slong the full length of each structure, Compact soil to not less than the following percentages of maximum dry unit weight according to ASTM D 698: 1. Under building pads, each layer of backfill or fill material at 100 percent. 2. Under structures, steps, and pavements, scarify and recompact top 24 inches of existing subgrade, backfill or fill material at 100 percent. Below top 24 inches at 95 percent 0230-7 HIGH POINT ABC 3. Under walkways, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill material at 95 percent. 4. Under lawn or unpaved areas, scarify and recompact top 6 inches below subgrade and compact each layer of backtill or fill material at 90 percent. 3.15 GRADING: A General: Uniformly grade areas to a smooth surface, free from irregular surface changes. ‘Comply with compaction requirements and grade to cross sections, lines, and elevations indicated 1, Provide a smooth transition between adjacent existing grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances. Site Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances: 1, Lawn or Unpaved Areas: Plus or minus 1 inch, 2. Walks: Plus or minus 1 inch. 3. Pavements: Plus or minus 1/2 inch, Grading inside Building Lines: Finish subgrade to a tolerance of 1/2 inch when tested with a 10-foot straightedge. 3.16 BASE COURSES: A Under pavements, place base course on prepared subgrade and as follows: 1, Place base course material over prepared subgrade. 2. Compact base courses at optitmum moisture content to required grades, lines, cross sections, and thickness to not fess than 95 percent of maximum dry unit weight according to ASTM D 698, 3. Shape base to required crown elevations and cross-slope grades. 4. When thickness of compacted base course is 6 inches or less, place materials in a single layer. 5. When thickness of compacted base course exceeds 6 inches, place materials in equal layers, with no layet more than 6 inches thick or less than 3 inches thick ‘when compacted, 3.17 FIELD QUALITY CONTROL: A B. EARTHWORK Testing Agency: Owner will engage a qualified independent geotechnical engineering testing agency to perform field quality-control testing. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earthwork only after test results for previously completed work comply with requirements. 0230-8 HIGH POINT ABC C. Footing Subgrade: At footing subgrades, at least one test of each soil stratum will be performed to verify design bearing capacities. Subsequent verification and approval of other footing subgrades may be based on a visual comparison of subgrade with tested subgrade when approved by Architect. D. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTMD 2167, ASTMD 2922, and ASTMD 2937, as applicable, Tests will be performed at the following locations and frequencies: 1. Building Areas: At subgrade and at each compacted fill and backfill layer, at least one test for every 2500 sq.ft. oF less of building slab, but in no case fewer than three tests. 2. Paved Areas: At subgrade and at each compacted fill and backfill layer, atleast ‘one test for every 5000 sq. ft. or less of paved area, but in no case fewer than three tests. 3. Trench Backfill: At each compacted initial and final backfill layer, atleast one test for each 300 feet or less of trench length, but no fewer than two tests. E, When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil to depth required; recompact and retest until specified compaction is obtained. 3.18 PROTECTION: A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion, Keep fie of trash and debris. B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions. 1. Scatify or remove and replace soil material to depth as directed by Architect; reshape and recompact. C. Where settling ocours before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing, 1, Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to the greatest extent possible. 3.19 DISPOSAL OF SURPLUS AND WASTE MATERIALS: ‘A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Owner's property. END OF SECTION 02300 EARTHWORK 02300-9 HIGH POINT ABC ‘SECTION 02362 - TERMITE CONTROL PART 1 -GENERAL: 1.1 SUMMARY: A. Section includes soil treatment for termite control below grade. 12 SUBMITTALS: A. Product Data: Submit toxicants to be used, composition by percentage, dilution schedule, intended application rate in accordance with manufacturer's current pesticide label 13. QUALIFICATIONS: A. Applicator: ‘Company specializing in performing the Work of this section with minimum five years documented experience. 1.4 REGULATORY REQUIREMENTS: ‘A. Conform to the requirements of the North Carolina Department of Agriculture and Consumer Services, Structural Pest Control Division for application licensing and authority to use toxicant chemicals. B. Provide certificate of compliance from authority having jurisdiction indicating approval of toxicants. 