Professional Documents
Culture Documents
Project Variability
Project Variability
PERT
PERT requires three time estimates for each of the activities in the project
An Optimistic Time Estimate To A Most Likely Time Estimate Tm A Pessimistic Time Estimate Tp Then the Mean Time or Expected Time can be calculated as:
PERT
When Expected Time for each of the activities is completed, we need to calculate the
Variance of Each of the Activities and Standard Deviation of the Project
Variance is calculated as
Activity Variance
2
2 (i )
PERT
Standard Deviation of the Project is calculated as
Lastly, we calculate the probability of completion of the project in said time (Ts) by calculating Z value from Z Score table