Draw the network diagram and calculate EST,LST,EFT,LFT & FLOAT.Mark the critical path and find total project duratio
10 10
3
4 0 0
1 1v
15 15
18
18
6
12
Activity Duration
( a) A 4
EST
LST
EFT
LFT
Total Cost
Free Float
Independent Float
(b) 0
(c-a) 0
(a+b) 4
(c) 4 0 0 0
B C D E
6 5 4 3
4 10 4 8
4 10 8 12
10 15 8 11
10 15 12 15
0 0 4 4
0 0 0 4
0 0 0 0
15
15
18
18
FORMULAE:
LST
TOTAL FLOAT
FREE FLOAT
Free Float = EST of tail event EST of head event activity duration
INDEPENDENT FLOAT
INDEPENDENT FLOAT= EST of tail (succeeding)event - LFT of head (preceeding)event activity duration