1.5 SEQUENCING: ‘A. Apply toxicant 12 hours prior to installation of vapor barrier under slabs-on-grade, 1.6 WARRANTY: ‘A. Provide five year warranty, B. Warranty: Include coverage for damage and repairs to building and building contents caused by termites, Repair damage. Re-treat where required. C. Inspect and report annually to Owner in writing. PART 2- PRODUCTS: 2.1 MATERIALS: A. Toxicant Chemical: EPA and local authority approved; synthetically color dyed to permit visual identification of treated soil. B, Dilutent: Recommended by toxicant manufacturer. ‘TERMITE CONTROL, 02362-1 HIGH POINT ABC 2.2 MIXES: A, Mix toxicant to manufacturer's instructions. PART3- EXECUTION: 3.1 EXAMINATION: A. Verify that soil surfaces are unftozen, sufficiently dry to absorb toxicant, and ready to receive treatment. B. Verify final grading is complete. 3.2 APPLICATION: A. Apply toxicant in accordance with manufacturet’s instructions. B. Apply toxicant at locations indicated in Schedule at end of section. C. Apply extra treatment to structure penetration surfaces such as pipe or ducts, and soil penetrations such as grounding rods or posts. D. _ Restreat disturbed treated soil with same toxicant as original treatment. E, If inspection or testing identifies the presence of termites, e-treat soil and re-test. 3.3. PROTECTION OF FINISHED WORK: A. Do not permit soil grading over treated work. 3.4 SCHEDULES: ‘A. Locations: 1. Under Slabs-on-Grade, 2. Both Sides of Foundation Surface. END OF SECTION 02362 ‘TERMITE CONTROL, 02362-2 HIGH POINT ABC SECTION 02512 - SITE WATER DISTRIBUTION PART 1- GENERAL: Al 12 13 14 Ls SUMMARY: A. Section includes pipe and fittings for site water line including domestic water line and fire water line; and valves, fire hydrants and appurtenances, B. Related Sections: 1. Section 02300 - Earthwork. 2. Section 02516 - Disinfection of Water Distribution: Disinfection of site service utility water piping, REFERENCES: ‘A. AWWA CIII (American Water Works Association) - Rubber- Gasket Joints for Ductile Iron and Grey-Iron Pressure Pipe and Fittings. B. AWWACISI (American Water Works Association) - Ductile-Iton Pipe, Centrifugally Cast in Metal Molds or Sand-Lined Molds, for Water or Other Liquids. €. AWWA C509 (American Water Works Association) - Resilient Seated Gate Valves 3 in through 12 in NPS, for Water and Sewage Systems. D, AWWA C600 (American Water Works Association) - Installation of Ductile-Iron Water Mains and Appurtenances. SUBMITTALS: A, Product Data: Provide data on pipe materials, pipe fittings, valves and accessories. B. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. C. Operation and Maintenance Manual: For backflow preventer. CLOSEOUT SUBMITTALS: ‘A. Project Record Documents: Record actual locations of piping mains, valves, connections, thrust restraints, and invert elevations. B. Identify and describe unexpected variations to subsoil conditions or discovery of uncharted utilities. QUALITY ASSURANCE: SITE WATER DISTRIBUTION 02512-1 HIGH POINT ABC ‘A. Perform Work in accordance with municipality requirements. B _ Valves: Mamufacturet’s name and pressure rating marked on valve body. 1.6 DELIVERY, STORAGE, AND HANDLING: B. Preparation for Transport: Prepare valves, including fire hydrants, according to the following: 1. Ensure that valves are dry and intemally protected against rust and corrosion, 2. Protect valves against damage to threaded ends and flange faces. 3. Set valves in best position for handling. Set valves closed to prevent rattling. B, During Storage: Use precautions for valves, including fire hydrants, according to the following 1. Donot remove end protectors unless necessary for inspection; then reinstall for storage. 2. Protect from weather. Store indoors and maintain temperature higher than ambient dew- point temperature. Support off the ground or pavement in watertight enclosures when. ‘outdoor storage is necessary. B. Handling: Use sling to handle valves and fire hydrants if size requires handling by erane or lift. Rig valves to avoid damage to exposed parts. Do not use handwheels or stems as lifting or rigging points. B. Deliver piping with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe-end damage and to prevent entrance of dirt, debris, and moisture, B. Protect stored piping ftom moisture and dirt, Elevate above grade, Do not exceed structural capacity of floor when storing inside. B. Protect flanges, fittings, and specialties from moisture and dirt, 1.7 PROJECT CONDITIONS: A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1. Notify Architect not less than two days in advance of proposed utility interruptions, 2. Donnot proceed with utility interruptions without Architect's written permission, 1.8 COORDINATION: A. Coordinate connection to water main with utility company. PART 2- PRODUCTS: SITE WATER DISTRIBUTION 02512-2 HIGH POINT ABC 24 22 23 24 25 ‘DUCTILE IRON PIPE: A, Ductile Iron Pipe: AWWA C151: 1. Fittings: Ductile iron, standard thickness. 2. Joints: AWWA C111, rubber gasket with rods. GATE VALVES: A. AWWA C509, Iron body, bronze trim, non-rising stem with square nut, single wedge, resilient seat, mechanical joint ends, and valve key. B Tapping-Sleeve Assemblies: Comply with MSS SP-60. Include sleeve and valve compatible with drilling machine. 