NAME STUDENT No. TUTORIAL 10 Q1: Learning Curve TUTORIAL GROUP

1) A well-known oil company is re-imaging all 450 of its retail outlets in Australia using 10 building crews across the country. Each crew will have an equal number of sites to complete. Past experience has indicated that mobile building crews have a learning rate of 0.88, with no single petrol station being completed in less than 14 days. A first trial site for each crew averaged 22 days to complete. a) How long can the project manager expect each crew to take in order to complete their quota of sites? b) Show all your calculations that support your answer to a). Round all your figures to 2 decimal places.