WORKS CENTRE MACHINES BACKLOG HRS CAPACITY PER DAY BACKLOG DAYS
HOLDING/DISPATCH AREA
36
15
1.5
QC INSPECTION
40
20
1.67
STRIPPING AREA
24
10
MACHINING
38
20
1.9
NDT
44
10
1.84
SPRAY BOOTH
20
21
0.84
SANDBLAST
SANDBLASTING
60
2.5
WELDING
WELDING
10
0.42
VALVE SHOP
12
16
0.5
OUTSOURCED SERVICES
24
20
WEEK 5
26-31 Jan 09
HOLDING/DISPATCH AREA
36
15
1.5
QC INSPECTION
40
20
1.67
STRIPPING AREA
24
10
MACHINING
38
20
1.9
NDT
44
10
1.84
SPRAY BOOTH
20
21
0.84
SANDBLAST
SANDBLASTING
60
2.5
WELDING
WELDING
10
0.42
VALVE SHOP
12
16
0.5
OUTSOURCED SERVICES
24
20
WEEK 5
26-31 Jan 09