PROJECT Date :
Conversation between
: : : PHONE
Time: 3:00PM
Instruction to retain the rooms at GL 6/J'-K' from Levels 4-12 Hotel Tower as Typical King (as confirmed by Ria Bonilla of SP - refer to attachment) instead of categorizing the unit as King Shearwall as shown in PMI 58. DCII instructed DMCI to revised For Construction drawings based on the attached drawing.
NO
NO
YES
YES
To be provided To be provided
This form is issued as a formal notification of an event which may form as a basis of possible claim of additional cost or an extension of time or both. Notwithstanding dissention to above instruction within 48 hours, above is considered confirmed.
Signed for and on behalf of D.M. CONSUNJI, INC. > Confirmed;
Authorized Representative