1. Tapping Sleeve: Cast- or ductile-iron or stainless steel, two-piece bolted sleeve with flanged outlet for new branch connection. Include sleeve matching size and type of pipe material being tapped and with recessed flange for branch valve. 2. Valve: AWWA, cast-iron, nonrising-stem, esilient-seated gate valve with one raised face flange mating tapping-sleeve flange. ©. Valve Boxes: Comply with AWWA M44 for castiron valve boxes. Include top section, adjustable extension of length required for depth of burial of valve, plug with lettering "WATER," bottom section with base of size to fit over valve, and approximately 5-inch diameter barrel. 1. Operating Wrenches: Steel, tee-handle with one pointed end, stem of length to ‘operate deepest buried valve, and socket matching valve operating nut. CORPORATION STOPS: ‘A. Service-Saddle Assemblies: Comply with AWWA C800. Include saddle and valve ‘compatible with tapping machine. 1. Service Saddle: Copper alloy with seal and AWWA C800, threaded outlet for ‘corporation valve. 2. Corporation Valve: Bronze body and ground-key plug, with AWWA C800, threaded inlet and outlet matching service piping material. COPPER TUBE AND FITTINGS: ‘A. Soft Copper Tube: ASTM B 88, Type K and ASTM B 88, Type L, water tube, annealed temper. 1. Copper Fittings: ASME B16.18, cast-copper-alloy or ASME B16.22, wrought- copper, solder-joint pressure type. Furnish only wrought-copper fittings if indicated, WATER METERS: A. Water meter will be supplied by utility company. SITE WATER DISTRIBUTION 02512-3 HIGH POINT ABC. 26 27 28 29 2.10 WATER METER BOXES: A. Description: Cast-iron body and cover for dise-type water meter with lettering "WATER METER" in cover; and slotted, open-bottom base section of length to fit over service piping. BACKFLOW PREVENTERS: ‘A. Backflow Preventers: AWWA C511, suitable for continuous pressure application. Include outside screw and yoke gate valves on inlet and outlet, and strainer on inlet; test cocks; and pressure-differential retief valve with ASME A\112.1.2, ar-gap fitting located between two positive-seating check valves. Maximum Pressure Loss: 12 psig through middle 1/3 of flow ange. Devices shall be as approved by the City of High Point. PROTECTIVE ENCLOSURES: A Protective Enclosures, General: ASSE 1060, outdoor weather-resistant enclosure designed to protect aboveground water piping equipment or specialties from vandalism. Provide size and dimensions required for access and service of protected unit Cover: Freeze-Protection Enclosures: Insulated and with heat source to maintain minimum. intemal temperature of 40 deg F (4 degC) when external temperatures reach as low as minus 34 deg F (minus 36 deg C). Unit shall include heater with self-limiting temperature control. Class I-V: For pressure or atmospheric vacuum breaker equipment or devices. Include drain opening in housing a. Housing: Reinforced aluminum construction. 1) Drain opening for units with drain connection. 2) Access doors with locking devices. 3) Insulation inside housing, 4) Anchoring devices for attaching housing to concrete base. Precast concrete base of dimensions required to extend at least 6 inches beyond edges of enclosure housings. Include openings for piping. BEDDING AND COVER MATERIALS: A. Bedding: Satisfactory soils specified in Section 02300. B. Cover: Satisfactory soils specified in Section 02300, ACCESSORIES: ‘A. Concrete for Thrust Restraints: 2500 psi concrete as specified in Section 03300. PART3- EXECUTION: SITE WATER DISTRIBUTION 02512-4 HIGH POINT ABC 31 32 33 34 EXAMINATION: ‘A. Verify that building service connection and municipal uility water main size, location, and invert areas indicated. PREPARATION: ‘A. Cutpipe ends square, ream pipe ends to full pipe diameter, remove burrs. B. Remove scale and dirt on inside and outside before assembly. C. Prepare pipe connections to equipment with flanges or unions. BEDDING: ‘A. Excavate pipe trench in accordance with Section 02300 for Work of this Section. B. Form and place concrete for pipe thrust restraints at any change of pipe direction, Place concrete to permit full access to pipe and pipe accessories. Provide thrust restraint bearing ‘on subsoil as indicated on the drawings. C. Place bedding material at trench bottom, level fill materials in one continuous layer not exceeding 6 inches compacted depth; compact to 95 percent. D. Backfill around sides and to top of pipe with cover fll, tamp in place and compact to 95 percent. Maintain optimum moisture content of fill material to attain required compaction densit INSTALLATION - PIPE: ‘A. Maintain separation of water main from sewer piping in accordance with North Carolina State Plumbing code and municipality requirements. y Install pipe to indicated elevation to within tolerance of 5/8 inches. 