Professional Documents
Culture Documents
13
INVENTORY MODEL
CONTENTS
13.0 Aims and Objectives 13.1 Introduction 13.2 Need of Inventory Control 13.3 Advantages of Material Controls 13.4 Essential Factors of Material Control 13.5 ABC Analysis Technique 13.6 Process of Inventory Control 13.7 Minimum Stock Level 13.8 Maximum Stock Level 13.9 Ordering Level or Re-order Level 13.10 Average Stock level 13.11 Danger Level 13.12 Let us Sum Up 13.13 Lesson-end Activities 13.14 Keywords 13.15 Questions for Discussion 13.16 Terminal Questions 13.17 Model Answers to Questions for Discussion 13.18 Suggested Readings
6. To Check National Wastage: Inventory control checks the wastage of nations resources such as raw minerals, ores, etc.
13. Regular Reporting System: The information regarding the stock position, materials quantity etc, should be available to management regularly.
and in case of quick moving material it is high. 10. Nature of Supply: If the supply is uncertain the maximum level should be as high as possible. 11. Economic Order Quantity (EOQ): Maximum level largely depends in economic order quantity, because unless otherwise contra indicated the economic order quantity decides the quantity ordered and hence decides the maximum level.
measure is to be taken so that the stock may not go below the minimum level. It is the point or level of stock which the material stock should never be allowed to reduce. It is generally a level below the minimum level. As soon as the stock of material reaches this point, urgent action is needed for replenishment of stock. Determination of Danger Level. This done as follows: Danger Level = Two days of normal consumption Re-order Quantity: The quantity which is ordered at re-order point is called re-order quantity. This is determined on the basis of minimum stock level and maximum stock level. This is normally used in notation of economic order quantity.
Example 2: From the following particulars, calculate: (a) Re-order Level (b) Minimum Level, (c) Maximum Level, (d) Average Level: Normal Usage 100 units per day Minimum Usage 60 units per day Maximum Usage 130 units per day Economic Order Quantity 5,000 units Re-order Period 25 to 30 days
Example 3: A manufacturer buys costing equipment from out side suppliers Rs. 30 per unit. Total annual needs are 800 units. The following data is available: Annual Return on Investment 10% Rent, Insurance etc. per unit per year Re. 1 Cost of Placing an order Rs. 100 Determine Economic Order Quantity.
Example 4: Fair Deal Limited uses Rs. 1,00,000 materials per year. The administration cost per purchase in Rs. 100 and the carrying cost is 20% of the average inventory. The company has a purchase policy on the basis of economic order quantity but has been offered a discount of 0.5% in the case of purchase five times per year. Advise the company whether it should accept new offer or not?
Example 5: A pharmaceutical factory consumes annually 6,000 kgms. of a chemical costing Rs. 5 per kgm. Placing each order costs Rs. 25 and the carrying cost is 6% per year per kgm. of average inventory. Find the Economic Order Quantity and the total inventory cost. The factory works for days in a year. If the procurement time is 15 days and safety stock 200 kgms., find the re-order point and maximum and average inventories levels. If the supplier offers a discount of 5% on the cost price for a single order of annual requirement, should the factory accept it?
Example 6: A trading company expects to sell 15,000 mixers during the coming year. The cost per mixer is Rs. 200. The cost of storing a mixer for 1 year is Rs. 5 and the ordering cost is Rs. 540 per order. Find the Economic Order Quantity. Would it be profitable to the company to accept a discount offer of 30% on a single order per year. The storing cost continuing to be Rs. 5 per mixer per year.
Example 7: A manufacturer requires 1,000 units of a raw material, per month. The ordering cost is Rs. 15 per order. The carrying cost in addition to Rs. 2 per unit, is estimated to be 15% of average inventory per unit per year. The purchase price of the raw material is Rs. 10 per unit. Find the Economic Lot Size and the total cost. The manufacturer is offered as 5% discount in purchase price for order for 2,000 units or more but less than 5,000 units. A further 2% discount is available for order of 5,000 or more units. Which of the three ways of purchase he should adopt?
On the basis of above analysis we find that the T.I.C. is minimum (Rs. 1,17,515) in second alternative. Hence the company should adopt this alternative.