VSIL

RCC AND PT . COST COMPARISION


PROJ-8.5MX8.5M GRID SLAB PANEL(8.5X8.5)M MATERIAL AREA SQM

72.25
PT 200

RCC SLAB THK.(MM) BEAM SIZE(MM) DROP SIZE(M) CONCRETE VOLM.(M3) SLAB STEEL(KG/SQM) POST. TEN.RATE(RS/SQM) ESTIMATE CONCRETE (M3) STEEL (KG) PT RATE CENTERING COST SLAB CYCLE STRENGTH RCC QUANTITY 21 2312 0 MORE 21 DAYS LESS 3.5X3.5X.450 21 32 250

3X3X0.4 16 12 500

RATE 3100 30 0

TOTAL 65100 69360 0

PT OUANTITY RATE 16 3300 867 30 72.25 500 LESS 7 DAYS MORE 134460 RS PTSLAB

TOTAL 52800 26010 36125

DIRECT OVERHEADS

INDIRECT OVERHEADS 114935 RS 1590.796 RS/SQM SAVING 270.2422 RS/SQM

RCC SLAB PT SLAB IS ECONOMICAL THAN RCC SLAB

1861.038 RS/SQM

SAVING SLAB AREA PER FLOOR TOTAL SAVING

Rs 270.2422 PER sqm 0 sqm Rs 0 FOR SLAB