2 Install ductile iron piping and fittings to AWWA C600. D, Install pipe to allow for expansion and contraction without stressing pipe or joints. E, Install access fittings to permit disinfection of water system performed under Section 02516. F. Slope water pipe and position drains at low points. G. _ Formand place concrete for thrust restraints at each elbow or change of direction of pipe ‘main 3-inches or larger. 1H, Establish elevations of buried piping to ensure not less than 3 feet of cover. SITE WATER DISTRIBUTION 02512 -5 HIGH POINT ABC 35 3.6 37 38 39 1. Backfill trench in accordance with Section 02300, INSTALLATION - VALVES: A. Set valves on solid bearing. B. Center and plumb valve box over valve. Set box cover flush with finished grade. INSTALLATION ~ WATER METERS: ‘A. Install water meters, piping, and specialties according to utility company’s written requirements. INSTALLATION ~ BACKFLOW PREVENTERS: A. Install backflow preventers of type, size, and capacity indicated. Include valves and test cocks. Install according to requirements of plumbing and health department and authorities having jurisdiction. B, Support NPS 2-1/2 and larger backflow preventers, valves, and piping near floor and on brick or conerete piers. INSTALLATION — PROTECTIVE ENCLOSURES: A. Install concrete base level and with top approximately 2 inches above grade. B. Install protective enclosure over valves and equipment. Anchor protective enclosure to concrete base. DISINFECTION OF DOMESTIC WATER PIPING SYSTEM: A. Flush and disinfect system in accordance with Section 02516. 3.10. FIELD QUALITY CONTROL: ‘A. Prossure Test: After installation of all piping, valves, and fire hydrants, conduct pressure test of 150 psi fora duration of one hout. Open and close all valves several times during testing. Repair or replace any joint, pipe ot fittings failing pressure test and retest. B, Leakage Test: After the completion of a successful pressure test, conduct a leakage test for a duration of two hours with a pressure of 150 psi. Any leakage greater than allowed by the City of High Point shall be repaired until leakage is within allowance END OF SECTION 02512 SITE WATER DISTRIBUTION 02512-6 HIGH POINT ABC SECTION 02516 - DISINFECTION OF WATER DISTRIBUTION PART 1- GENERAL rat 12 13 SUMMARY: A. Section includes disinfection of potable water distribution system; and testing and reporting results, B. Related Sections: 1. Section 02512 - Site Water Distribution. REFERENCES: A. AWWA (American Waterworks Association) B300 - Standard for Hypochiorites. B. AWWA (American Waterworks Association) B30I - Standard for Liquid Chlorine. C. AWWA (American Waterworks Association) C651 - Standards for Disinfecting Water Mains. SUBMITTALS: ‘A. Test Reports: Indicate results comparative to specified requirements B. Procedures, Chemicals, and Treatment Levels: Submit procedures, proposed chemicals, and treatment levels for review. Certificate: Certify that cleanliness of water distribution system meets or exceeds City of High Point requirements. CLOSEOUT SUBMITTALS: ‘A. Disinfection Report: ‘Type and form of disinfectant used. Date and time of disinfectant injection start and time of completion. Test locations. [Name of person collecting samples. Initial and 24 hour disinfectant residuals (quantity in treated water) in ppm for each, outlet tested. Date and time of flushing start and completion. Disinfectant residual after flushing in ppm for each outlet tested. peeps B. Bacteriological Report 1. Date issued, project name, and testing laboratory name, address, and telephone number. 2, Time and date of water sample collection. DISINFECTION OF WATER DISTRIBUTION 2516-1 HIGH POINT ABC ‘Name of person collecting samples. ‘Test locations. Initial and 24 hour disinfectant residuals in ppm for each outlet tested. Coliform bacteria test results for each outlet tested. Certification that water conforms, or fails to conform, to bacterial standards of the City of High Point, 1.5 QUALITY ASSURANCE: A. Perform Work in accordance with AWWA C651. B, Water Treatment Firm: Company specializing in disinfecting potable water systems specified in this Section with minimum three years documented experience. C. Testing Firm: Company specializing in testing potable water systems, certified by the State of North Carolina. D, Submit bacteriologist’s signature and authority associated with te PART 2 - PRODUCTS: 2.1. DISINFECTION CHEMICALS: A. Chemicals: AWWA B300, Hypochlorite or AWWA B301, Liquid Chlorine. PART 3 -EXECUTION: 3.1 EXAMINATION: ‘A. Verify that piping system has been cleaned, inspected, and pressure tested. B, Perform scheduling and disinfecting activity with start-up, water pressure testing, adjusting and balancing, demonstration procedures, including coordination with related systems. 