CPM Example

Steps to Determine CPM


- Build the Network (AON)
-Put in all precedence relationships
- Calculate each Activities EST, LST,
EFT, LFT
-Work forward and backward
- Determine slack times
- Determine Critical Path
-Activities with no slack are critical
Example
Activity Predecessors Duration
a --- 5
b --- 4
c a 3
d a 4
e a 6
f b,c 4
g d 5
h d,e 6
i f 6
j g,h 4
Calculate EST/EFT
- Go thru chains to see where
longest - use EFT
-a d g j = 18
-a e h j = 21
-a d h j = 19
-a c f i = 18
-b f i = 18
- 21 days is longest chain a e h j
Calculate LST / LFT
- Work backwards from 21 days on
each activity
Calculate Slack
- Slack = LST - EST or LFT - EFT
- Critical activities - slack = 0
#esult
Activity LST - EST LFT - EFT
a 0 0
b 7 7
c 3 3
d 2 2
e 0 0
f 3 3
g 3 3
h 0 0
i 3 3
j 0 0