WATER Water for industrial purpose can be obtained from one of two general sources which is the plants

own source and municipal supply. In our plant, water is supply from Semambu Water Treatment Plant. The table below shows the consumption of water used by our plant. Equipment Condenser 1 Condenser 2 Condenser 3 Heat Exchanger (H-01) Heat Exchanger (H-04) Heat Exchanger (H-05) Heat Exchanger (H-06) Heat Exchanger (H-07) Boiler (Feed Water) Total Mass of water, kg/hr 13,809.98 16,019.85 260.26 91,360.80 10,947.60 22,233.60 7,153.20 8,932.68 10,896.70 181,614.67

Boiler Feed Water

Using the ideal gas law V= nRT/P n=moles of water R=constant T=temperature P=Pressure T P = 293.15K =101325 Pa