3.2. EXECUTION: Provide and attach required equipment to perform the Work of this Section. Introduce treatment into piping system. ‘Maintain disinfectant in system for 24 hours. pop > Flush, circulate, and clean until required cleanliness is achieved; use municipal domestic water. E. _ Replace permanent system devices removed for disinfection, F. Pressure test system to 150 psi. Repair leaks and re-test, DISINFECTION OF WATER DISTRIBUTION 02516 -2 HIGH POINT ABC 10. ‘After completion of the pipeline installation, including backfill, bt prior to final connection to the existing system, conduct, in the presence of the Architect, concutrent hydrostatic pressure and leakage tests in accordance with AWWA C600. Provide all equipment required to perform the leakage and hydrostatic pressure tests, The test pressure shall be not less than 150 psi or 50 psi in excess of maximum static pressure, whichever is greater. ‘The hydrostatic test shall be at least a two-hour duration, No pipeline installation will be approved ifthe pressure varies by more than 5 psi during the duration of the hydrostatic pressure test. Before applying the test pressure, air shall be expelled completely from the section of piping under test. Corporation cocks shall be installed so thatthe air can be expelled as the pipeline is being filled with water. After all the air has been expelled, the ‘corporation cocks shall be closed and the test pressure applied. At the conclusion of the tests, the corporation cocks shall be removed and plugged. Slowly bring the piping tothe test pressure and allow the system to stabilize prior to conducting the leakage test. ‘Valves shall not be operated in either the opening or closing direction at differential pressures above the rated pressure. Alll exposed piping, fittings, valves, hydrants, and joints shall be examined carefully during the hydrostatic pressure test. Any damage or defective pipe, fittings, valves, hhydrants, or joints that are discovered following the pressure test shall be repaired or replaced with sound material at no cost to the Owner, and test shall be repeated to the satisfaction of the Architect. No pipeline installation will be approved if the leakage is greater than that determined by the following formula: L spv--P 133,200 L = theallowable, in gallons pec hour S = the length of pipe tested, in inches D = the nominal diameter ofthe pipe, in inches P = the average test pressure during the leakage test, in pounds per square inch (gauge) If leakage exceeds the rate as determined in Paragraph 9 above, locate the source and ‘make repairs as necessary tothe satisfaction of the Architect. 3.3. FIELD QUALITY CONTROL: A. Disinfection, Flushing, and Sampling: L 2 Disinfect the pipeline installation in accordance with AWWA C651, except that liquid chlorine shall not be used. Upon completion of the retention period required for disinfection, flush the pipeline ‘until the chlorine concentration of water leaving the pipeline is no higher than that generally prevailing in the existing system or is acceptable for domestic use. Dispose of the chlorinated water in conformance with all Federal, State and ‘Municipal laws, ordinances, rules, and regulations. If there is any possibility that the DISINFECTION OF WATER DISTRIBUTION 02516 -3, HIGH POINT ABC chlorinated discharge will cause damage to the environment, then a neutralizing chemical shall be applied to the chlorinated water to neutralize thoroughly the chlorine residual remaining in the water. 4, After final flushing and before the pipeline is connected to the existing system, ot placed in service, the Contractor shall employ an approved independent testing laboratory to sample, test and certify the water for conformance with the purity standards of the City of High Point, the United States Environmental Protection ‘Agency, and the Federal Clean Water Act Health Standards. The Architect shall be furnished with a copy of such certification by the testing laboratory, and no installation will be approved without such certification, END OF SECTION 02516 DISINFECTION OF WATER DISTRIBUTION 02516 -4 HIGH POINT ABC SECTION 02539 - SANITARY SEWAGE SYSTEMS. PART 1- GENERAL: rat 12 13 14 15 17 SUMMARY: ‘A. Section includes sanitary sewerage drainage piping, fittings, accessories and bedding; connection of building sanitary drainage system to existing on-site sewers; and manholes. B. Related Sections 1. Section 02300 - Earthwork: Excavating subsoil for sewer system piping and backfilling around manhole structures. REFERENCES: A. ASTM DIS57- Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10 Tb Rammer and 18 inch Drop. DEFINITIONS: ‘A. Bedding: Fill placed under, beside and directly over pipe, prior to subsequent backfill operations. B. PVC: Polyvinyl Chloride. SUBMITTALS: A. Product Data: Submit data indicating pipe, pipe accessories, and manhole shaft and covers. B, — Manufacturer’s Installation Instructions: Indicate sp Products specified. procedures required to install C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. CLOSEOUT SUBMITTALS: A. Project Record Documents: Record location of pipe runs, connections, manholes, and invert elevations. B. Identify and describe unexpected variations to subsoil conditions or discovery of uncharted utilities, FIELD MEASUREMENTS: ‘A. Verify that field measurements and elevations are as indicated, COORDINATION: SANITARY SEWAGE SYSTEMS 02539-1 HIGH POINT ABC A. Coordinate the Work with termination of sanitary sewer connection