Professional Documents
Culture Documents
FM Recovery Process
FM Recovery Process
FM Mill
1
G
A
L
V
1. For recovery Batch number Reversal need to be done through MB1A 262 mvt . Y
2. Material transferring from for recovery material to constant material with the prime batch. MB1A
3. As per request Master Desk will increase the SCO qty 261
4. ZSCO will be created against the sco number which will send the material to vendor location and create a challan.
5. ZSCOGR will br created against the challan number and stock will transfer from vendor to SRCV.
6. Material will be trasfer to mill material with reqd qty through MB1B 309 mvt. 7
7. . MB1A/261 mvt GI need to be done for the order.
As per the above diagram with screen shot enclosed for the process.
RECOVERY PROCSS