To send Proforma Invoice to Client, Hyderabad with Brief write-up of test equipment , (Suppler)

Confirm receipt of Proforma invoice to Shipper and apply for STPI approval ,(Importer)

Apply & Collect STPI certificate from STPI, Hyderabad 3 w-days

Shipment Clearance from the Supplier Bonded were House ,(Suppler)

Apply & Collect Procurement Certificate from CEX (by EGL) (2 w days)

Delivery of Consignment at Importer Premises, (Suppler)

IC & PC Original Certificates Hand Over to Supplier (or) Importer, (EGL)

Intimate to EGL

Intimate to the CEX Office for verification by EGL


Bond Register updating & Obtaining RWC from CEX, (EGL)

Handing over of Original RWC to Supplier or Import to submit with port, (EGL)

Sl # 1

Description Proforma Invoice

Timeline reference to To To-5

Estimated number of days 5 days ahead of shipment

2 3 4

STPI Approval Procurement Certificate IC & PC Hand over to Supplier or Importer

To-2 To-1 T0-0

3 Days 2 Days

Shipment Clearance from the supplier

To-as per PO

Delivery of premises

Consignment

at

importer

To-as per PO

Intimation to EGL

Verification by CEX Inspector

To-1

2 Day

Note:

Sl. Sl. Sl. Sl. Sl.

No. 1 is the responsibility of the Customer / Shipper. No. 2, 3 and 4 are responsibilities of the EGL. No. 5 and 6 is responsibility of Supplier. No 7 is responsibility of Customer. No. 8 is responsibility of EGL.