outside building Existing Facilities shall remain in operation. Verify locations of existing building services and maintain service during the life of the project. Reconnect existing services to new lines as required to maintain service. PART 2-PRODUCTS: 21 22 23 24 SEWER PIPE MATERIALS: ‘A. PVC Sewer Pipe and Fittings, NPS 15 and Smaller: ASTM D 3034, SDR 35, for solvent- cemented or gasketed joints, 1. Gaskets: ASTM F 477, elastomeric seals. PIPE ACCESSORIES: A. Fittings: Same material as pipe molded or formed to suit pipe size and end design, in required tee, bends, elbows, cleanout, reducers, traps and other configurations required. BEDDING MATERIALS: A, Bedding: Satisfactory soil materials specified in Section 02300. CLEANOUTS: A. PVC Cleanouts: PVC body with PVC threaded plug. Include PVC sewer pipe fitting and riser to cleanout of same material as sewer piping. PART3 - EXECUTION: 34 32 33 EXAMINATION: A. Verify that trench cut and excavation base is ready to receive work and excavations, dimensions, and elevations are as indicated on drawings. PREPARATION: A. Correct over excavation with satisfactory soil material as specified in section 02300, B. Remove large stones or other hard matter which could damage pipe or impede consistent backfilling or compaction. BEDDING: ‘A. Excavate pipe trench in accordance with Section 02300 for Work of this Section. Hand trim excavation for accurate placement of pipe to elevations indicated, B. Place bedding material at trench bottom, level materials in continuous layer not exceeding 6 inches compacted depth, compact to 95 percent minimum Standard Proctor. SANITARY SEWAGE SYSTEMS 02539-2 HIGH POINT ABC C. Maintain optimum moisture content of bedding material to attain required compaction density. 3.4 INSTALLATION — PIPE: ‘A. Install pve pipe, fittings, and accessories in accordance with AWWA 2. Seal joints watertight. B. Lay pipe to slope gradients noted on drawings; with maximum variation from true slope of 1/8 inch in 10 feet. Install bedding at sides and over top of pipe to minimum compacted thickness of 12 inches; compacted to 95 percent. D. Refer to Section 02300 for trenching requirements. Do not displace or damage pipe when compacting. 3.5 INSTALLATION ~ CLEANOUTS: A. Install cleanouts and riser extension from sewer pipe to cleanout at grade. Install piping so cleanouts open in direction of flow in sewer pipe. B. Set cleanout frames and covers in earth in cast-in-place concrete block, 18 by 18 by 12, inches deep. Set with tops 1 inch above surrounding grade, C. Setcleanout frames and covers in concrete pavement with tops flush with pavement surface. 3.6 FIELD QUALITY CONTROL: ‘A. Request inspection prior to and immediately after placing bedding, B. Compaction testing will be performed in accordance with Section 02300. C. IP tests indicate Work does not meet specified requirements, remove Work, replace and retest at no cost to Owner. 3.7 PROTECTION OF FINISHED INSTALLATION: ‘A. Protect pipe and aggregate cover from damage or displacement until backfilling operation is in progress. 3.8 SCHEDULE: A. Refer to Site Plan Drawing for location, type, and size of sanitary sewerage systems. END OF SECTION 02539 SANITARY SEWAGE SYSTEMS 02539-3 HIGH POINT ABC SECTION 02630 - STORM DRAINAGE SYSTEMS PART 1 ~ GENERAL ra 12 13 14 ‘SUMMARY: This Section includes storm drainage $ feet outside the building line. Systems include the following: 1. Storm drainage. Related Sections include the following: 1, Section 02115- Soil Erosion and Sediment Control 2. Section 02300- Earthwork DEFINITIONS: RCP: Reinforced concrete pipe. PVC: Polyvinyl chloride pipe. SUBMITTALS: Product Data: For the following: 1, Reinforced concrete pipe and fittings. 2. PVC Plastic Pipe and fittings. Shop Drawings: Include plans, elevations, details, and attachments for the following: 1, Precast concrete manholes and other structures, including frames, covers, and grates. 2, Frames, covers, and grates for cast-in-place manholes and other structures. Field Test Reports: Indicate and interpret test results for compliance with performance requirements, DELIVERY, STORAGE, AND HANDLING: Protect pipe, pipe fittings, and seals from dirt and damage. Handle precast concrete manholes and other structures according to manufacturer's written rigging instructions. STORM DRAINAGE SYSTEMS 02630-1 HIGH POINT ABC 15 A B. c PROJECT CONDITIONS: Site Information: Perform site survey, research public utility records, and verify existing utility locations. ‘Locate existing structures and piping to be closed and abandoned. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1, Notify Architect not less than two days in advance of proposed utility interruptions, 2. Do not proceed with utility interruptions without Architect's written permission. PART 2- PRODUCTS 21 A B. 22 A 23 A PIPES AND FITTINGS: Reinforced-Conerete Sewer Pipe and Fittings (15 inch diameter and larger): ASTM C76, Class II, Wall B, for gasketed joints. 