Geothermal Foundation Design Proposal for 70 Fort York Boulevard

Deep Energy Incorporated

Background
1.

placeholder

Foundation Systems
Deep Foundations Shallow Foundations

Geothermal Systems
Horizontal Collectors Vertical Collectors

Design Objectives
1.

Design a structurally adequate foundation that supports building loads for the obtained site Incorporate a geothermal system within each foundation alternative that harnesses ground energy for use by the structures heating and cooling systems

2.

3.

Develop a weighting method to determine the optimal design alternative considering the triple bottom line

Scope of Work

Design at least three (3) foundation alternatives that satisfy requirements for the dissipation of structural loads with appropriate safety factors Design a geothermal energy system for each design alternative that can be contained within the foundation Recommend an alternative using a weighted triple bottom line approach

Complete progress reports and presentations to update client through project timeline, culminating with a final report following the completion of the above scope of work

Tasks and Approach


TASK 100 - Preliminary Engineering TASK 200 - Foundation Design Criteria TASK 300 - Preliminary Design TASK 400 - Evaluation of Design Alternatives

TASK 500 Selection of Design Alternative

Project Schedule