Professional Documents
Culture Documents
1 DIANE J. HUMETEWA
United States Attorney
District of Arizona
2
ROBERT K. LU
3 Assistant U.S. Attorney
Two Renaissance Square
40 North Central Avenue, Suite 1200
4 Phoenix, Arizona 85004-4408
Telephone: (602) 514-7500
Facsimile: (602) 514-7760
5 E-Mail: robert.lu@usdoj.gov
7 DISTRICT OF ARIZONA
16
17 INTRODUCTION
18 1. This is a civil action brought by the United States, to recover treble damages
19 and civil penalties under the False Claims Act, as amended, 31 U.S.C. §§ 3729-3733, arising
20 from a fraud upon the United States Department of Interior (“Interior”) and the General
21 Services Administration (“GSA”) in connection with construction contracts for the Grand
22 Canyon National Park and the Lake Mead National Recreation Area.
23
24 JURISDICTION AND VENUE
25 2. The Court has jurisdiction over this matter pursuant to 28 U.S.C. § 1345 and its
1
PROGRAM BACKGROUND
2
4. Interior and GSA are agencies or departments of the United States. The
3
National Park Service (“NPS”) is an agency of Interior. The Grand Canyon National Park
4
(“GCNP”) and the Lake Mead National Recreational Area (“LMNRA”) are agencies under
5
the authority of the NPS.
6
5. Federal construction contracts, including those administered by Interior and
7
GSA, are subject to the “Miller Act,” 40 U.S.C. §§ 3131-3134, and the Federal Acquisition
8
Regulations (“FAR”), 48 C.F.R. Chapter 1, et seq. Both the Miller Act and FAR requires a
9
prime or general contractor to obtain performance and payment bonds (i.e., surety bonds) for
10
all federal construction contracts that exceed $100,000. This requirement is to ensure that in
11
the event of default by the general contractor, third parties or sub-contractors are protected.
12
6. In addition to the bonding requirements, general contractors working under
13
federal construction contracts are also required to provide certification of progress payments
14
to any subcontractors that they use. These progress payment certification forms are officially
15
known as Certification of Progress Payments Under Fixed-Price Construction Contracts, GS
16
form 2419 (hereafter, the “Progress Payment Forms”). A general contractor is required to
17
make these certifications in order to receive continuing contract payments under federal
18
construction contracts.
19
20
PARTIES
21
7. Pacific General, Inc. (PGI) was a construction management company with its
22
corporate office located at 26054 Acero Street, Mission Viejo, California. PGI entered into
23
construction contracts with various federal government agencies, including GSA, Interior,
24
GCNP and LMNRA. PGI obtained federal government construction contracts, and acted as
25
the general contractor, and hired local business entities as subcontractors to complete the
26
work while PGI managed the projects.
27
28 2
Case 2:09-cv-00809-SRB Document 1 Filed 04/17/2009 Page 3 of 10
1 to PGI varied in price and complexity, and the work was to be performed at both the North
2 and South rims of the GCNP, as well as the LMNRA. The projects included designing and
3 constructing buildings and facilities, making repairs to buildings, renovating old cabins,
4 rehabilitating campgrounds, and performing a variety of other miscellaneous services. As a
5 construction management company, PGI subcontracted with other business entities to
6 perform the actual construction work on the projects at the GCNP and LMNRA.
7 12. PGI continued to receive task orders for construction projects at the GCNP and
8 LMNRA through the early part of 2003.
9 13. As part of their scheme to defraud Interior in connection with the work
10 performed at the GCNP and LMNRA, defendant submitted, or caused to submitted, two
11 types of false claims to NPS for payment.
12 (a) In the first type, defendant submitted, or caused to be submitted, to
13 NPS false certifications of compliance with bonding requirements under FAR and the
14 Miller Act. These false certifications resulted in false charges to NPS for surety bond
15 payments when in fact the underlying projects were never bonded.
16 (b) In the second type, defendant submitted, or caused to be
17 submitted, false progress payment certification forms to NPS in which PGI falsely
18 certified the company had paid its subcontractors when in fact no such progress
19 payments had been made to the subcontractors.
