TOPICS STUDIED IN OPERATION MANAGEMENT

Fishbone diagram Process flow chart Line balancing 5s Inventory management Supply chain management Layout design

PROJECT- IMPROVE PRODUCTIVITY AND EFFICIENCY BY LINE BALANCING


Existing method- Problems

Target setting and the way the balancing has done Cycle time is less than time taken in work stations Balancing has done by considering labour only not time Balancing has done by considering efficiency at 65% No proper process flow chart No calculation of cycle time, minimum no of workstations, line efficiency ,percentage of idle time

PROCESS FLOW FOR LINE BALANCING

First step is to calculate cycle time, minimum no of

workstations.

Then is to prepare process flow chart of each operation by considering immediate follower.

Then assign operations to each workstation by


considering time, machine type and the follower operations.

Finally calculate idle time percentage and line efficiency.

Line balancing layout format


S. NO No. of operator Details about the workstation M/C Type SAM

EXAMPLE PRIMARK GEORGETTE BLOUSE


Process flow chart and line balancing layout has attached as a word document.
Factors Tailor Helper Ironer Checker Existing method 66 6 5 2 New method 46 6 5 2

Cycle time
no of work stations Idle percentage time Line efficiency

.64
55 39% 61%

.64
48 20.55% 79.45%

Thank you