PARVEEN

Well Test Equipment

LAYOUT FOR TESTING GAS CONDENSATE OR OIL WELLS

Burner Manifold Burner Manifold Air Water to Smoke Suppressor Gas Water Separator Burner Oil SSV Actuator Pressure Surface Safety Valves Flowline Manifold* Water Header Pump Surface Test Tree Manifold Tuning Head Swivel Water to Heat Shield Gas Air Water to Smoke Suppressor

Oil

Burner

Water to Heat Shield

Choke Manifold

OBJECTIVES OF WELL TEST OPERATIONS


Following important data & samples to be obtained from well test : Gas production rate in MMSCF/D. Oil or Condensate production rate in barrels per day. B&W percentage of crude. Gravities of oil , gas & water Salinity of water with further compositional analysis if possible. Viscosity of condensate or crude. Pourpoint of condensate or crude, determined from fresh wellhead samples. Rough wellhead composition of produced gas, including H2S,CO2, CO&N2 content. Bottom hole pressures, build-ups and draw-downs. Bottom hole temperature. Accurate recording of surface pressures, temperatures and flow data versus time. Separator gas samples, Oil samples , under pressure Bottom hole PVT samples.

! ! ! ! ! ! ! ! ! ! ! ! !

Above introductory figure shows typical well testing layout for a very complete set of equipment. The equipment requirements and design for successful well testing obviously vary according to the specific requirement of operators.

PARVEEN

Well Test Equipment

MODEL ANSHOO BURNER WITH 60/75/90 BOOM

Capacity : Features :

12000 BOPD Designed to dispose off crude oil /diesel, pollution free Pilot ignition system for each burner head. Consist of Atomizers for multistage automization. Specially designed nozzle and high velocity of effluent gives flame narrow shape , resulting in reducing heat radiation. Flow rates up to 12,000 STBD at any water percentage. Swivel provided in structure allows a rotation in 30 each side of boom axis. Total length of boom available : 60' - 75' - 90' in 2 - 3 sections Booms comprises of : Oil line 3 SCH 80 Gas line 4' / 5 SCH 80 Air 2 SCH 40 Water line 3 SCH 40 Diesel line 1.50 SCH 40 Relief Line 4 SCH 40 Propane line SCH 40 Electric cable Material of construction : Suitable for H2S Service asper NACE MR-01-75

PARVEEN

Well Test Equipment

GAUGE TANK / SURGE TANK

Gauge Tank Capacity : 100 BBL ( Twin Compartment) Features : Supplied with Centrifugal pump with electric driven motor (chemical proof) w/ HP Flame proof console. Complete with piping, flanges, valves , instrumentation & union Connections.

Surge Tank Capacity : 100 BBL (Twin Compartments) Features : Design pressure : 150 PSI / W.P. : 50 PSI Magnetic level controllers with High/Low level alarm. Complete with piping, flanges, valves, instrumentation & union connections With automatic control valve to control pressure in tank up to 50 psi. Supplied with Centrifugal pump with electric driven motor (chemical proof) w/ HP Flame proof console.

PARVEEN

Well Test Equipment

MANIFOLDS / UNITIZED WELL CONTROL HEAD / DATA HEADER


3.1/8 x 5000 PSI CWP - 3.1/16 X 100000 PSI CWP Construction : Skid mounted suitable for H2S Service asper NACE MR-01-75. Complete with 4-5 Gate Valves / Adjustable & Positive Chokes, 3 Thru bore. With provision for measuring pressure, temperature & sampling both Upstream & Downstream of chokes.
Choke Manifold

2.1/16 x 5000 PSI CWP - 3.1/8X 5000 - 3.1/16 -10000 PSI CWP Construction : Skid mounted suitable for H2S Service asper NACE MR-01-75. Complete with 8 Gate Valves / Adjustable & Positive Chokes, 2 / 3 Thru bore. Orientation of Gate Valves, Chokes asper customer requirement. With provision for measuring pressure, temperature & sampling both Upstream & Downstream of chokes.
Eruption Manifold

3.1/16 x 10000 PSI CWP Construction : Skid mounted - Unitized type. Suitable for H2S Service asper NACE MR - 01- 75. Complete with two side outlets one for connection to Kill line & other for production testing.

2 /3 /4 5000 PSI & 10000 PSI WP 3 to 8 Length Material :


Utilized Well Control Head

Suitable for H2S Service asper NACE MR-01-75. With Union / Gray Lock End Connections. Supplied with multiple ports Plugged or Flanged at specified intervals and degrees.

Data Header

Supplied with Thermowell , Pressure Gauges as required by customer.