1. Gaskets: ASTM C443, rubber. Polyvinyl Chloride Pipe and Fittings: ASTM D-1785 Schedule 80, 1, Joints: ASTM D-2467 SPECIAL PIPE COUPLINGS AND FITTINGS: Sleeve-Type Pipe Couplings: ASTM C 1173, rubber or elastomeric sleeve and band assembly fabricated to mate with OD of pipes to be joined, for nonpressure joints. 1, Sleeve Material for Concrete Pipe: ASTM C 443, rubber. 2, Sleeve Material for Cast-Iron Soil Pipe: ASTM C 564, rubber. 3. Sleeve Material for Plastic Pipe: ASTM F 477, elastomeric seal. 4. Sleeve Material for Dissimilar Pipe: Compatible with pipe materials being joined. CATCH BASINS: Construct catch basins as indicated. 1. Frames and Grates: ASTM A 48, Class 30 minimum, gray-iron casting, 2. Steps: Manufactured from deformed, 1/2-ineh steel reinforcement rod complying with ASTM A 615/A 615M and encased in polypropylene complying with ASTM D 4101. Include pattem designed to prevent lateral slippage off step. Cast or anchor into sidewalls with steps at 12- to 16-inch intervals. ‘STORM DRAINAGE SYSTEMS 026302 HIGH POINT ABC 24 A B c 25 A ‘CONCRETE: General: Cast-in-place concrete according to ACI 318, ACI 350R, and the following: Cement: ASTM C 150, Type IL. Fine Aggregate: ASTM C 33, sand. Coarse Aggregate: ASTM C 33, crushed gravel. Water: Potable. Pepe Portland Cement Design Mix: 3000 psi minimum, with 0.45 maximum water-cementitious ratio. 1. Reinforcement Fabric: ASTM A 185, steel, welded wire fabric, plain. 2. Reinforcement Bars: ASTM A 615/A 615M, Grade 60, deformed steel. Structure Channels and Benches: Factory or field formed from concrete. Portland cement design mix, 4000 psi minimum, with 0.45 maximum water-cementitious ratio. CLEANOUT! ASME A112.36.2M, round, cast-iron housing with clamping device and round, secured, scoriated cast-iron cover. Include cast-iron ferrule with inside caulk or spigot connection and ‘countersunk, tapeted-thread, brass closure plug, PART 3 ~ EXECUTION 3 A 32 A B D. EARTHWORK: Excavating, trenching, and backfilling are specified in Section 02300 "Earthwork." INSTALLATION, GENERAL: General Locations and Arrangements: Drawing plans and details indicate general location and arrangement of underground storm drainage piping. Location and arrangement of piping layout take design considerations into account. Install piping as indicated, to extent practical Install piping beginning at low point, rue to grades and alignment indicated with unbroken continuity of invert. Place bell ends of piping facing upstream. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions for use of lubricants, cements, and other installation requirements. Maintain swab o drag in line, and pull past each joint as, it is completed. Use junction boxes for changes in direction, unless otherwise indicated. Use fittings for ‘branch connections, unless direct tap into existing sewer is indicated. Use proper size increasers, reducers, and couplings where different sizes ot materials of pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited, STORM DRAINAGE SYSTEMS 026303 HIGH POINT ABC E. 33 34 35 36 Install gravity-flow piping and connect to building's storm drains, of sizes and in locations indicated. Terminate piping as indicated, 1, Install piping pitched down in direction of flow, at minimum slope of 1 percent, unless otherwise indicated, 2. Install piping with 18-inch minimum cover. ‘Tunneling: Install pipe under streets or other obstructions that cannot be disturbed by tunneling, jacking, or a combination of both. PIPE JOINT CONSTRUCTION AND INSTALLATION: General: Join and install pipe and fittings according to installations indicated, Install with top surfaces of components, except piping, flush with finished surface. Concrete Pipe and Fittings: Install according to ACPA's "Concrete Pipe Installation Manual.” ‘Use the following sea 1, Round Pipe and Fittings: ASTM C 443, rubber gaskets, PVC Pipe and Fittings: As follows: 1. Join pipe, tubing, and fittings with couplings according to manufacturer's written 2. Insal cordng to ASTMCD 221 and manicures writen nsttions. Join piping made of different materials or dimensions with couplings made for this application. Use couplings that are compatible with and that fit both systems’ materials and dimensions. CATCH-BASIN INSTALLATION: Construct catch basins to sizes and shapes indicated, Set frames and grates to elevations indicated. CONCRETE PLACEMENT: Place cast-in-place concrete according to ACI318 and ACI 350R. FIELD QUALITY CONTROL: Clear interior of piping and structures of dirt and superftuous material as work progresses. Maintain swab or drag in piping, and pull past each joint as itis completed 1, Inarge, accessible piping, brushes and brooms may be used for cleaning. ‘STORM DRAINAGE SYSTEMS 026304 HIGH POINT ABC Place plug in end of incomplete piping at end of day and when work stops. Flush piping between structures to remove collected debris, if required by authorities having jurisdiction, B. Inspect interior of piping to determine whether line displacement or other damage has occurred. Inspect after approximately 24 inches of backfill is in place, and again at completion of Project. L 2. 