Guide
Getting Connected
A Checklist for Permitting and Plugging In
Your Skystream 3.7TM in the USA
Step 1: First Things First Many utilities have a simple interconnection agreement for small
self-generators. If they do not have one, a sample interconnection
application form is available at: www.skystreamenergy.com. You may
Interconnection: Working with your utility wish to offer this as a guide for them to develop an interconnection
agreement
Utility-connected installations can be set up either to use all power
on site, supplementing your electrical use with utility power as Interconnection agreements vary from each utility or co-op, but all
needed, or to feed excess production back onto the grid in a net will most likely require specific safety information about the wind
metered arrangement. Different connection standards and electrical generator and should outline the type of net-metering agreement
safety considerations apply to each option. you have with them. Southwest Windpower products that connect
to the grid are UL listed and comply with anti-islanding laws that
United States Federal law (specifically, the Public Utility Regulatory require the system to shut down in the even the electric grid goes
Policies Act of 1978, or PURPA) requires utilities to connect with and down. You may be the first person within your utility asking for an
purchase power from small wind energy systems. Many utilities offer interconnection agreement for small wind. It is advised that you work
“net metering,” allowing the excess energy from a small wind system at with your Southwest Windpower authorized dealer to ensure you
any given time to spin your meter backwards at full retail value for all have the support you need should questions arise.
energy produced. Your first step will be to contact your utility and ask
for an “interconnection agreement”. This is a contract with your utility Most utilities will require an on-site inspection at the completion of
to use their meter and allows you to run excess power into the grid. install. By developing your relationship with the utility early, you will
be ready at the time of install to “Flip the Switch.”
Contact the building permit agent in your town or county planning Publichearings and zoning meetings Disconnect
Switch
department to obtain any required forms to be filled out and to learn Environmental reviews
more about the local process, fees, and requirements for installing Drawing reviews
your Skystream. Various fees
Prepare detailed engineered site layout map and electrical drawings Your Southwest Windpower Authorized dealer can provide a founda-
Skystream provides
to show placement of your equipment. tion drawing and sound data. If a particular fee seems excessive or
electricity to home
inappropriate for your situation, find out the basis for the fee. You
Your Skystream will not need FAA lights as its total tower height is may be able to avoid it or have it reduced.
Interconnection: Process of connecting electrical generator to elec- Total System Height: The height from ground level to the tip of the
tric grid to transfer power generated. rotor at its highest point.
Inverter: Electronic device that allows direct current to be converted Tower Height: The height above grade of the fixed portion of the
to alternating current and appropriate voltage, phase and frequency wind turbine tower, excluding the wind turbine and rotor.
to feed into the utility grid.
Wind Turbine: A system that converts energy in the wind to electri-
Kilowatt Hour: Use of 1 kilowatt (1,000 Watts) for 1 hour, con- cal energy, comprised of a rotor, generator and tower.
suming 1 kWh of electricity. The average US household consumes
12,000 kWh per year.
Acknowledgements
This guide was developed by eFormative Options LLC on behalf of
Southwest Windpower. Thanks to the American Wind Energy Asso-
ciation, the Canadian Wind Energy Association, the New York State
Energy Research & Development Authority, Northwest Sustainable
Energy for Economic Development, and the California Energy Com-
mission for their previous guidance documents on permitting small
wind turbines.
Southwest Windpower dealer contact info Interstate Renewable Energy Council Interconnection Guide
www.irecusa.org/pdf/guide.pdf
Permit agent contact info Connecting to the Grid and Net Metering Tables
www.irecusa.org/connect/statebystate.html
Utility specialist contact info
Wind Powering America Small Wind Consumer’s Guide
www.eere.energy.gov/windandhydro/windpoweringamerica/
Other notes
small_wind.asp
Southwest Windpower
928-779-9463
www.skystreamenergy.com
1801 W. Route 66
Flagstaff, AZ 86001