20
A. False Certification Of Compliance With Bonding Requirements
21
14. In January 2002, PGI began experiencing financial difficulty, including issues
22
with its working capital, net worth, and cash flow. The situation became so severe that it was
23
difficult, if not nearly impossible, for PGI to obtain bonds. In fact, between 2002 and 2004,
24
PGI was not able to obtain any bonds because of concerns among industry underwriters
25
about PGI’s financials, cash flow, and backlog of incomplete and ongoing construction
26
projects.
27
28 4
Case 2:09-cv-00809-SRB Document 1 Filed 04/17/2009 Page 5 of 10
1 15. Defendant McFarland knew that the construction projects that PGI was
2 awarded under the Contract were required to comply with the bonding requirements as set
3 forth in FAR and the Miller Act because:
4 (a) The GSA notified PGI and defendant McFarland that all contracts for
5 GCNP and LMNRA had to be bonded;
6 (b) The PGI Operations Manual specifically set forth the requirements to
7 acquire payment and performance bonds on all government contracts;
8 (c) Defendant McFarland’s own personal bonding agent, Eric Lowey,
9 specifically informed him of the bonding requirements;
10 (d) The former Business Unit Manager of PGI, Kenneth Fischer, knew that
11 construction projects at GCNP awarded to PGI were required to be bonded and
12 Fischer explained the same to defendant McFarland about this bonding requirement;
13 and
14 (e) As noted in paragraph 10, above, the Contract itself required PGI to
15 obtain surety and performance bonds.
16 16. As the owner of PGI, defendant McFarland was required to sign Indemnity
17 Agreements in order to obtain surety bonds for government construction projects. As a result
18 of entering into these Indemnity Agreements, McFarland became personally liable for all
19 projects bonded by PGI.
20 17. Following an investigation by NPS in the summer of 2003 based on complaints
21 from PGI subcontractors that they were not being paid by PGI for work completed at the
22 GCNP and LMNRA, it was discovered that defendant, through PGI, submitted numerous
23 invoices on construction projects for payment to NPS that were not properly bonded. These
24 invoices falsely certified to NPS that each of the construction projects had been properly
25 bonded as required by FAR and the Miller Act. The following are examples of false bond
26 invoices submitted by defendant for the construction projects under the Contract:
27
28 5
Case 2:09-cv-00809-SRB Document 1 Filed 04/17/2009 Page 6 of 10
1 defraud the government. Defendant McFarland pled guilty to six counts of making false
2 statements in a scheme to fraudulently obtain funds via federal construction contracts.
3 (United States v. McFarland, et al., No. CR-07-731-PCT-NVW). Specifically, defendant
4 McFarland admitted that between November 2003 and January 2004, he fraudulently
5 obtained $348,652.99 from the government by falsely certifying that PGI was paying its
6 subcontractors for work on projects funded by federal construction contracts in the GCNP.
7
8 FIRST CAUSE OF ACTION
False Claims Act, 31 U.S.C. § 3729(a)(1)
9 (Submission, or Causing the Submission, of False Claims)
10
23. The United States repeats and realleges each allegation set forth above in
11
paragraphs 1 through 22 as if set forth fully herein.
12
24. By virtue of the acts described above, and in violation of 31 U.S.C. §§ 3729 -
13
3733, the defendant knowingly presented, or caused others to present, to an officer, employee
14
or agent of the United States, false or fraudulent claims to obtain payment or approval in
15
violation of the False Claims Act.
16
25. The United States paid the false or fraudulent claims because of the acts of the
17
defendant and, as a result, the United States has incurred damages in an amount to be proven
18
at trial.
19
26. Pursuant to the False Claims Act, 31 U.S.C. § 3729(a)(1), as amended, the
20
defendant are liable to the United States under the treble damage and civil penalty provisions
21
of the False Claims Act for a civil penalty of not less than $5,500 and not more than $11,000
22
for each of the false or fraudulent claims herein, plus three (3) times the amount of damages
23
which the United States has sustained because of the defendant’s actions.
24
25
26
27
28 8
Case 2:09-cv-00809-SRB Document 1 Filed 04/17/2009 Page 9 of 10
1 (d) that the United States be granted such other and further relief as the Court shall
2 deem just and proper.
3 Respectfully submitted this 17th day of April, 2009.
4 DIANE J. HUMETEWA
United States Attorney
5 District of Arizona
6 S/Robert K. Lu
7 ROBERT K. LU
Assistant U.S. Attorney
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28 10