Reference No.

PROJECT Date :

DMCI-SOLR-CP3-CVI-AR-008 March 22, 2012

CONFIRMATION OF VERBAL INSTRUCTION (CVI)


To : Attention : Project : DCII Gail Manalastas/ Graeme Noble Entertainment City Project : NAME Conrado Lizano Lady Roxanne Mogol COMPANY DCII DMCI

Conversation between

Date Thru Details

: : : PHONE

March 23, 2012 VERBAL OTHERS

Time: 3:00PM

Instruction to retain the rooms at GL 6/J'-K' from Levels 4-12 Hotel Tower as Typical King (as confirmed by Ria Bonilla of SP - refer to attachment) instead of categorizing the unit as King Shearwall as shown in PMI 58. DCII instructed DMCI to revised For Construction drawings based on the attached drawing.

Cost Impact : Time Impact :

NO
NO

YES
YES

Amount: No. of Days:

To be provided To be provided

This form is issued as a formal notification of an event which may form as a basis of possible claim of additional cost or an extension of time or both. Notwithstanding dissention to above instruction within 48 hours, above is considered confirmed.
Signed for and on behalf of D.M. CONSUNJI, INC. > Confirmed;

Alfredo Juan J. De Villa DMCI Representative

Authorized Representative

OP-C-066-0 D.M Consunji, Inc.