3. 4 Submit separate reports for each system inspection. Defects requiting correction include the following 4 Alignment: Less than full diameter of inside of pipe is visible between structures. Crushed, broken, cracked, or otherwise damaged piping Infiltration: Water leakage into piping. Exfiltraion: Water leakage from or around piping aes Replace defective piping using new materials, and repeat inspections until defects are within allowances specified. Reinspect and repeat procedure until results are satisfactory. C. Test new piping systems, and parts of existing systems that have been altered, extended, or repaired, for leaks and defects. 1 Do not enclose, cover, or put into service before inspection and approval, 2, Test completed piping systems according to authorities having jurisdiction. 3. Schedule tests and inspections by authorities having jurisdiction with at least 24 hours’ advance notice. 4, Submit separate reports for each test. 3, Leaks and loss in test pressure constitute defects that must be repaired. 6. Replace leaking piping using new materials, and repeat testing until leakage is within allowances specified. END OF SECTION 02630 ‘STORM DRAINAGE SYSTEMS 02630-5 HIGH POINT ABC SECTION 02745 - ASPHALTIC CONCRETE PAVING PART | - GENERAL, 1 12 13 SUMMARY ‘This Section includes the following: 1. Hot-mix asphalt paving. 2. Pavement-marking paint. Related Sections include the following: 1. Section 02300 "arthworl'" for subgrade preparation, 2. Section 02753 "Portland Cement Concrete Pavement " for sidewalks and concrete cur and gutter. SYSTEM DESCRIPTION Provide hot-mix asphalt pavement according to the materials, workmanship, and other applicable requirements of the standard specifications of the State of North Carolina, 1. Standard Specification: North Carolina Department of Transportation “Standard ‘Specifications for Roads and Structures”, latest edition. 2. Measurement and payment provisions and safety program submittals included in standard specifications do not apply to this Section SUBMITTALS Product Data: For each product specified. Include technical data and tested physical and performance properties. Job-Mix Designs: Certification, by authorities having jurisdiction, of approval of each job mix proposed for the Work. Qualification Data: For firms and persons specified in the "Quality Assurance” Article to demonstrate their capabilities and experience. Include lists of completed projects with project, names and addresses, names and addresses of architects and owners, and other information specified. Material Test Reports: Indicate and interpret test results for compliance of materials with requirements indicated. Material Certificates: Certificates signed by manufacturers certifying that each material ASPHALTIC CONCRETE PAVING 7745-1 HIGH POINT ABC 14 15 16 complies with requirements, QUALITY ASSURANCE, Installer Qualifications: Engage an experienced installer who has completed hot-mix asphalt paving similar in material, design, and extent to that indicated for this Project and with a record of successful in-service performance. Manufacturer Qualifications: Engage a firm experienced in manufacturing hot-mix asphalt similar to that indicated for this Project and with a record of successful in-service performance. 1, Firm shall be a registered and approved paving mix manufacturer with the North Carolina DOT. Asphalt-Paving Publication: Comply with Al's "The Asphalt Handbook," except where more stringent requirements are indicated. Preinstallation Conference: Conduct conference at Project site to comply with requirements of Division 1 Section "Project Meetings" Review methods and procedures related to asphalt paving including, but not limited to, the following: 1. Review proposed sources of paving materials, including capabilities and location of plant that will manufacture hot-mix asphalt. 2. Review condition of substrate and preparatory work performed by other trades. 3. Review requirements for protecting paving work, including restriction of traffic during installation period and for remainder of construction period. 4, Review and finalize construction schedule for paving and related work. Verify availability of materials, paving Installer's personnel, and equipment required to execute the Work without delays. 5. Review inspection and testing requirements, governing regulations, and proposed installation procedures. 6. Review forecasted weather conditions and procedures for coping with unfavorable conditions. DELIVERY, STORAGE, AND HANDLING Deliver pavement-marking materials to Project site in original packages with seals unbroken and bearing manufacturer's labels containing brand name and type of material, date of ‘manufacture, and directions for storage. Store pavement-marking materials in a clean, dry, protected location and within temperature range required by manufacturer. Protect stored materials from direct sunlight. PROJECT CONDITIONS Environmental Limitations: Do not apply asphalt materials if substrate is wet or excessively